Bruce 4 defuelled in record time

Friday, 28 February 2025

Bruce 4 defuelled in record time
(Image: Bruce Power)

Bruce unit 4 began its Major Component Replacement – or MCR – outage earlier this month. It is the third of six units at the Bruce site in Ontario to undergo MCR, which involves removing and replacing key reactor components including steam generators, pressure tubes, calandria tubes and feeder tubes, adding 30-35 years to the reactor’s operating life.

The first unit to undergo MCR, Bruce unit 6, took 46 days to complete defueling, and the second – Bruce unit 3 – took 29 days. Each successive MCR has leveraged innovation and lessons learned from the previous projects, said Bruce A Plant Manager Lucas Van Wieringen. “Our private investments in state-of-the-art innovative modifications to improve safety and efficiency of our defuel campaign set our teams up for success,” he said. “Our continued focus on proficiency of our workforce and a high-quality schedule through planning and preparation will enable us to continue to build momentum in our Life-Extension Program.”

The next major milestone for the Bruce 4 MCR project is the chemical decontamination of the Primary Heat Transport (PHT) system prior to the start of construction activity, which begins with major component disassembly. Lessons learned from the first MCR outage at Bruce 6 led to the development of an innovative approach, with chemical decontamination of the PHT system at low level drain state, before the start of work at Bruce 3. This innovation, which reduces dose rates, will also be applied in unit 4.

The renewed unit will be loaded with new fuel bundles ahead of its restart in 2027.

Bruce Power will see overlapping MCR outages until 2033 in a CAD13 billion (USD9 billion) refurbishment that is one of the largest infrastructure projects in Canada.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    Middle East Oil Tankers Are Going Dark for Longer

    • August 14, 2026
    Middle East Oil Tankers Are Going Dark for Longer

    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    • August 14, 2026
    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    • August 14, 2026
    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    • August 14, 2026
    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    Holcim UAE starts cement carbon capture pilot project

    • August 14, 2026
    Holcim UAE starts cement carbon capture pilot project

    Qatar Ras Laffan train five ‘goes offline’

    • August 14, 2026
    Qatar Ras Laffan train five ‘goes offline’

    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    • August 14, 2026
    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn