Assembly of Taipingling 3 containment vessel begins

Monday, 28 July 2025

The bottom head of the containment vessel of unit 3 at the Taipingling nuclear power plant has been installed on the central raft foundation of the unit’s nuclear island, China General Nuclear announced.

Assembly of Taipingling 3 containment vessel begins
(Image: CGN)

The HPR1000 (Hualong One) reactor design features a double-layered containment structure. The main function of the containment building is to ensure the integrity and leak tightness of the reactor building, and it plays a key role in the containment of radioactive substances.

The 36 steel sub-modules of the bottom head module were prefabricated off-site, transported to the construction site and welded together. The completed module – measuring about 43 metres in diameter, 6 metres in height and weighing more than 130 tonnes – was hoisted into place using a 2,000-tonne crawler crane.

China General Nuclear (CGN) said installation of the first containment module at Taipingling unit 3 “marks the steady advancement of the modular construction technology of nuclear island civil engineering in the Taipingling Nuclear Power Project, and lays a solid foundation for the high-quality construction of subsequent nuclear island civil engineering projects”.

The Taipingling plant in Guangdong province will eventually have six Hualong One reactors. The construction of the first and second units began in 2019 and 2020, respectively. Unit 1 is scheduled to start up later this year, with unit 2 following in 2026.

Construction of the second phase of the plant – units 3 and 4 – was approved by China’s State Council on 29 December 2023. The first safety-related concrete was poured for the reactor building of Taipingling unit 3 last month.

   

  • Related Posts

    FANCO expands cooperation with Hyundai E&C on EAGL-1

    The master service agreement – signed at Hyundai E&C’s headquarters in Gye-dong, Jongno-gu, Seoul, on 30 October – advances to the contract stage a framework agreement the two companies signed…

    Heat raised for UK’s MAST Upgrade fusion machine

    The UK Atomic Energy Authority (UKAEA) said the double beam box has a “double decker” layout with two neutral beam injectors – injectors fire high-energy neutral atoms into the plasma…

    Have You Seen?

    Nigeria’s Oil and Gas Output Rises to 3.04 Million Boepd

    • November 4, 2026
    Nigeria’s Oil and Gas Output Rises to 3.04 Million Boepd

    European Gas Prices Fall 2% as Traders Wait on Trump’s Next Move in Iran

    • November 4, 2026
    European Gas Prices Fall 2% as Traders Wait on Trump’s Next Move in Iran

    UAE-Controlled Moeve Sells Algerian Upstream Assets

    • November 4, 2026
    UAE-Controlled Moeve Sells Algerian Upstream Assets

    Dangote Breaks Ground on $2.5 Billion Namibia Fuel Hub for Southern Africa

    • November 4, 2026
    Dangote Breaks Ground on $2.5 Billion Namibia Fuel Hub for Southern Africa

    Ohio ethanol producer to acquire biofuels firm HLCP for $915m

    • November 4, 2026
    Ohio ethanol producer to acquire biofuels firm HLCP for $915m

    Bosch’s new semiconductor division targets €5bn sales by 2030

    • November 4, 2026
    Bosch’s new semiconductor division targets €5bn sales by 2030

    China Now Home to Nearly Half of World’s Clean Industrial Plants

    • November 4, 2026
    China Now Home to Nearly Half of World’s Clean Industrial Plants

    India Races to Triple Coal Stockpiles to Prevent Summer Blackouts

    • November 4, 2026
    India Races to Triple Coal Stockpiles to Prevent Summer Blackouts

    Iran Says Four Oil Tankers Destroyed by Mines Near Strait of Hormuz

    • November 4, 2026
    Iran Says Four Oil Tankers Destroyed by Mines Near Strait of Hormuz

    Renewables Stocks Soar as Democrats Sweep U.S. Congress

    • November 4, 2026
    Renewables Stocks Soar as Democrats Sweep U.S. Congress