Hot testing of Chinese SMR under way

Hot functional tests involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Carried out before the loading of nuclear fuel, such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

A  says these tests are now under way at the ACP100 – also referred to as the Linglong One – with the aim of loading fuel into the reactor within the year.

Background

China National Nuclear Corporation (CNNC) announced in July 2019 the launch of a project to construct an ACP100 SMR at Changjiang. The site is already home to two operating CNP600 pressurised water reactors (PWRs), while the construction of two Hualong One units began in March and December 2021. The first of these Hualong One units entered commercial operation last month, with the second scheduled to follow early next year.

First concrete for the ACP100 was poured on 13 July 2021, with a planned total construction period of 58 months. Equipment installation work commenced in December 2022 and the main internal structure of the reactor building was completed in March 2023. The outer containment dome was hoisted into place in February last year.

Cold functional tests – carried out to confirm whether components and systems important to safety are properly installed and ready to operate in cold conditions – were completed in October last year. The main purpose of those tests was to verify the leak-tightness of the primary circuit and components – such as pressure vessels, pipelines and valves of both the nuclear and conventional islands – and to clean the main circulation pipes. The tests mark the first time the reactor systems were operated together with the auxiliary systems.

Under development since 2010, the 125 MWe ACP100 integrated PWR’s preliminary design was completed in 2014. In 2016, the design became the first SMR to pass a safety review by the International Atomic Energy Agency.

Once completed, the Changjiang ACP100 reactor will be capable of producing 1 billion kilowatt-hours of electricity annually, enough to meet the needs of 526,000 households. The reactor is designed for electricity production, heating, steam production or seawater desalination.

   

  • Related Posts

    Kairos Power automates fuel pebble inspections

    The automated quality control and tracking system supports Kairos Power’s iterative approach to fuel development by streamlining throughput, strengthening material accountability, and generating data that can inform future pebble manufacturing…

    US maritime nuclear firm Bluecore Energy announces uranium purchase

    The uranium hexafluoride, which is enriched to 4.95% uranium-235, is currently held at “a US nuclear fuel facility outside the state of California”, Bluecore Energy said, without giving details about…

    Have You Seen?

    Oman Overtakes U.S. as India’s Top LNG Supplier in September

    • October 14, 2026
    Oman Overtakes U.S. as India’s Top LNG Supplier in September

    Aramco’s New Chinese JV Refinery Gets First Saudi Crude Cargo

    • October 14, 2026
    Aramco’s New Chinese JV Refinery Gets First Saudi Crude Cargo

    Russian Strikes Cut Power to 600,000 Ukrainians Days After U.S. Diesel Deal

    • October 14, 2026
    Russian Strikes Cut Power to 600,000 Ukrainians Days After U.S. Diesel Deal

    India’s Gas Demand Drops as Iran War Hikes LNG Spot Prices

    • October 14, 2026
    India’s Gas Demand Drops as Iran War Hikes LNG Spot Prices

    IWDC names Chris Stout as Executive Vice-President

    • October 14, 2026
    IWDC names Chris Stout as Executive Vice-President

    Veterinary sector draws lessons from Covid oxygen shortages

    • October 14, 2026
    Veterinary sector draws lessons from Covid oxygen shortages

    Trio aims to build Singapore’s bioLNG bunkering capabilities

    • October 14, 2026
    Trio aims to build Singapore’s bioLNG bunkering capabilities

    MMA Proposes 2nd Alaska Oil, Gas Lease Sale

    • October 14, 2026
    MMA Proposes 2nd Alaska Oil, Gas Lease Sale

    Taiwan Commits Up to $4.4 Billion to Alaska LNG Megaproject

    • October 14, 2026
    Taiwan Commits Up to $4.4 Billion to Alaska LNG Megaproject

    Saudi Aramco Headquarters Hit as Houthi Attacks Escalate

    • October 14, 2026
    Saudi Aramco Headquarters Hit as Houthi Attacks Escalate