CERC Rejects Tariff Adoption For 300 MW Wind-Solar Hybrid Project Over Procedural Lapses

Representational image. Credit: Canva

The Central Electricity Regulatory Commission (CERC) on July 9, 2025, dismissed a petition filed by CESC Limited seeking approval for the adoption of a tariff of ₹3.81 per unit for the long-term procurement of 300 MW power from a grid-connected Wind-Solar Hybrid Project. The tariff was discovered through a competitive bidding process conducted under the guidelines issued by the Ministry of Power for such projects. The petition was filed under Section 63 of the Electricity Act, 2003.

CESC had floated a Request for Selection (RfS) on November 8, 2024, inviting bids for a 150 MW Wind-Solar Hybrid Project with an additional 150 MW under the Greenshoe Option. The bidding process, conducted on the ISN ETS e-bidding portal, attracted three technically qualified bidders, and an e-reverse auction was held on December 27, 2024. The successful bidder, Purvah Green Power Private Limited, was awarded the total 300 MW capacity, and a Letter of Award was issued on January 7, 2025.

CESC defended the tariff of ₹3.81/kWh, stating that the project has a higher Capacity Utilisation Factor (CUF) of 50% compared to the usual 30% in similar projects, and a shorter completion timeline of 20 months. The Bid Evaluation Committee (BEC) had certified that the discovered tariff was in line with market conditions. A report by the Administrative Staff College of India also supported this claim.

However, the Commission noted several procedural lapses. The primary issue was that CESC obtained approval for deviations from the bidding guidelines from the Government of West Bengal, instead of the Central Government, even though the project was connected to the Inter-State Transmission System (ISTS). The Commission had earlier cautioned CESC in a similar matter (Petition No. 365/AT/2024) that for inter-state projects, such deviations must be approved by the Central Government.

The Commission emphasized that despite being made aware of the proper procedure on November 5, 2024, CESC proceeded to issue the RfS on November 8, 2024, without correcting the jurisdictional lapse. Moreover, the Commission raised concerns over transparency and limited competition, as the successful bidder in both this and the previous petition was a sister company of CESC.

CERC concluded that accepting the petition would violate the principles under Section 63 of the Electricity Act, as the mandatory guidelines for competitive bidding were not followed. Therefore, the Commission rejected the adoption of the discovered tariff and advised CESC to conduct a fresh bidding process in compliance with the appropriate guidelines and approvals.

The petition was thus disposed of, with CESC now required to restart the procurement process if it wishes to proceed with the project.

 

  • Related Posts

    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    Australian energy retailer AGL Energy is set to develop one of Australia’s largest privately owned, non-mining renewable energy microgrids for Koompartu Farms, the largest almond orchard in South Australia. The…

    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    State of Charge (SoC) is one of the most critical indicators of battery health and performance, representing the amount of usable energy available in a battery. This edition of Solarpedia…

    Have You Seen?

    Oil Prices Little Changed for Week as US-Iran Peace Efforts Hold

    • July 4, 2026
    Oil Prices Little Changed for Week as US-Iran Peace Efforts Hold

    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    • July 4, 2026
    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    • July 4, 2026
    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    Aboitiz Renewables Inaugurates 92.55 MWp San Manuel Solar Power Plant In Pangasinan, Philippines

    • July 4, 2026
    Aboitiz Renewables Inaugurates 92.55 MWp San Manuel Solar Power Plant In Pangasinan, Philippines

    Bhutan Commissions 7.83 MW Rooftop Solar Project Across 187 Public Buildings

    • July 4, 2026
    Bhutan Commissions 7.83 MW Rooftop Solar Project Across 187 Public Buildings

    Green Guarantee Company Mobilizes USD 70 Million To Expand Clean Energy Access Across Africa

    • July 4, 2026
    Green Guarantee Company Mobilizes USD 70 Million To Expand Clean Energy Access Across Africa

    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    • July 4, 2026
    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    What Natural Gas’s Ascendancy Says About the US

    • July 4, 2026
    What Natural Gas’s Ascendancy Says About the US

    Oil Prices Little Changed as US-Iran Peace Efforts Hold

    • July 4, 2026
    Oil Prices Little Changed as US-Iran Peace Efforts Hold

    TotalEnergies Offers Millions of Barrels of Iraqi Crude to Asian Buyers

    • July 4, 2026
    TotalEnergies Offers Millions of Barrels of Iraqi Crude to Asian Buyers