Wyoming uranium project ramp-up ‘slower than anticipated’

Production ramp-up at the project, which returned to operation as a low-pH in-situ recovery (ISR) operation in 2024 after a five-year hiatus, has progressed more slowly than originally anticipated, Peninsula said, “and, as a result, the Company’s previously announced CY2026 (calendar year) production guidance of 400,000 to 500,000 pounds of U3O8 will not be achieved and is therefore withdrawn”.

ISR – also known as solution mining, or in situ leach (ISL) – involves recovering minerals from a suitable orebody by dissolving them and pumping the pregnant solution to the surface where the minerals can be recovered. The choice of leaching solution – acidic or alkaline – depends on the geology of the ore: an acidic (low-pH) solution gives higher uranium recovery with lower operating costs than an alkaline leach, but cannot be used if significant quantities of acid-consuming minerals such as gypsum and limestone are present in the host aquifers. 

Until operations were suspended in 2019, Lance – like other ISR operations in the USA – had used the high-pH method, but this was delivering lower than expected recoveries of uranium. Following studies and field trials, the company decided in 2022 that it would return to operations using a low-pH recovery process. 

As Lance is the first commercial-scale application of low-pH ISR uranium recovery in the USA, there has been “minimal domestic operating experience, established workforce capability or industry knowledge on which to draw”, the company said. Although “meaningful operational progress has been achieved”, the company said it “continues to encounter a number of operational challenges, including resolution of gas generation within sections of the wellfield taking longer than expected, resulting in lower-than expected solution flow rates, and the ongoing optimisation of wellfield chemistry”.

Peninsula Energy Managing Director and CEO George Bauk said the company is “naturally disappointed” by the slower-than-exepected ramp-up and the decision to withdraw its production guidance, but added that the year has delivered valuable operating experience and important insights as Lance transitions into a large-scale low-pH ISR operation. “While the transition has presented a steeper operational learning curve than we originally anticipated, the challenges we have encountered relate primarily to the wellfield hydraulics, solution flow and chemistry optimisation – not the quality of the uranium resource or the effectiveness of the low-pH recovery process itself,” he said. “The encouraging aspect is that the underlying fundamentals continue to validate our long-term strategy.”

Wellfield and uranium capture operations at the project resumed in December 2024, with the first dried yellowcake from the expanded Lance Central Processing Plant produced the following September.

   

  • Related Posts

    Containment tests completed at Lufeng unit 5

    The two-part tests, which began on 29 August, confirm that the containment vessel meets design and construction quality requirements. The first part – the structural integrity test – involved the…

    Natural draft cooling tower is preferred JEK2 option

    The results of the feasibility study were released as part of the latest reports made public before the country prepares for a planned referendum on new nuclear. Bruno Glaser, Technical…

    Have You Seen?

    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    • September 19, 2026
    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    Vedanta Aluminium Prepares for Rising Demand for Specialised Aluminium in India’s Power Grid Expansion

    • September 19, 2026
    Vedanta Aluminium Prepares for Rising Demand for Specialised Aluminium in India’s Power Grid Expansion

    GEON Commissions 10 MW/20 MWh BESS Project In Phalodi, Rajasthan

    • September 19, 2026
    GEON Commissions 10 MW/20 MWh BESS Project In Phalodi, Rajasthan

    Suzlon Energy Allots 6.4 Lakh Equity Shares Under ESOP 2022, Paid-Up Capital Rises to INR 2,749.26 Crore

    • September 19, 2026
    Suzlon Energy Allots 6.4 Lakh Equity Shares Under ESOP 2022, Paid-Up Capital Rises to INR 2,749.26 Crore

    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    • September 19, 2026
    NTPC Green Energy Commissions 68.22 MW Solar Capacity At Dahod Project In Gujarat

    INEOS Opens EU’s First Full-Scale Carbon Storage Site in Denmark

    • September 19, 2026
    INEOS Opens EU’s First Full-Scale Carbon Storage Site in Denmark

    Strait of Hormuz oil shipments hit six-month high, U.S. commander says

    • September 19, 2026
    Strait of Hormuz oil shipments hit six-month high, U.S. commander says

    LNG Tankers Push Through Hormuz Again as Qatar, UAE Fight Supply Crunch

    • September 18, 2026
    LNG Tankers Push Through Hormuz Again as Qatar, UAE Fight Supply Crunch

    Hormuz Tanker Traffic Slumps as Saudi Arabia Scrambles for New Oil Routes

    • September 18, 2026
    Hormuz Tanker Traffic Slumps as Saudi Arabia Scrambles for New Oil Routes

    India’s Clean Energy Boom Halts Coal Power Growth

    • September 18, 2026
    India’s Clean Energy Boom Halts Coal Power Growth