Xudabao unit 3 completes cold testing

China National Nuclear Corporation (CNNC) said that the joint Chinese and Russian project reached the landmark on 12 December.

It said: “The cold functional test is a significant milestone in the construction of a nuclear power unit, representing the first comprehensive ‘check-up’ of the reactor and primary loop equipment. It aims to verify the overall performance of related systems and equipment under cold, high-pressure conditions. The successful completion of this test fully demonstrates that the primary loop pressure boundary of unit 3 at the Xudabao Nuclear Power Plant is intact and the equipment performance is reliable, effectively ensuring the safe and stable operation of the unit in the future.”

In June 2018, Russia and China signed four agreements, including for the construction of two VVER-1200 reactors at the new Xudabao (also known as Xudapu) site. Agreements signed in June 2019 included a general contract for the construction of Xudabao units 3 and 4, as well as a contract for the supply of nuclear fuel.

Construction of Xudabao unit 3 began in July 2021, with that of unit 4 starting in May 2022. The dome was lifted into place on the reactor building for unit 3 in July 2023. Commissioning of the units is scheduled for 2027 and 2028, respectively.

The Xudabao plant is owned by Liaoning Nuclear Power Company Limited, a joint venture between CNNC (70%), Datang International Power Generation Company (20%) and State Development and Investment Corporation (10%).

   

  • Related Posts

    India begins public consultation on SHANTI Bill rules

    The SHANTI Bill – to give it its full name, the Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Bill, 2025 – completed the legislative process in…

    Blue Energy, GE Vernova take gas-plus-nuclear collaboration to next stage

    In May, Blue Energy – a vertically integrated deployment platform for financeable, turnkey nuclear power plants compatible with leading reactor technology – announced it was joining up with GE Vernova…

    Have You Seen?

    UK researchers make MOF for capturing heavy metals from wastewater

    • August 18, 2026
    UK researchers make MOF for capturing heavy metals from wastewater

    US semiconductor investment tops $820bn since 2020

    • August 18, 2026
    US semiconductor investment tops $820bn since 2020

    UK biogas plant gets green light for CO2 capture and liquefaction

    • August 18, 2026
    UK biogas plant gets green light for CO2 capture and liquefaction

    Outlook for electronic specialty gases

    • August 18, 2026
    Outlook for electronic specialty gases

    10 minutes with… Airgas and Air Liquide North America CEOs

    • August 18, 2026
    10 minutes with… Airgas and Air Liquide North America CEOs

    Will Oil Prices Keep Rising?

    • August 18, 2026
    Will Oil Prices Keep Rising?

    UCLR completes first hot fire of cryogenic LOX engine

    • August 18, 2026
    UCLR completes first hot fire of cryogenic LOX engine

    Analysis: The key role of LNG in the UK North Sea debate

    • August 18, 2026
    Analysis: The key role of LNG in the UK North Sea debate

    Analysis: The key role of LNG in the UK North Sea debate

    • August 18, 2026
    Analysis: The key role of LNG in the UK North Sea debate

    India Daily: RRECL Launches RE Monitoring Tool, CSPDCL Seeks ₹2.98/kWh BESS Tariff, GERC Advances GNA Regulations, CleanMax Plans ₹400 Cr NCDs and More…

    • August 18, 2026
    India Daily: RRECL Launches RE Monitoring Tool, CSPDCL Seeks ₹2.98/kWh BESS Tariff, GERC Advances GNA Regulations, CleanMax Plans ₹400 Cr NCDs and More…