UK Fast-Tracks $5-Billion in Grid Infrastructure Investments

UK Fast-Tracks $5-Billion in Grid Infrastructure Investments | OilPrice.com

`;
document.write(write_html);
}

Breaking News:

ByTsvetana Paraskova– Mar 20, 2025, 8:00 AM CDT
Grid

image

The UK’s energy regulator, Ofgem, on Thursday said a new set of rules are granting early access to nearly $5.18 billion (£4 billion) of investment for crucial transmission equipment and services, which is expected to connect renewable energy projects to the grid quicker.

Ofgem’s new Advanced Procurement Mechanism (APM) will unblock supply chains by allowing Britain’s electricity transmission owners (TOs) to buy essential equipment – such as switchgear, cables, and steel – years in advance of when it is needed.

‘;
document.write(write_html);
}

The process to unblock supply chains is expected to ensure that approved projects would be ready to break ground as soon as planning approval is granted. This in turn would allow transmission owners to avoid delays, control costs, and attract international investment in the drive to net zero, Ofgem said.

“Across the world many countries are stepping up their investment in clean energy at the same time, putting unprecedented pressure on the supply chain as growing demand for essential materials forces up prices and lengthens delivery times,” said Akshay Kaul, Director General, Infrastructure, for Ofgem.

“This is why it’s vital that we help the electricity transmission owners move quickly, procuring at scale as early as possible to reduce financial risk.”

Energy Minister Michael Shanks commented, “This fast-track measure means we can quickly get Britain building the infrastructure we need to deliver clean power by 2030 and an energy system that can bring down bills for households and businesses for good.”

Ofgem is currently seeking feedback on proposed changes to the grid connection policy from a first-come first-served approach to prioritizing projects where generation capacity is needed the most and projects are at a more advanced stage of development. 

The UK government last month set out proposals to reform planning consent criteria and the flagship scheme for awarding renewable projects, aiming to fast-track clean energy rollout as Britain targets clean power by 2030.

By Tsvetana Paraskova for Oilprice.com

More Top Reads From Oilprice.com

Join the discussion | Back to homepage

`;
document.write(write_html);
}



GOOGLE+
LINKEDIN
REDDIT
PRINT

`;
document.write(write_html);
}

EXXON Mobil
-0.35

Open57.81
Trading Vol.6.96M
Previous Vol.241.7B

BUY 57.15

Sell 57.00

 

  • Related Posts

    Investors From 119 Countries Pile Into Dangote’s Record Refinery IPO

    The initial public offering of Nigeria’s Dangote refinery has reached its target to raise $1.6 billion in funds from domestic and retail investors alone, sources with knowledge of the IPO…

    Ras Tanura Fire Follows Attacks on Aramco Offices and Near Shaybah Field

    A fire broke out near Saudi Arabia’s key oil export hub of Ras Tanura on the Persian Gulf following an attack early on Tuesday, but the Kingdom quickly contained the…

    Have You Seen?

    Diesel Drives India’s Fuel Export Windfall as Earnings Reach $12.6 Billion

    • October 27, 2026
    Diesel Drives India’s Fuel Export Windfall as Earnings Reach $12.6 Billion

    Ras Tanura Fire Follows Attacks on Aramco Offices and Near Shaybah Field

    • October 27, 2026
    Ras Tanura Fire Follows Attacks on Aramco Offices and Near Shaybah Field

    Investors From 119 Countries Pile Into Dangote’s Record Refinery IPO

    • October 27, 2026
    Investors From 119 Countries Pile Into Dangote’s Record Refinery IPO

    AM Green to supply Japan with green ammonia under five-year deal

    • October 27, 2026
    AM Green to supply Japan with green ammonia under five-year deal

    Is Something Else Influencing the Value of Oil?

    • October 27, 2026
    Is Something Else Influencing the Value of Oil?

    Homecare: Bringing respiratory care closer to the patient

    • October 27, 2026
    Homecare: Bringing respiratory care closer to the patient

    Taking the pulse in medical gases

    • October 27, 2026
    Taking the pulse in medical gases

    QatarEnergy extends LNG force majeure on Edison cargoes to end-December

    • October 27, 2026
    QatarEnergy extends LNG force majeure on Edison cargoes to end-December

    Video | Too early for a post-mortem: the 2026 helium shortage

    • October 27, 2026
    Video | Too early for a post-mortem: the 2026 helium shortage

    IEA Warns of Dangerous Concentration in Global Clean Energy Supply Chains

    • October 27, 2026
    IEA Warns of Dangerous Concentration in Global Clean Energy Supply Chains