APTEL Rules In Favor Of Solar Developer Ordering NTPC To Refund Liquidated Damages For 140 MW Projects

Representational image. Credit: Canva

The Appellate Tribunal for Electricity (APTEL) has delivered a judgment in favor of Solaire Surya Urja Private Limited, a solar power developer in Rajasthan, against NTPC Limited and other entities. The case arose from a dispute over the delay in the commissioning of two solar power projects with a total capacity of 140 MW. The company had sought an extension of the Scheduled Commercial Operation Date (SCOD) due to the non-availability of the required evacuation transmission infrastructure, which was under the responsibility of Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL).

The appellant had entered into Power Purchase Agreements (PPAs) with NTPC in May 2016, under which the projects were scheduled to be commissioned by June 1, 2017. However, the company faced delays due to the absence of an adequate evacuation system, which prevented it from injecting power into the grid. Despite its repeated communications regarding the issue, NTPC imposed liquidated damages on the company for the delay in supplying power.

The Central Electricity Regulatory Commission (CERC), in its August 2021 order, had ruled against the appellant, holding it liable for the delay and allowing NTPC to recover liquidated damages. Dissatisfied with the decision, the company filed an appeal before APTEL.

APTEL reviewed the case and acknowledged that the delay was caused by factors beyond the control of the solar power developer. The tribunal observed that RRVPNL had not provided the necessary evacuation infrastructure in time and had even restricted the company from injecting power into the grid without prior approval. The tribunal noted that the appellant had commissioned parts of the projects much earlier but was unable to commence power supply due to the transmission constraints.

APTEL further examined the contractual clauses under the PPAs and concluded that the appellant was entitled to an extension of the SCOD under the force majeure provisions. It ruled that the appellant could not be penalized for a delay caused by external factors, such as the non-availability of the transmission system. The tribunal set aside CERC’s order and directed NTPC to refund the liquidated damages amount, if any, collected from the appellant.

The judgment highlights the importance of proper infrastructure planning for renewable energy projects and emphasizes that developers should not be penalized for delays caused by deficiencies in government agencies’ responsibilities. The ruling sets a precedent for similar cases where transmission constraints hinder the timely commissioning of renewable energy projects. The decision also reinforces the need for coordination between power developers and transmission utilities to ensure smooth project execution.

 

  • Related Posts

    Indian Green Energy Stocks Show Mixed Performance As Sensex And Nifty End Higher On June 24

    Professionals analyze rising trends in Indian green energy stocks in a modern office. The Indian stock market ended on a positive note on June 24, 2026, with both benchmark indices…

    Week in South East Asia: Meralco-MGEN Eye 2.5 GW RE Project; Novva Buys 120 MWp Solar Asset; TotalEnergies ENEOS Expands Rooftop Solar and More…

    Representational image. Credit: Canva Meralco PowerGen Corporation (MGEN), Meralco, and Vietnam-based VinEnergo have signed an agreement to explore a 2.5 GW renewable energy project in the Philippines. The proposed development…

    Have You Seen?

    Rubio on Gulf Tour as Allies Sceptical About Iran Deal Seek Answers

    • June 24, 2026
    Rubio on Gulf Tour as Allies Sceptical About Iran Deal Seek Answers

    U.S. Crude Stocks at Cushing Hit Near 12-Year Low, Fuel Inventories Rise, EIA

    • June 24, 2026
    U.S. Crude Stocks at Cushing Hit Near 12-Year Low, Fuel Inventories Rise, EIA

    Iran, Oman to Coordinate Hormuz Transits

    • June 24, 2026
    Iran, Oman to Coordinate Hormuz Transits

    Adani Targets 10 GW Nuclear Power Capacity in India by 2035

    • June 24, 2026
    Adani Targets 10 GW Nuclear Power Capacity in India by 2035

    UK Climate Panel Urges Faster Electrification to Lower Energy Bills

    • June 24, 2026
    UK Climate Panel Urges Faster Electrification to Lower Energy Bills

    VLCC Earnings Near $470,000 a Day as Hormuz Hopes Drive Tanker Frenzy

    • June 24, 2026
    VLCC Earnings Near $470,000 a Day as Hormuz Hopes Drive Tanker Frenzy

    Oil Extends Losses on Expectations of Smoother Crude Flows via Hormuz

    • June 24, 2026
    Oil Extends Losses on Expectations of Smoother Crude Flows via Hormuz

    US CFOs in Survey Say Firms Mostly Absorbed Oil Price Shock

    • June 24, 2026
    US CFOs in Survey Say Firms Mostly Absorbed Oil Price Shock

    Global Physical Crude Markets Mired in Discounts as Middle East Ramps Up Supply

    • June 24, 2026
    Global Physical Crude Markets Mired in Discounts as Middle East Ramps Up Supply

    CarbonX CO2 electrolysis prize fund winner plots scale up timelines

    • June 24, 2026
    CarbonX CO2 electrolysis prize fund winner plots scale up timelines