Defuelling of German plant completed

The 1410 MWe pressurised water reactor was shut down on 31 December 2021. PreussenElektra – a subsidiary of EOn Group – applied for approval to decommission and dismantle the plant in December 2017.

In October 2024, the Schleswig-Holstein Ministry for Energy Transition, Climate Protection, Environment and Nature issued the first decommissioning and dismantling permit to PreussenElektra for the Brokdorf plant. Phase 1 of the plant’s decommissioning and dismantling included the decommissioning and dismantling of the plant components that are no longer required and subject to nuclear regulatory supervision, with the exception of the reactor pressure vessel and the biological shield. In December 2024, all the requirements for using the permit were met when the last documents requiring approval came into force. On the same day, PreussenElektra notified the authorities that it was using the permit, meaning the plant’s post-operation phase had ended and it had entered the dismantling phase.

PreussenElektra has now announced that a total of 764 fuel assemblies have now been transferred from the storage pool into CASTOR used fuel storage casks since 2023.


Brokdorf (Image: PreussenElektra)

“This means that the radioactive core of the plant has been completely removed – and with it, over 99% of the radioactivity,” the company noted.

“The removal of nuclear fuel is an important milestone in the decommissioning of our plant, as it creates the conditions for further technical and organisational adjustments,” explains plant manager Tammo Kammrath. “We can now shut down additional systems and reduce the size of the shift crew. Their valuable expertise is urgently needed elsewhere, for example for the dismantling of the reactor pressure vessel internals, which is scheduled to begin in the spring of next year.”

PreussenElektra added: “For this important decommissioning project, various components and plant parts must first be removed from the area of ​​the now-empty spent fuel pool in order to create the necessary storage, handling, dismantling, and packaging areas. A further prerequisite for starting this work is the still-pending official permit for the use of the transport preparation hall for radioactive waste, which is currently under construction.”

A second dismantling permit is required to dismantle the reactor pressure vessel and the biological shield. This requires the removal of all fuel elements and special fuel rods. PreussenElektra submitted the application for the second dismantling permit on 30 August 2024.

Once all dismantling work has been completed, the site will be released for reuse.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    • October 2, 2026
    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    Oil Prices Come Under Pressure

    • October 2, 2026
    Oil Prices Come Under Pressure