Work on the 41-metre-long, 19-metre-wide, and 8.5-metre-high facility, which began in November 2024, involved demolishing the old storage facility and rebuilding it on the same site, with a volume equal to that of the dismantled building.

The new facility – referred to as the No 2 storage facility – will house both legacy waste, currently stored in storage facility No 1 and the “buffer test tank”, as well as waste generated by upcoming decommissioning operations.

At the same time, the characterisation and disposal of materials resulting from the demolition work, consisting primarily of iron, concrete, and excavated soil, has been completed.

The next stage of the project involves the installation of electrical, fire-prevention, and radiological monitoring systems, which will be completed by the first half of this year. Commissioning, following testing, is scheduled for early 2027.

Societa Gestione Impianti Nucleari SpA (Sogin) – established in 1999 to take responsibility for decommissioning Italy’s former nuclear power sites and locating a national waste store – said the new facility will bring the Trino plant (also referred to as the Enrico Fermi plant) “up to the latest regulatory safety standards”.

Upon completion, Sogin will begin work to upgrade the other repository on the site, No 1, as part of the programme to optimise the storage space for radioactive waste generated by the plant’s operation and the ongoing decommissioning work, with a view to its subsequent transfer to the national repository, once available.

Trino – comprising a single 270 MWe pressurised water reactor – was Italy’s first commercial nuclear power plant. Its construction began in 1961 and the plant started generating electricity in 1964. As a result of a referendum held in 1987 in the wake of the Chernobyl accident, Italy decided to shut down its four nuclear power plants. Trino was subsequently permanently shut down in 1990. Sogin took over ownership of the plant from utility Enel in 1999 and is responsible for its decommissioning.

   

  • Related Posts

    Construction of Chinese HTGR begins

    Xuwei Phase I was among 11 reactors approved by China’s State Council in August 2024. China National Nuclear Corporation (CNNC) plans to build two 1,208 MWe (net) Hualong One (HPR1000)…

    NAC to supply used fuel storage solution for Norway

    Norway holds about 16.5 tonnes of used fuel from six decades of operating nuclear research reactors. Much of it cannot be stored long term or disposed of in its current…

    Have You Seen?

    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    • November 6, 2026
    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    • November 6, 2026
    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    Europe’s Grid Spending Is Up 155% Since 2019

    • November 6, 2026
    Europe’s Grid Spending Is Up 155% Since 2019

    ADNOC Expands LNG Empire With Major New India Supply Deal

    • November 6, 2026
    ADNOC Expands LNG Empire With Major New India Supply Deal

    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    • November 6, 2026
    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    • November 6, 2026
    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    Viridi raises £2.2m to turn captured CO2 into chemicals

    • November 6, 2026
    Viridi raises £2.2m to turn captured CO2 into chemicals

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Oil Market Arrives at ‘Remarkable Destination’

    • November 6, 2026
    Oil Market Arrives at ‘Remarkable Destination’