MNRE Issues FAQs On SPV Module Testing Guidelines Under QCO 2025

Representational image. Credit: Canva

The Ministry of New & Renewable Energy has issued frequently asked questions (FAQs) to clarify testing guidelines for SPV module series approval under the Solar Systems, Devices and Components Goods Order, 2025. The Q&A explains that for multiple power class bins, at least two modules each from lower, median, and higher classes must be tested. Standards like IEC 60904-1:2020 are specified for measuring hysteresis loss in high-capacitance modules. It details sample requirements for IS 14286:2023, IS/IEC 61730-2:2023, and IS/IEC 61730-1:2023, with the highest capacity module serving as the lead model in the family. These clarifications aim to ensure consistency and compliance in BIS testing.

Question 1: What sequence/method of testing is to follow for multiple bins of power classes?

Answer: For the qualification of multiple bins of power classes within the boundaries given in IEC TS 62915, at least 2 modules each, from the lower end, median, and higher end power classes shall be used for testing. If the median power class does not exist, the next higher class shall be used. If qualification of a single power class shall be extended to further bins of power classes within the boundaries given in IEC TS 62915 (then at least 2 modules each, from the lower end and higher end power class shall be used for label verification (Gate No.1). If a power class is extended only towards higher (or lower) bins, then modules only from the higher (or lower) bins, respectively, shall be used for verification of rated label values. bins of power classes: power (typically maximum power), sorting criteria from the PV module manufacturer

Question 2: Which standard/test to follow for the measurement of hysteresis loss for high-capacitance PV module?

Answer: For IV measurement of a high-capacitance PV module, hysteresis loss needs to be minimized, as per IEC 60904-1:2020, hysteresis shall be less than 0.5%. Or the following results shall be reported for an investigation of the high capacitance of PV module as per IEC 60904-1:2020 • dI/dt and dV/dt for IPmax and VPmax, errcap, etc.

Question 3: What is the number of samples required for testing as per Indian Standards IS 14286: 2023?

Answer: A total of twelve modules shall be taken at random from a production batch or batches, in accordance with the procedure given in IS 14286. The modules shall have been manufactured from specified materials and components in accordance with the relevant drawings and process sheets and have been subjected to the manufacturer’s normal quality control and production acceptance procedures. The modules shall be complete in every detail and shall be accompanied by the manufacturer’s handling, mounting, and connection instructions, including the maximum permissible system voltage. The modules should contain the bypass diode wherever applicable. In case of the modules with sealed junction boxes, the client should provide one extra module having access to the diode for conducting the bypass diode test.

Question 4: What is the number of samples required for testing as per Indian Standards IS/IEC 61730-2: 2023?

Answer: The selection of the sample should be as per clause 6 of IS/IEC 61730-2: 2023. All these modules should fulfil the requirement as stated above for IS 14286. A minimum of 10 PV modules and two unframed PV modules are used for safety testing (plus spares as desired). In order to prove the reduction of Pollution Degree to PD 1, one additional PV module is required. If tests of Sequence F are performed in parallel, between one and three additional modules are required.

Question 5: What is the number of samples required for testing as per Indian Standards IS/IEC 61730-1: 2023?

Answer: No additional sample is required to submit for the testing of this standard since this refers to Requirements for Construction, which can be done by samples submitted for testing of IS/IEC 61730-2: 2023.

Question 6: Which will be the lead model in the family of modules?

Answer: The Highest capacity Module will be the lead model in the family of modules intended to be covered, and which is also being tested.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    CERC Issues First Amendment To 2022 REC Regulations, Introducing VPPAs And New Certificate Multipliers

    The Central Electricity Regulatory Commission (CERC) has issued the First Amendment to the 2022 regulations governing Renewable Energy Certificates (RECs) in India, marking a significant update in how renewable energy…

    Sukošan Solar Power Plant Set For 45 MW Grid Connection And New 110/33 kV Substation Construction

    The Sukošan Solar Power Plant project, known as SPP Sukošan, is being developed in Zadar County, within the Municipality of Sukošan. The site covers cadastral plots 645/1 and 645/5 in…

    Have You Seen?

    Two Halma group brands move under Salaera tech platform

    • April 7, 2026
    Two Halma group brands move under Salaera tech platform

    Somalia Set To Begin First Ever Offshore Oil Drilling In April

    • April 7, 2026
    Somalia Set To Begin First Ever Offshore Oil Drilling In April

    Iraq Prepares to Ramp Up Production After War Disruption

    • April 7, 2026
    Iraq Prepares to Ramp Up Production After War Disruption

    South Korea Scrambles to Secure Oil Beyond Hormuz

    • April 7, 2026
    South Korea Scrambles to Secure Oil Beyond Hormuz

    Oil Market Maintains Cautiously Bullish Bias

    • April 7, 2026
    Oil Market Maintains Cautiously Bullish Bias

    Charbone refills helium trailer for Canadian distributor

    • April 7, 2026
    Charbone refills helium trailer for Canadian distributor

    Nikkiso CE&IG wins cryogenic pump contract for major German LNG site

    • April 7, 2026
    Nikkiso CE&IG wins cryogenic pump contract for major German LNG site

    Airgas provides high-pressure nitrogen for Artemis II

    • April 7, 2026
    Airgas provides high-pressure nitrogen for Artemis II

    INOXAP commissions first ultra-high purity liquid oxygen facility in India

    • April 7, 2026
    INOXAP commissions first ultra-high purity liquid oxygen facility in India

    LNG ships halted as strait deadline nears

    • April 7, 2026
    LNG ships halted as strait deadline nears