NextEra updates NRC on Duane Arnold plans

The company presented an overview of the current status and its plans for the proposed restart of the shuttered plant in submitted to the US Nuclear Regulatory Commission (NRC) ahead of a 7 August Pre-Submittal Meeting.

The 610 MWe boiling water reactor plant, owned and operated by NextEra Energy Duane Arnold, LLC in Linn County, Iowa, commenced commercial operation in 1974. Although currently licensed for operations until 2034, the Duane Arnold plant ceased operations in 2020 and is currently “idled and in decommissioning status”, but in January, the company submitted documents including a restart overview and regulatory path to reauthorisation of power operations.

Since it was shut, all the plant’s used fuel has been transferred to its Independent Spent Fuel Storage Installation, and most major plant systems have been drained and deenergised. Training and administrative buildings have been removed, as have the mechanical draft cooling towers, and generator output transformer and in-scope transmission lines, but the main power block buildings remain intact.

Planned restart activities will restore the plant to its previous operating licence condition at 2020 shutdown. Planned plant modifications include new cooling towers, restoration of in-scope transmission lines, new office and warehouse buildings, and upgrades to the sewage treatment system upgrade. Plans also include dredging of the water intake from the Cedar River.

“Under NEPA [the National Environmental Policy Act], it is anticipated that NRC will prepare an Environmental Assessment (EA) for this restart,” the company said in the slides. NextEra Energy Duane Arnold, LLC will coordinate with the NRC Environmental Project Manager regarding the need for an environmental review document, and the subject areas to cover; and “submit an environmental review document (tentatively in October 2025) that focuses on restart activities useful for the NRC’s NEPA review”.

It anticipates that a final EA and Finding of No Significant Impact “will be issued within 12 months of acceptance of an environmental submittal”.

NextEra Energy recently filed a request with the US Federal Energy Regulatory Commission seeking to reclaim interconnection rights that were previously transferred from the shut down Duane Arnold nuclear power plant in Iowa to a solar energy project: about 40 acres of the Duane Arnold site are now occupied by a solar farm.

   

  • Related Posts

    Containment tests completed at Lufeng unit 5

    The two-part tests, which began on 29 August, confirm that the containment vessel meets design and construction quality requirements. The first part – the structural integrity test – involved the…

    Natural draft cooling tower is preferred JEK2 option

    The results of the feasibility study were released as part of the latest reports made public before the country prepares for a planned referendum on new nuclear. Bruno Glaser, Technical…

    Have You Seen?

    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    • September 19, 2026
    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    Vedanta Aluminium Prepares for Rising Demand for Specialised Aluminium in India’s Power Grid Expansion

    • September 19, 2026
    Vedanta Aluminium Prepares for Rising Demand for Specialised Aluminium in India’s Power Grid Expansion

    GEON Commissions 10 MW/20 MWh BESS Project In Phalodi, Rajasthan

    • September 19, 2026
    GEON Commissions 10 MW/20 MWh BESS Project In Phalodi, Rajasthan

    Suzlon Energy Allots 6.4 Lakh Equity Shares Under ESOP 2022, Paid-Up Capital Rises to INR 2,749.26 Crore

    • September 19, 2026
    Suzlon Energy Allots 6.4 Lakh Equity Shares Under ESOP 2022, Paid-Up Capital Rises to INR 2,749.26 Crore

    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    • September 19, 2026
    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    INEOS Opens EU’s First Full-Scale Carbon Storage Site in Denmark

    • September 19, 2026
    INEOS Opens EU’s First Full-Scale Carbon Storage Site in Denmark

    LNG Tankers Push Through Hormuz Again as Qatar, UAE Fight Supply Crunch

    • September 18, 2026
    LNG Tankers Push Through Hormuz Again as Qatar, UAE Fight Supply Crunch

    Hormuz Tanker Traffic Slumps as Saudi Arabia Scrambles for New Oil Routes

    • September 18, 2026
    Hormuz Tanker Traffic Slumps as Saudi Arabia Scrambles for New Oil Routes

    India’s Clean Energy Boom Halts Coal Power Growth

    • September 18, 2026
    India’s Clean Energy Boom Halts Coal Power Growth

    Saudi Oil Exports Rebound at Hormuz While East-West Pipeline Remains Offline

    • September 18, 2026
    Saudi Oil Exports Rebound at Hormuz While East-West Pipeline Remains Offline