EDF estimates EPR2 programme cost at EUR72.8 billion

The figure was presented to its board of directors on Thursday. The board approved a EUR2.7 billion budget allocation to the programme for 2026, the company said.

The cost estimate is to be audited in the first three months of 2026 by France’s Interministerial Delegation for New Nuclear Technology, which reports to the French president.

France submitted its proposed state aid measures for approval to the European Commission in November – they comprise a subsidised loan to finance at least half of the construction costs; a 40-year Contract for Difference; and risk sharing between the state and EDF.

A Contract for Difference is essentially where there is a future fixed price guaranteed for electricity generated, with the government either paying the difference between the market price and the agreed sale price, or receiving payment if the market price is higher. 

The aim is to be able to take a Final Investment Decision by the end of 2026.

Bernard Fontana, Chairman and CEO of the EDF Group, said: “The establishment of the preliminary cost estimate for the EPR2 programme reflects the commitment of EDF teams, its subsidiaries, and all of our industrial partners to controlling deadlines and costs.”

EDF said that “the completion of the EPR2 programme will contribute to France’s energy and industrial sovereignty, as well as its energy transition, for decades to come”.

In February 2022 President Emmanuel Macron announced that the time was right for a nuclear renaissance in France, saying the operation of all existing reactors should be extended without compromising safety, and unveiling the proposed programme for six new EPR2 reactors, with an option for a further eight EPR2 reactors to follow. The first three pairs of EPR2 reactors are proposed to be built, in order, at the Penly, Gravelines and Bugey nuclear power plant sites. Construction was expected to start in 2027 with commissioning in 2035, but that target date for commissioning the first reactor at Penly is now 2038, with subsequent units following at intervals of up to 18 months.

The cost was originally estimated at EUR51.7 billion (USD56.4 billion), but this was revised to EUR67.4 billion in 2023. The new estimate is at 2020 values.

The EPR2 reactor is a pressurised water reactor project developed by EDF and Framatome. It meets the general safety objectives of the third generation of reactors. Its aim is to incorporate design, construction and commissioning experience feedback from the EPR reactor, as well as operating experience from the nuclear reactors currently in service.

   

  • Related Posts

    Deep Isolation launches full-scale demonstration programme

    A groundbreaking event was held on 28 January to mark the beginning of the demonstration project, which is aimed at building stakeholder and regulatory confidence in the company’s deep borehole…

    WANO rolls out new enhanced monitoring initiative

    World Association of Nuclear Operators (WANO), which has traditionally focused on peer review visits to nuclear units every four years, is now also getting key data from each of the…

    Have You Seen?

    Washington Prepares Broad License to Restart Venezuelan Oil Production

    • February 4, 2026
    Washington Prepares Broad License to Restart Venezuelan Oil Production

    US Crude Oil Inventories Take Big Hits In Storm Aftermath

    • February 4, 2026
    US Crude Oil Inventories Take Big Hits In Storm Aftermath

    Trump Administration Greenlights Deepwater Texas Oil Terminal

    • February 4, 2026
    Trump Administration Greenlights Deepwater Texas Oil Terminal

    Equinor Reduces Share Buyback

    • February 4, 2026
    Equinor Reduces Share Buyback

    Exus Renewables Enters UK And Ireland With New Cambridge Office, Marking Major Step In International Growth Strategy

    • February 4, 2026
    Exus Renewables Enters UK And Ireland With New Cambridge Office, Marking Major Step In International Growth Strategy

    GameChange Solar Selected to Supply Trackers for 1,290 MWp Bisha Solar PV Plant in Saudi Arabia

    • February 4, 2026
    GameChange Solar Selected to Supply Trackers for 1,290 MWp Bisha Solar PV Plant in Saudi Arabia

    Meta And Zelestra Expand Clean Energy Partnership With 176 MWdc Skull Creek Solar Plant In Texas To Support 100% Renewable Operations

    • February 4, 2026
    Meta And Zelestra Expand Clean Energy Partnership With 176 MWdc Skull Creek Solar Plant In Texas To Support 100% Renewable Operations

    DEE Development Engineers Reports Q3 FY26 Revenue Of ₹286.7 Crore, Up 77% YoY, Driven By Strong Execution In Piping & Fittings For Oil & Gas Sector

    • February 4, 2026
    DEE Development Engineers Reports Q3 FY26 Revenue Of ₹286.7 Crore, Up 77% YoY, Driven By Strong Execution In Piping & Fittings For Oil & Gas Sector

    The growth in low-cost commercial CO2 sources

    • February 4, 2026
    The growth in low-cost commercial CO2 sources

    Access and security dominate LNG Qatar conference

    • February 4, 2026
    Access and security dominate LNG Qatar conference