Safety work planned for Chernobyl turbine hall

The operators of the Chernobyl nuclear power plant – State Specialised Enterprise Chornobyl NPP (ChNPP) – explained that the work is required because parts of the turbine hall and deaerator stack structures remained outside the area covered by the New Safe Confinement (NSC).

ChNPP added: “Preliminary surveys and expert assessments have established that the premises of the protruding parts of the deaerator stack are functionally necessary for the operation of the NSC-Shelter Object complex and have sufficient structural strength. However, certain structural elements require reinforcement or replacement to ensure reliable long-term operation. At the same time, the protruding parts of the turbine hall are not in use, and their technical condition does not meet the requirements for long-term safe operation, which necessitates their dismantling”.

A consortium consisting of UTEM, the Institute for Nuclear Safety Problems of the National Academy of Sciences of Ukraine, the State Research Institute of Building Structures, and the Design and Research Institute of the Security Service of Ukraine has been appointed as contractor for the works.

ChNPP said the detailed design documentation will include technical solutions “for reconstruction and reinforcement of the structures, determination of the sequence of construction work, definition of radiation protection measures, organisation of monitoring and control activities, with the aim of minimising any impact on the functioning of the NSC”.

It said that the project will be an “important step in maintaining the safe condition of the New Safe Confinement and creating the required conditions for the future dismantling of the unstable” original shelter from 1986.

The work is being funded by contributors to the International Chernobyl Cooperation Account through its administrator, the European Bank for Reconstruction and Development.

Serhiy Tarakanov, Director General of ChNPP, said: “We sincerely appreciate our donors and EBRD’s continued support in the implementation of these essential projects. We are aware of our responsibility and, despite the difficult situation, continue to work hard to transform the Shelter facility into an environmentally safe system and to ensure safety for future generations.”

Background

Chernobyl unit 4 was destroyed in the April 1986 accident (you can read more about it in ) with a shelter constructed in a matter of months to encase the damaged unit, which allowed the other units at the plant to continue operating. It still contains the molten core of the reactor and an estimated 200 tonnes of highly radioactive material.

However that shelter was not designed for the very long-term, and so the New Safe Confinement – the largest moveable land-based structure ever built – was constructed to cover a much larger area including the original shelter. The New Safe Confinement has a span of 257 metres, a length of 162 metres, a height of 108 metres and a total weight of 36,000 tonnes and was designed for a lifetime of about 100 years. It was built nearby in two halves which were moved on specially constructed rail tracks to the current position, where it was completed in 2019.

With the new NSC in place there have been plans to make safe and dismantle the original shelter. However, the New Safe Confinement was damaged by a drone strike last year, and there is an on-going assessment and project to put together a plan to restore its full protective functionality.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    China Added 200,000 Bpd to Crude Reserves in July Despite Hormuz Crisis

    • August 17, 2026
    China Added 200,000 Bpd to Crude Reserves in July Despite Hormuz Crisis

    Japan’s Oil Crisis Eases, But the Import Bill Keeps Climbing

    • August 17, 2026
    Japan’s Oil Crisis Eases, But the Import Bill Keeps Climbing

    Iraq-Syria Oil Pipeline to Bypass Hormuz Is 4 Years and $15 Billion Away

    • August 17, 2026
    Iraq-Syria Oil Pipeline to Bypass Hormuz Is 4 Years and $15 Billion Away

    China’s Renewables Boom Faces Record Clean Power Curtailments

    • August 17, 2026
    China’s Renewables Boom Faces Record Clean Power Curtailments

    Diversifying helium: Can dedicated projects reshape global supply?

    • August 17, 2026
    Diversifying helium: Can dedicated projects reshape global supply?

    Hormuz Tanker Traffic Slows to a Trickle

    • August 17, 2026
    Hormuz Tanker Traffic Slows to a Trickle

    India Lets Delayed Renewable Projects Pay to Keep Grid Access

    • August 17, 2026
    India Lets Delayed Renewable Projects Pay to Keep Grid Access

    Indian Oil Giant Secures U.S. License to Return to Venezuela

    • August 17, 2026
    Indian Oil Giant Secures U.S. License to Return to Venezuela

    Asian Refiners Seek Alternative Pickup Point for Saudi Crude

    • August 17, 2026
    Asian Refiners Seek Alternative Pickup Point for Saudi Crude

    India’s Chief Economic Adviser Calls for Return of E10 Petrol

    • August 17, 2026
    India’s Chief Economic Adviser Calls for Return of E10 Petrol