USA completes final deliveries for ITER’s central solenoid

The most recent deliveries included busbars and leads for electrical connections between the modules; earlier, all magnet modules, support structures, and tooling components had been delivered.

The central solenoid magnet consists of six individual sections, or modules, each wound from about 6 kilometres of niobium-tin superconducting cable and weighing more than 122.5 tonnes. Each module required more than two years to fabricate, followed by testing, and then shipment to France. As part of ITER’s strategy to build redundancy into mission-critical systems, a full spare module was manufactured to reduce technical and schedule risk. It will be deployed only if a problem emerges with one of the six modules already on site. The 15-year project to produce the modules was completed inside General Atomics’ Magnet Technologies Center in Poway, California.

The 18-metre-tall, 4.25-metre-wide magnet is now under assembly at the ITER site. Five of six modules are stacked, with the final module – delivered in September – to be added later this year. Assembly is the responsibility of the ITER Organization, with additional technical support provided through an agreement with the US ITER project team based at Oak Ridge National Laboratory.

Once all six modules are in place, a compression structure, tasked with applying downward precompression on the module stack, will be put in place. The completed central solenoid will then remain on its platform in the Assembly Hall until all nine vacuum vessel sector modules are installed, and then will be moved into the centre of the tokamak pit.

US ITER has also delivered the ‘exoskeleton’ support structure that will enable the central solenoid to withstand the extreme forces it will generate. The exoskeleton is comprised of more than 9000 individual parts, manufactured by eight US suppliers.

ITER’s central solenoid will generate most of the magnetic flux charge of the plasma, initiating the initial plasma current and contributing to its maintenance.

“The completion of the central solenoid magnet highlights the capability of the United States to design and deliver the world’s most complex fusion systems,” said Kevin Freudenberg, US ITER Interim Project Director. “Congratulations to the entire team who contributed, including those here at Oak Ridge National Laboratory who led the work, and our suppliers who fabricated critical components.”

ITER’s magnetic system consists of toroidal and poloidal magnetic field coils, correction coils, and the central solenoid. This is the largest superconducting system ever created. The fully assembled pulsed magnetic system will weigh almost 3000 tonnes.

ITER is a major international project to build a tokamak fusion device designed to prove the feasibility of fusion as a large-scale and carbon-free source of energy. The goal of ITER is to operate at 500 MW (for at least 400 seconds continuously) with 50 MW of plasma heating power input. It appears that an additional 300 MWe of electricity input may be required in operation. No electricity will be generated at ITER.

Thirty-five nations are collaborating to build ITER – the European Union is contributing almost half of the cost of its construction, while the other six members (China, India, Japan, South Korea, Russia and the USA) are contributing equally to the rest. Construction began in 2010 and the original 2018 first plasma target date was put back to 2025 by the ITER council in 2016. However, in June 2024, a revamped project plan was announced which aims for “a scientifically and technically robust initial phase of operations, including deuterium-deuterium fusion operation in 2035 followed by full magnetic energy and plasma current operation”.

   

  • Related Posts

    Podcast: World Nuclear Symposium 2026

    People featured, in order of appearance: Sama Bilbao y León, Director General, World Nuclear Association Mark Muldowney, MD, Energy, Resources and Infrastructure, BNP Paribas Alejandro López Delgado, Managing Director, Infrastructure,…

    Hydraulic tests completed at Turkey’s Akkuyu 1

    During the tests, the pressure in the primary circuit (the reactor, main circulation pumps, steam generators, the pressuriser, and the main circulation pipeline connecting them) was increased to 24.5 MPa…

    Have You Seen?

    Crude Oil is Underpriced, Energy Aspects Says

    • October 9, 2026
    Crude Oil is Underpriced, Energy Aspects Says

    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    • October 9, 2026
    Petronas to Raise Malaysia Dividend 19% to $7.8 Billion for 2027

    129 Gulf Platforms Evacuated as Isaias Gets Stronger

    • October 9, 2026
    129 Gulf Platforms Evacuated as Isaias Gets Stronger

    Lessons from Covid: Achieving resilience in medical oxygen supply

    • October 9, 2026
    Lessons from Covid: Achieving resilience in medical oxygen supply

    Australia Close to Finalizing Gas Reservation Plan for LNG Exporters

    • October 9, 2026
    Australia Close to Finalizing Gas Reservation Plan for LNG Exporters

    Hormuz Crisis Leaves EU Gas Storage Short Heading Into Winter

    • October 9, 2026
    Hormuz Crisis Leaves EU Gas Storage Short Heading Into Winter

    Asian Refiners Ditch U.S. Oil as Supertanker Rates Hit $82 Million

    • October 9, 2026
    Asian Refiners Ditch U.S. Oil as Supertanker Rates Hit $82 Million

    Samruk-Energy And O-GREEN Partner To Develop 2 GW Solar And Wind Projects Across Kazakhstan And Global Markets

    • October 9, 2026
    Samruk-Energy And O-GREEN Partner To Develop 2 GW Solar And Wind Projects Across Kazakhstan And Global Markets

    Africa GreenCo And AXIAN Group Sign PPA For 200 MW Kudu Solar Project In Zambia

    • October 9, 2026
    Africa GreenCo And AXIAN Group Sign PPA For 200 MW Kudu Solar Project In Zambia

    US DOW awards conditional $1.5bn loan to bandgap semiconductor firm

    • October 9, 2026
    US DOW awards conditional $1.5bn loan to bandgap semiconductor firm