Assam Introduces Draft Regulations 2025 For Intra-State Transmission Connectivity: Streamlining Power Integration And Reliability

Representational image. Credit: Canva

The Assam Electricity Regulatory Commission (AERC) has introduced the Draft Regulations for Grant of Connectivity to the Intra-State Transmission System (InSTS), 2025. These regulations aim to facilitate the integration of entities into the state transmission system effectively, reliably, and economically. They emphasize healthy competition in electricity generation and supply while ensuring system security. The rules will take effect from April 1, 2025, covering all applications for connectivity submitted to the State Transmission Utility (STU) from this date onward.

The regulations outline eligibility criteria for entities seeking connectivity to InSTS. Entities such as power-generating stations, renewable energy generators, and distribution licensees are eligible to apply. Additionally, trading licensees and energy storage systems (ESS) are also covered. Applications must comply with specific requirements, including submission of technical and financial details. Applicants are also required to provide bank guarantees, termed Conn-BG1, Conn-BG2, and Conn-BG3, which vary based on the voltage level and augmentation needs.

Connectivity is granted after a thorough interconnection study conducted by the Nodal Agency. This study assesses the existing system’s adequacy and identifies any augmentation required for transferring power. If no augmentation is needed, connectivity is granted within 45 days; otherwise, it takes up to 90 days. Applicants must adhere to technical standards and enter into agreements for the construction, operation, and maintenance of dedicated transmission lines and terminal bays.

The regulations permit the transfer of connectivity rights under specific conditions, such as within subsidiaries or between parent companies. Renewable energy generators can split their connectivity among different capacities post-commercial operation. Entities relinquishing their connectivity must provide advance notice and may incur charges proportional to their relinquished quantum.

In case of project delays or cancellations, connectivity can be revoked. Bank guarantees submitted by applicants may be encashed to cover costs or settle outstanding transmission charges. The Nodal Agency monitors the implementation of works under its purview, ensuring timely updates and corrective actions.

For effective metering and data transmission, applicants must develop infrastructure for real-time communication with the State Load Dispatch Centre (SLDC). The regulations also allow the injection of infirm power and the drawal of start-up power under prescribed conditions. Detailed procedures and formats for applications, agreements, and updates are to be finalized within three months of notification of these regulations.

These comprehensive measures aim to streamline connectivity processes, enhance transparency, and support the growing demand for reliable power in Assam. The framework also ensures the optimal utilization of transmission systems while accommodating future growth and advancements in energy technologies.

 

  • Related Posts

    LONGi Receives The EUPD Top Innovation Award 2026 for the Hi-MO One Pro Commercial Storage System

    LONGi received the EUPD Top Innovation Award 2026 in the storage category for the European region. The distinction acknowledges the Hi-MO One Pro energy storage system. EUPD Group chief executive…

    Department of Energy Announces $17.5 Billion Loan Commitment To Accelerate 10 New Nuclear Reactors In The U.S.

    The U.S. Department of Energy (DOE) has announced a major step to strengthen the country’s nuclear energy sector by offering a conditional loan commitment worth $17.5 billion. The funding, provided…

    Have You Seen?

    Sasol, Topsoe to dissolve Zaffra SAF joint venture

    • June 26, 2026
    Sasol, Topsoe to dissolve Zaffra SAF joint venture

    Canada waste-to-energy project grapples with carbon price pressures

    • June 26, 2026
    Canada waste-to-energy project grapples with carbon price pressures

    PowerCell wins 4MW contract to power Norwegian liquid hydrogen cargo ships

    • June 26, 2026
    PowerCell wins 4MW contract to power Norwegian liquid hydrogen cargo ships

    Major Saudi Oil Terminal Roars Back to Life as Gulf Supply Recovery Accelerates

    • June 26, 2026
    Major Saudi Oil Terminal Roars Back to Life as Gulf Supply Recovery Accelerates

    Gas Prices Are Falling. Your July 4 Fill-Up Still Won’t Feel Cheap.

    • June 26, 2026
    Gas Prices Are Falling. Your July 4 Fill-Up Still Won’t Feel Cheap.

    SpaceX Wants to Fuel Its Mars Ambitions With Its Own Gas Pipeline

    • June 26, 2026
    SpaceX Wants to Fuel Its Mars Ambitions With Its Own Gas Pipeline

    Oil Heads for Weekly Loss as Hormuz Tanker Traffic Rebounds

    • June 26, 2026
    Oil Heads for Weekly Loss as Hormuz Tanker Traffic Rebounds

    Qatar’s LNG Recovery Picks Up Speed as Tankers Mass at Ras Laffan

    • June 26, 2026
    Qatar’s LNG Recovery Picks Up Speed as Tankers Mass at Ras Laffan

    Why Is Oil Trading Down Today?

    • June 26, 2026
    Why Is Oil Trading Down Today?

    Security and sustainability clash in Ireland FSRU plans

    • June 26, 2026
    Security and sustainability clash in Ireland FSRU plans