Kursk II’s first unit reaches 40% capacity

By 13:00 local time on 30 January the unit was operating at a load of 408 MW, which is about 40% capacity for the VVER-TOI reactor. Pilot operation began the previous day, for the unit which was connected to the grid on 31 December.

Prior to the start of pilot operation a series of tests were carried out before Russia’s nuclear regulator Rostekhnadzor gave approval for the go-ahead.

At each stage of the commissioning process, as the power is gradually increased, tests and checks take place before moving on to the next level, with the regulator overseeing all stages to confirm it complies with all safety standards.

Alexey Likhachev, Rosatom Director General, said: “Pilot operation is a crucial stage, confirming the design conformity of the power unit’s systems and equipment under various operating conditions. This is a significant achievement for the entire Kursk NPP-2 team and Rosenergoatom, whose daily efforts are bringing the power unit closer to commercial operation.”

The plan is for the power unit to enter commercial operation during 2026.

Background

Kursk II is a new nuclear power plant in western Russia, about 60 kilometres (37.5 miles) from the Ukraine border, that will feature four VVER-TOI reactors, the latest version of Russia’s large light-water designs. They have upgraded pressure vessels and a power rating of 1,250 MW. Construction of the first unit began in 2018, its polar crane was installed in October 2021 and the reactor vessel was put in place in June 2022. Concreting of the outer dome of the first unit was completed in August 2023. The second unit is also under construction and the target is for all four units to be in operation by 2034.

Rosatom says the service life of the main equipment has doubled, and that the VVER-TOI units feature a mix of passive and active safety systems and include a core meltdown localiser. The new units at Kursk II will replace the four units at the existing, nearby Kursk nuclear power plant, which are scheduled to shut by 2031. The first unit was shut down after 45 years of operation in December 2021 and the second unit followed in January 2024. The original design life for the four RBMK-1000 reactors at the plant was for 30 years but had been extended by 15 years following life extension programmes.

   

  • Related Posts

    X-energy, Talen to assess deployment of multiple SMR plants

    The companies will explore opportunities to deploy three or more four-unit XE-100 plants “to add clean baseload capacity to help support reliability and meet growing energy demand from onshoring of…

    Framatome to supply low-enriched fuel for Belgium’s BR2 research reactor

    The French-based fuel specialist will supply high-density silicide low-enriched uranium (HD LEU) fuel elements for the 100 MWt reactor, which is a key global producer of medical radioisotopes. Framatome delivered three Lead…

    Have You Seen?

    US Loans 45.2 Million Barrels of Strategic Reserve Oil in First Batch Since Iran War

    • March 21, 2026
    US Loans 45.2 Million Barrels of Strategic Reserve Oil in First Batch Since Iran War

    NTPC Explores Power Sector Collaboration with Tajikistan at Bharat Electricity Summit 2026

    • March 21, 2026
    NTPC Explores Power Sector Collaboration with Tajikistan at Bharat Electricity Summit 2026

    MNRE Seeks Expanded Powers Under Electricity Act to Strengthen Renewable Energy Governance

    • March 21, 2026
    MNRE Seeks Expanded Powers Under Electricity Act to Strengthen Renewable Energy Governance

    PM Narendra Modi Shares Article Highlighting India’s Transformative Energy Transition

    • March 21, 2026
    PM Narendra Modi Shares Article Highlighting India’s Transformative Energy Transition

    CEO Roundtable Highlights Urgent Reforms for Power Distribution under Draft National Electricity Policy 2026

    • March 21, 2026
    CEO Roundtable Highlights Urgent Reforms for Power Distribution under Draft National Electricity Policy 2026

    Power Sector: Centre, States Align on Energy Security and Reforms at BES 2026 Ministerial Meet

    • March 21, 2026
    Power Sector: Centre, States Align on Energy Security and Reforms at BES 2026 Ministerial Meet

    Vikram Solar Limited Appoints Sameer Nagpal as CEO

    • March 21, 2026
    Vikram Solar Limited Appoints Sameer Nagpal as CEO

    India Pushes DISCOM Reforms: Shripad Yesso Naik Chairs GoM Meet at Bharat Electricity Summit 2026

    • March 21, 2026
    India Pushes DISCOM Reforms: Shripad Yesso Naik Chairs GoM Meet at Bharat Electricity Summit 2026

    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    • March 21, 2026
    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033

    • March 21, 2026
    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033