GERC Grants Partial Extension For 100 MW Solar Project Amid Dispute Over Delay And Force Majeure

Representational image. Credit: Canva

The Gujarat Urja Vikas Nigam Limited (GUVNL) filed a petition against Juniper Green Energy Pvt. Ltd. and other parties regarding a 100 MW solar power project under the Gujarat State Electricity Regulatory Commission (GERC). The case revolved around the Power Purchase Agreement (PPA) that was signed between GUVNL and Juniper Green Energy on August 26, 2021, for a tariff of Rs. 2.22 per unit. Juniper later requested a revision in the commissioning timeline, citing delays due to a Force Majeure event caused by global supply chain disruptions and increased module prices due to policy changes, especially the imposition of Basic Customs Duty (BCD) and the Approved List of Models and Manufacturers (ALMM) mandate.

Juniper argued that these circumstances were beyond their control and significantly impacted their ability to complete the project on time. As per the terms of the PPA, the scheduled commissioning date was set for August 25, 2022. However, Juniper sought an extension of 258 days, requesting the date to be moved to May 10, 2023. GUVNL, however, denied this extension and imposed penalties for the delay. The case then moved to GERC for adjudication.

During the hearings, Juniper submitted that the international module market experienced price hikes due to post-COVID supply issues and geopolitical tensions like the Russia-Ukraine war, which disrupted logistics and manufacturing. They also pointed to policy changes in India that added further financial and logistical challenges, including the imposition of BCD from April 2022 and ALMM compliance requirements, which limited the availability of approved modules. The company claimed they had taken all possible steps to mitigate delays, including signing contracts with module suppliers and starting project construction.

GUVNL, on the other hand, argued that the reasons cited did not qualify under the Force Majeure clause. It contended that the imposition of BCD and ALMM compliance was already known well in advance, and developers had been given ample time to plan accordingly. GUVNL maintained that the delay was due to commercial reasons and did not merit an extension of the commissioning date. It insisted that the PPA terms should be enforced strictly, including the imposition of liquidated damages and reduction of tariff for the capacity commissioned after the deadline.

After reviewing the arguments, GERC observed that while certain macroeconomic events like BCD and ALMM affected the renewable energy industry as a whole, the developer must prove specific adverse impacts on their project. The commission acknowledged that there were global issues, but also noted that Juniper had not provided clear documentary evidence of being directly and severely impacted. Ultimately, GERC ruled that Juniper was not entitled to the full extension sought. Instead, the commission granted a partial extension of 107 days, up to December 10, 2022, considering some delay due to unforeseen circumstances.

As a result, any capacity commissioned beyond that date would be subject to reduced tariffs and other penalties as per the PPA. The ruling highlighted the need for developers to plan with greater foresight and flexibility, especially in a rapidly evolving regulatory and economic landscape. The order set a precedent on how Force Majeure claims are evaluated in renewable energy contracts, stressing the importance of evidence and contract discipline.

 

  • Related Posts

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Enviromena has started construction of the Longpasture Solar Farm in County Durham, UK, marking a major milestone for the company’s second-largest UK project to date. The company acquired the project…

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    Indian stock markets ended lower on August 24, 2026, as investors remained cautious amid selling pressure across benchmark indices. The S&P BSE SENSEX closed at 77,369.11, declining 0.22%, or around…

    Have You Seen?

    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    • August 24, 2026
    Exxon Eyes Shell’s $8 Billion U.S. Chemicals Business

    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    • August 24, 2026
    Iran Unveils Huge New Gas Discovery Amid U.S. Economic Pressure

    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    • August 24, 2026
    Norway Vows to Keep Drilling for Oil and Gas in the Arctic

    Japan Power Prices Surge to Highest Since 2023

    • August 24, 2026
    Japan Power Prices Surge to Highest Since 2023

    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    • August 24, 2026
    Enviromena Begins Construction of Longpasture Solar Farm, Its Second-Largest UK Project, Targeting 2027 Energisation

    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    • August 24, 2026
    Indian Green Energy Stocks Show Mixed Performance Amid Market Weakness (24 August 2026)

    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    • August 24, 2026
    MPA Completes 780,000 kWh Solar Power System At Singapore’s Marina South Pier

    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    • August 24, 2026
    Solar SG Targets Next Growth Phase as Singapore Raises Solar Capacity Goal to 3 GWp by 2030

    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia

    • August 24, 2026
    ACWA Signs Storage Services Agreements for 1.5 GW/6 GWh BESS Projects in Saudi Arabia

    Lithuania approves EIA programme for Klaipėda CO2 terminal

    • August 24, 2026
    Lithuania approves EIA programme for Klaipėda CO2 terminal