First Taipingling unit enters commercial operation

On 19 April, the 1116 MWe (net) domestically-designed pressurised water reactor completed a series of commissioning tests, including a test run lasting 168 hours, China General Nuclear (CGN) said.

The Taipingling plant will eventually have six Hualong One reactors, with a total investment exceeding CNY120 billion (USD17 billion). The construction of the first and second units began in 2019 and 2020, respectively. Hot testing of unit 1 was completed in September 2024, with that of unit 2 completed in July 2025.


(Image: CGN)

Taipingling 1 received an operating licence from the Ministry of Ecology and Environment on 24 December last year. The loading of the first fuel assemblies began at the unit later that day following approval from the National Nuclear Safety Administration. A total of 177 fuel assemblies were loaded into the reactor’s core. It attained a sustained chain reaction for the first time (referred to as first criticality) on 3 February and was connected to the grid on 13 February.

“After its official commissioning, the unit will generate over 9 billion kilowatt-hours of electricity annually, enough to meet the electricity needs of one million residents in the Greater Bay Area,” CGN said. “This clean energy output is equivalent to reducing carbon dioxide emissions by approximately 8.4 million tonnes annually and afforesting 20,000 hectares.”

Construction of the second phase of the Taipingling plant – units 3 and 4 – was approved by China’s State Council in December 2023, with construction of unit 3 getting under way in June last year.

“After Taipingling unit 1 is put into commercial operation, the number of nuclear power generating units in operation managed by the company (including associates) will increase to 29 units and the installed capacity of nuclear power generating units in operation will also increase from 31,838 MW to 33,040 MW,” CGN noted.

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    • June 23, 2026
    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    • June 23, 2026
    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    Europe’s Battery Storage Installations Set to Quadruple by 2030

    • June 23, 2026
    Europe’s Battery Storage Installations Set to Quadruple by 2030

    Tankers Emerge from Dark Mode amid Tentative Hormuz ReopeningTankers Emerge from

    • June 23, 2026
    Tankers Emerge from Dark Mode amid Tentative Hormuz ReopeningTankers Emerge from

    Ballard’s GeoPura buy marks business model shift from hydrogen equipment seller

    • June 23, 2026
    Ballard’s GeoPura buy marks business model shift from hydrogen equipment seller

    Posco opens rare gas plant for South Korean semiconductor market

    • June 23, 2026
    Posco opens rare gas plant for South Korean semiconductor market

    Oil Steady as Investors Focus on Hormuz Flows After Peace Talks

    • June 23, 2026
    Oil Steady as Investors Focus on Hormuz Flows After Peace Talks

    US Gasoline Prices Tumble for Sixth Straight Week

    • June 23, 2026
    US Gasoline Prices Tumble for Sixth Straight Week