Wyoming approves permit for demo Natrium plant

Wednesday, 15 January 2025

Wyoming approves permit for demo Natrium plant
A rendering of a Natrium plant (Image: TerraPower)

Natrium technology features a 345 MWe sodium-cooled fast reactor using high-assay low-enriched uranium fuel, with a molten salt-based energy storage system that can boost the system’s output to 500 MWe for more than five and a half hours when needed.

The Industrial Siting Council (ISC) reviews the socio-economic and environmental impacts of industrial facilities before issuing a permit for construction. Emphasis is placed upon social-economic impacts.

The permit from the Wyoming ISC – which TerraPower applied for in October 2024 – will allow for the construction of non-nuclear facilities for the first-of-a-kind plant, including the energy island portion of the Natrium plant that houses the molten-salt energy storage tanks and turbines. With this permit complete, TerraPower will continue its construction schedule, with plans to start construction on both the Kemmerer Training Centre and the energy island in 2025, as well as continue work on the sodium test and fill facility that began in 2024.

“This is the first state permit ever awarded to a commercial-scale advanced nuclear project and is a testament to the groundbreaking work of our TerraPower team,” the company’s President and CEO Chris Levesque said. “The regulatory process to bring new nuclear plants to fruition is robust, and our team has been working relentlessly to successfully manoeuvre through a complicated, multi-jurisdictional environment to bring the first Natrium plant to market.”

TerraPower – a company largely funded by Microsoft founder Bill Gates – noted it is the first and only advanced nuclear developer with a permit application for a commercial advanced reactor submitted to the Nuclear Regulatory Commission (NRC), which oversees all nuclear portions of the Natrium plant. That application was submitted in March 2024 and is on track for approval in December 2026.

“The unique Natrium design enables the company to start non-nuclear construction onsite during the NRC review,” TerraPower said.

A ground-breaking ceremony held in June last year marked the start of non-nuclear construction at the Kemmerer site, and came weeks after the NRC accepted for docketing TerraPower’s application for a construction permit, submitted earlier in 2024.

In its application to the ISC, TerraPower said: “Contingent upon obtaining approval from the ISC and securing all other required permits, building activities are planned to begin in March 2025 and continue for approximately 69 months. Nuclear fuel load is projected for fall of 2030 and commercial operation for the fall of 2031.”

TerraPower will need to submit a separate operating licence application to obtain permission to run the reactor.

   

  • Related Posts

    Czech-Korean ministerial committee established for Dukovany project

    The Czech Republic’s Minister of Industry and Trade Karel Havlíček said: “We pushed through the Dukovany project during our previous government and at the same time we approved the timetable.…

    TVONS to provide advice for Estonian SMR project

    Under the agreement, TVONS will advise on the key stages of the project, from project initiation and permit preparations to the assessment of delivery models and support for commissioning and…

    Have You Seen?

    US Natural Gas Futures Sink to Four-Month Low on Warm Forecast

    • February 19, 2026
    US Natural Gas Futures Sink to Four-Month Low on Warm Forecast

    US Energy Chief Downplays Interest in Greenland’s Rare Earths

    • February 19, 2026
    US Energy Chief Downplays Interest in Greenland’s Rare Earths

    Japan, US Reach $36 Billion of Gas, Mineral Deals in Trump Pact

    • February 19, 2026
    Japan, US Reach $36 Billion of Gas, Mineral Deals in Trump Pact

    California, Colorado and Washington Sue Trump Administration to Unlock Funding for Clean Energy Projects

    • February 19, 2026
    California, Colorado and Washington Sue Trump Administration to Unlock Funding for Clean Energy Projects

    US Refiners Phillips 66, Citgo Seek to Buy Crude Directly From Venezuela, Sources Say

    • February 19, 2026
    US Refiners Phillips 66, Citgo Seek to Buy Crude Directly From Venezuela, Sources Say

    U.S. Attacks Alleged Drug Boats as Venezuela Oil Crackdown Escalates

    • February 19, 2026
    U.S. Attacks Alleged Drug Boats as Venezuela Oil Crackdown Escalates

    The Staggering Cost of Nigeria Missing OPEC+ Oil Quotas

    • February 18, 2026
    The Staggering Cost of Nigeria Missing OPEC+ Oil Quotas

    Which USA Oil Major Produced the Most in 2025?

    • February 18, 2026
    Which USA Oil Major Produced the Most in 2025?

    SM Energy to Sell Some Texas Assets for $950 Million

    • February 18, 2026
    SM Energy to Sell Some Texas Assets for $950 Million

    Mapped: What Powers Each U.S. State and Canadian Province? – Visual Capitalist

    • February 18, 2026
    Mapped: What Powers Each U.S. State and Canadian Province? – Visual Capitalist