GERC Reviews Extension Request For 30 MW Hybrid Project Amid Regulatory And Supply Chain Delays In Gujarat

Representational image. Credit: Canva

Imandra Solar Private Limited filed Petition No. 2462 of 2025 before the Gujarat Electricity Regulatory Commission (GERC), seeking an extension of 120 days to complete the construction and commissioning of the evacuation infrastructure for its 30 MW wind-solar hybrid power project at Jafrabad, Amreli, Gujarat. The petitioner also requested that the Gujarat Energy Transmission Corporation (GETCO) be directed not to revoke its connectivity or encash its bank guarantees until the work is completed.

The project was to be completed within 12 months of receiving Stage-II connectivity approval from GETCO, dated 12 March 2024. Hence, the commissioning deadline was 11 March 2025. However, Imandra Solar cited several unforeseen and uncontrollable events that caused delays. These included delays in obtaining banking regulation clarity under the Green Energy Open Access (GEOA) Rules, delivery delays of crucial equipment like circuit breakers and transformers due to global supply chain disruptions, and right-of-way (ROW) issues with local landowners and farmers. Additional procedural delays included late approvals under Sections 68 and 164 of the Electricity Act and material drawing revisions.

GETCO, in its response, argued that the petitioner was aware of the project timelines and requirements and that delays in procurement and land acquisition were foreseeable risks, not force majeure. It further stated that the bank guarantees could be encashed if the project commissioning was not completed in time. GETCO maintained that any extension had to be granted strictly by the Commission as per the Hybrid Tariff Order and not by GETCO.

The Commission noted that many of the petitioner’s claims, such as the banking regulation confusion and supply chain issues, were legitimate and had been documented with follow-ups to government authorities. The Commission also observed that significant progress had been made, including completion of over 98% of the transmission line and partial work on the generator PSS and bay infrastructure.

Imandra Solar agreed to bear long-term transmission charges for 10% of the project capacity until commissioning and emphasized its intent to fulfill obligations. After hearing both parties, the Commission recognized the merit in the petitioner’s request and the industry-wide impact of the challenges cited. A decision on the extension and related reliefs will be based on the final findings in the order.

 

  • Related Posts

    ib vogt And Airtrunk Launch Malaysia’s First 29.99 MW Solar VPPA For Data Center Under CGPP

    Renewable energy developer ib vogt and hyperscale data center company AirTrunk have officially started commercial operations of a 29.99 MWac solar power project in Malaysia. The project marks the country’s…

    EU Approves €2.5 Billion Modernisation Fund To Accelerate Clean Energy Projects Across 11 Member States

    The European Commission and the European Investment Bank have approved a new funding package worth €2.5 billion under the Modernisation Fund to support clean energy projects across the European Union.…

    Have You Seen?

    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    • July 4, 2026
    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    What Natural Gas’s Ascendancy Says About the US

    • July 4, 2026
    What Natural Gas’s Ascendancy Says About the US

    Oil Prices Little Changed as US-Iran Peace Efforts Hold

    • July 4, 2026
    Oil Prices Little Changed as US-Iran Peace Efforts Hold

    TotalEnergies Offers Millions of Barrels of Iraqi Crude to Asian Buyers

    • July 4, 2026
    TotalEnergies Offers Millions of Barrels of Iraqi Crude to Asian Buyers

    Americans Hit Road for July 4 Despite High Gasoline Prices

    • July 3, 2026
    Americans Hit Road for July 4 Despite High Gasoline Prices

    Oil Set for Fourth Straight Weekly Loss as Hormuz Flows Return

    • July 3, 2026
    Oil Set for Fourth Straight Weekly Loss as Hormuz Flows Return

    India Denies Directly Exporting Fuel to Russia, But Admits Traders May Be

    • July 3, 2026
    India Denies Directly Exporting Fuel to Russia, But Admits Traders May Be

    Citi: Oil Could Sink to $60 as Hormuz Traffic Normalizes

    • July 3, 2026
    Citi: Oil Could Sink to $60 as Hormuz Traffic Normalizes

    Soaring Imports Push India’s Crude Stocks to Near 1-Year High

    • July 3, 2026
    Soaring Imports Push India’s Crude Stocks to Near 1-Year High

    Japan’s Top Oil Refiner Eyes a Post-Hormuz Future

    • July 3, 2026
    Japan’s Top Oil Refiner Eyes a Post-Hormuz Future