Flamanville EPR reaches full power

The ramp-up of nuclear thermal power reached 100% at11:37 on Sunday, EDF said. 

It added: “Reaching the 100% mark for the first time enables testing of equipment at full power, taking of measurements and verifying that everything is functioning properly. Over the coming weeks, and as part of the start-up programme, the power of the reactor will vary to continue testing at different power levels and an operation will be carried out on an internal electrical substation. This milestone reflects the commitment and expertise of the teams of EDF and of its industrial partners over the past months to ensure the safe start-up of the reactor.”

This is the latest stage of commissioning the 1650 MWe (gross) pressurised water reactor. The Autorité de Sûreté Nucléaire et de Radioprotection (ASNR) authorised the start of commissioning in May last year. That authorisation was followed by fuel loading, with the start-up process beginning in September 2024.

Starting up a nuclear reactor takes place over several months. Gradually, the circuits are brought up to temperature and pressure, power tests are carried out, and then the production unit is connected to the electrical grid – which happened with Flamanville 3 in December 2024.

The power is then increased in a series of stages, with numerous tests carried out at each level before the unit is cleared to move to the next stage. In January this year the French regulator gave permission for the reactor to go beyond 25% of its capacity, with tests and checks carried out through the year.

ASNR said: “During this phase, the physical testing of the core continued at different power levels and were supplemented by tests such as islanding (isolation from the electricity grid while maintaining energy production for the plant’s own needs) or manual shutdown of the reactor.

“The ASNR carried out several inspections of the reactor from the 25% power level. It also analysed the significant events declared by EDF and checked the corrective actions implemented. The ASNR has not identified any element that could call into question the possibility of continuing to ramp up the reactor beyond 80% of its nominal power.

“ASNR will continue to monitor the subsequent stages of the reactor ramp-up until the end of the start-up tests.”

It said its new approval “allows EDF to continue ramping up the reactor until it reaches its nominal power, and then to complete the start-up test programme”.

Construction work began in December 2007 on the third unit at the Flamanville site in Normandy in northern France – where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013 but has faced a series of delays.

The first EPR units came online at Taishan in China, where unit 1 became the first EPR to enter commercial operation in 2018 followed by Taishan 2 in September 2019. In Europe, Olkiluoto 3 in Finland entered commercial operation in 2023, and two units are currently under construction at Hinkley Point C in the UK.

   

  • Related Posts

    Construction of Chinese HTGR begins

    Xuwei Phase I was among 11 reactors approved by China’s State Council in August 2024. China National Nuclear Corporation (CNNC) plans to build two 1,208 MWe (net) Hualong One (HPR1000)…

    NAC to supply used fuel storage solution for Norway

    Norway holds about 16.5 tonnes of used fuel from six decades of operating nuclear research reactors. Much of it cannot be stored long term or disposed of in its current…

    Have You Seen?

    ADNOC Expands LNG Empire With Major New India Supply Deal

    • November 6, 2026
    ADNOC Expands LNG Empire With Major New India Supply Deal

    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    • November 6, 2026
    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    • November 6, 2026
    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    Viridi raises £2.2m to turn captured CO2 into chemicals

    • November 6, 2026
    Viridi raises £2.2m to turn captured CO2 into chemicals

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Oil Market Arrives at ‘Remarkable Destination’

    • November 6, 2026
    Oil Market Arrives at ‘Remarkable Destination’

    The Global Oil Glut Returns as High Prices Crush Demand

    • November 6, 2026
    The Global Oil Glut Returns as High Prices Crush Demand

    China’s Carbon Emissions Plunge 3.1% as Oil Demand Slumps

    • November 6, 2026
    China’s Carbon Emissions Plunge 3.1% as Oil Demand Slumps

    Pentagreen Capital and Candi Solar Sign US$50 Million Deal for 400 MW Solar and BESS Projects in India

    • November 6, 2026
    Pentagreen Capital and Candi Solar Sign US$50 Million Deal for 400 MW Solar and BESS Projects in India