Testing under way for Atucha 2’s dry storage facility equipment

The ASECG II (Almacenamiento en Seco de Combustibles Gastados de Atucha II) facility is seen as a key part of the necessary work for the long-term operation of the unit.

When complete, it will have the capacity to store up to 50,000 used fuel elements safely and securely on the plant site, and includes a passive ventilation system that maintains the temperature of the elements within safe ranges without requiring electricity or human intervention, Nucleoelectrica said.

Used fuel is generally stored under water for at least five years – and often much longer – once it is removed from reactors, after which it will have cooled and will not emit as much radiation.

At Atucha 2, the cooling ponds are likely to be full by the end of next year and Nucleoelectrica says the new facility is needed to ensure the plant can remain operational.

Among equipment being tested is the gantry crane, which will be needed to safely and accurately move containers within the facility. It was developed by IMPSA, based on a technical specification from Nucleoelectrica, and was delivered at the end of 2025. Installation and commissioning was scheduled to take place over a four-month period.

A dry fuel storage facility for the Atucha 1 nuclear power plant was opened in 2022 to store fuel assemblies used in the pressurised heavy water reactor.

Background

Atucha II is a 693 MWe pressurised heavy water reactor and was ordered in 1979. It was a Siemens design, a larger version of the first unit at Atucha, and construction started in 1981 by a joint venture of Argentina’s National Atomic Energy Commission (CNEA) and Germany’s Siemens-Kraftwerk Union. However, work proceeded slowly due to lack of funds and was suspended in 1994 with the plant 81% complete.

In 1994, Nucleoeléctrica Argentina was set up to take over the nuclear power plants from CNEA and oversee construction of Atucha II. In 2003, plans for completing Atucha II were presented to the government. The government announced a strategic plan in August 2006 for the country’s nuclear power sector, including completion of Atucha II. The unit was effectively completed in September 2011. First criticality was achieved early in June 2014, and grid connection was later that month, with full power in February 2015.

In May this year the Autoridad Regulatoria Nuclear issued a renewed 10-year operating licence until May 2036.

   

  • Related Posts

    Newcleo-led consortium to develop floating nuclear plant

    The consortium – which includes classification society Bureau Veritas Marine & Offshore and French engineering company ABMI Groupe – was selected under the call-for-projects “Supporting the decarbonisation of the French…

    Welding of Akkuyu 2’s primary circuit completed

    The welding of the main coolant pipeline at the Turkish site was completed in 73 days and included 32 pipeline joints, which all underwent a high-temperature treatment, with special surfacing…

    Have You Seen?

    India Surpasses 300 GW of Non-Fossil Power Capacity

    • August 28, 2026
    India Surpasses 300 GW of Non-Fossil Power Capacity

    Pakistan’s Five Refineries Set for $6 Billion Upgrade Push

    • August 28, 2026
    Pakistan’s Five Refineries Set for $6 Billion Upgrade Push

    Amazon Nears 1 GW of Wind Power in Sweden With Four New Deals

    • August 28, 2026
    Amazon Nears 1 GW of Wind Power in Sweden With Four New Deals

    Qatar Extends Force Majeure as Hormuz Crisis Still Blocks LNG Traffic

    • August 28, 2026
    Qatar Extends Force Majeure as Hormuz Crisis Still Blocks LNG Traffic

    India and Indonesia look to strengthen semiconductor ties

    • August 28, 2026
    India and Indonesia look to strengthen semiconductor ties

    Woodside receives final Pluto LNG train 1 module

    • August 28, 2026
    Woodside receives final Pluto LNG train 1 module

    Interlune recreates lunar helium in simulant for Earth-based extraction testing

    • August 28, 2026
    Interlune recreates lunar helium in simulant for Earth-based extraction testing

    Trump Sends Saudi Nuclear Deal to Congress as Riyadh Rejects Israel Condition

    • August 28, 2026
    Trump Sends Saudi Nuclear Deal to Congress as Riyadh Rejects Israel Condition

    U.S. In Talks To Take Direct Ownership Of Venezuelan Oil Fields

    • August 28, 2026
    U.S. In Talks To Take Direct Ownership Of Venezuelan Oil Fields

    Oil Prices Head for a Weekly Loss Despite Escalating Iran Tensions

    • August 28, 2026
    Oil Prices Head for a Weekly Loss Despite Escalating Iran Tensions