Delay in Flamanville 3 attaining full power

Monday, 4 August 2025

The long-delayed Flamanville 3 EPR reactor in Normandy in northern France is now expected to reach full power for the first time “before the end of autumn 2025”, EDF said. It had earlier been scheduled to reach full power in “summer 2025”.

Delay in Flamanville 3 attaining full power
The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

The 1630 MWe (net) pressurised water reactor was connected to the grid for the first time on 21 December 2024. At that time, EDF said that “in accordance with the startup operations, the phases of testing and of connection and disconnection to the grid will continue for several months … until the reactor reaches 100% power”. This had been scheduled for summer 2025.

However, EDF has now said: “After its next reconnection to the grid, the Flamanville 3 teams will continue the testing phase before commissioning with an objective to reach full capacity before the end of autumn 2025.

“At the end of this testing period, the unit is expected to be operated at 100% capacity until the first planned outage for maintenance and refuelling, called Visite Complète 1 (VC1). This first planned outage should mainly take place in 2026.”

Construction work began in December 2007 on the third unit at the Flamanville site – where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013 but has faced a series of delays.

The first EPR units came online at Taishan in China, where unit 1 became the first EPR to enter commercial operation in 2018 followed by Taishan 2 in September 2019. In Europe, Olkiluoto 3 in Finland entered commercial operation in 2023, and two units are currently under construction at Hinkley Point C in the UK, with two more planned at Sizewell C.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    • April 10, 2026
    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates

    • April 10, 2026
    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates