Nuclear fuel loading completed at Rooppur 1

The loading of the fuel began on 28 April, and is a key step as the plant moves towards generating its first electricity.

Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh, said: “The work was conducted in strict compliance with the initial core loading programme, process regulations, and nuclear safety standards. The next stage is installing the upper reactor unit and connecting all necessary in-core instrumentation systems. We will conduct hundreds of further tests to prove the reliable and safe operation of all process systems.”

The reactor is expected to be brought to its minimum controllable power level “in the near future”, with tests and checks taking place before the power start-up – with further tests and checks before power levels are increased – and trial commercial operation of the unit.

Background

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March last year, Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, followed by hot functional tests. An operating licence was issued by the Bangladesh Nuclear Regulatory Authority on 16 April.

   

  • Related Posts

    Supply chain challenges prompt Cigar Lake suspension

    “Orano’s McClean Lake mill has encountered operational challenges with its sulphuric acid plant that caused it to shut down in order to repair the issue. Orano is currently working to…

    Action needed to achieve tripling of global nuclear capacity target, says NEA

    The report – – assesses the current status and future trajectory of nuclear generating capacity worldwide. The goal of at least tripling global nuclear capacity – currently almost 400 GWe – by…

    Have You Seen?

    EWE breaks ground on 24km hydrogen pipeline from 320MW electrolyser

    • July 3, 2026
    EWE breaks ground on 24km hydrogen pipeline from 320MW electrolyser

    Coal India Secures LOA for 600 MW Solar Power Project at Jalaun Solar Park in Uttar Pradesh

    • July 3, 2026
    Coal India Secures LOA for 600 MW Solar Power Project at Jalaun Solar Park in Uttar Pradesh

    APTEL Allows Delayed Appeal In 300 MW Solar Project Dispute With Cost Penalty

    • July 3, 2026
    APTEL Allows Delayed Appeal In 300 MW Solar Project Dispute With Cost Penalty

    Jinko Solar’s Kazhimukhan Amangaliev on Driving Greater Value with Tiger Neo 3.0

    • July 3, 2026
    Jinko Solar’s Kazhimukhan Amangaliev on Driving Greater Value with Tiger Neo 3.0

    Trump Administration Advances New California Oil Lease Plans

    • July 3, 2026
    Trump Administration Advances New California Oil Lease Plans

    Renfra Energy India Files INR430 Crore IPO Papers With SEBI To Expand Renewable Energy Business

    • July 3, 2026
    Renfra Energy India Files INR430 Crore IPO Papers With SEBI To Expand Renewable Energy Business

    Adani Green Commissions 150 MW Solar, 156 MW Wind, and 185 MWh BESS Projects At Khavda In Gujarat

    • July 3, 2026
    Adani Green Commissions 150 MW Solar, 156 MW Wind, and 185 MWh BESS Projects At Khavda In Gujarat

    CERC Orders Return Of INR214 Crore Bank Guarantee To APDCL After Assam 750 MW Solar Project Suspension

    • July 3, 2026
    CERC Orders Return Of INR214 Crore Bank Guarantee To APDCL After Assam 750 MW Solar Project Suspension

    ACWA Power Signs Landmark Agreements for 230 MW N’diago CCGT Power Plant, Advancing Mauritania’s Power Sector Reform

    • July 3, 2026
    ACWA Power Signs Landmark Agreements for 230 MW N’diago CCGT Power Plant, Advancing Mauritania’s Power Sector Reform

    CERC Grants Extension For 300 MW Solar Project Land Compliance In Gujarat

    • July 3, 2026
    CERC Grants Extension For 300 MW Solar Project Land Compliance In Gujarat