Steam generator installation begins at Haiyang 4

Steam generators are heat exchangers which convert heat generated by the reactor core into steam, which is transported to the conventional island via the main steam pipeline. The steam generator drives the steam turbine, which then drives the generator to generate electricity.

The first of the two steam generators for Haiyang 4 – each with a diameter of nearly 6 metres, a length of about 24 metres, and a net weight of over 630 tonnes – was hoisted into place within the reactor building on 13 August in an operation lasting 3 hours and 22 minutes.


(Image: CNNC)

State Power Investment Corporation (SPIC) said the installation of the first steam generator – the heaviest and largest components of the nuclear island reactor’s primary circuit – has “laid a solid foundation for the connection of the main circuit of the nuclear island reactor and the capping of the reactor building”.

SPIC noted that, based on the construction experience of Haiyang unit 3, workers “formulated improvement measures, established a daily meeting system to sort out various prerequisites, used mature and reliable laser 3D measurement and modeling technology to carry out installation simulation, carried out special prerequisite supervision and inspection, and strictly controlled on-site safety and quality during the hoisting process to ensure the precise positioning of the steam generator.”


(Image: CNNC)

The construction of two CAP1000 reactors – the Chinese version of the Westinghouse AP1000 – as units 3 and 4 of the Haiyang plant was approved by the country’s State Council on 20 April 2022.

The first safety-related concrete was poured for the nuclear island of Haiyang unit 3 in July 2022, with that for unit 4 being poured in April 2023. The two units are scheduled to be fully operational in 2027.

   

  • Related Posts

    Kaleidos microreactor begins journey to Idaho

    “We said we’d make a microreactor that is transportable by land, sea and air. We did. Kaleidos is traveling more than 1,000 miles on a trailer bed,” the company said. …

    Detritiation facility reopens at Culham

    In the last three years of plasma operations, the Joint European Torus’s (JET’s) deuterium-tritium experiments resulted in residual tritium being retained within the tokamak’s walls and internal components. This reflected…

    Have You Seen?

    Gulf-to-China Supertanker Rates Hit $510,000 a Day

    • August 18, 2026
    Gulf-to-China Supertanker Rates Hit $510,000 a Day

    Romania Restarts Coal Plant as Danube Drought Forces Nuclear Shutdown

    • August 18, 2026
    Romania Restarts Coal Plant as Danube Drought Forces Nuclear Shutdown

    China’s Solar Exports Fell 21.4% in July

    • August 18, 2026
    China’s Solar Exports Fell 21.4% in July

    UK researchers make MOF for capturing heavy metals from wastewater

    • August 18, 2026
    UK researchers make MOF for capturing heavy metals from wastewater

    US semiconductor investment tops $820bn since 2020

    • August 18, 2026
    US semiconductor investment tops $820bn since 2020

    UK biogas plant gets green light for CO2 capture and liquefaction

    • August 18, 2026
    UK biogas plant gets green light for CO2 capture and liquefaction

    Outlook for electronic specialty gases

    • August 18, 2026
    Outlook for electronic specialty gases

    U.S.-Iran Tensions Push Oil Prices Higher as Diesel Margins Hit Records

    • August 18, 2026
    U.S.-Iran Tensions Push Oil Prices Higher as Diesel Margins Hit Records

    Libya Seeks Up to $40 Billion to Boost Oil Output to 2 Million Bpd

    • August 18, 2026
    Libya Seeks Up to $40 Billion to Boost Oil Output to 2 Million Bpd

    China Boosts Fuel Exports as Domestic Stockpiles Swell

    • August 18, 2026
    China Boosts Fuel Exports as Domestic Stockpiles Swell