APTEL Orders Reimbursement Of Safeguard Duty And IGST For 50 MW Solar Project Modules Under Change-In-Law Ruling In Karnataka

Representational image. Credit: Canva

On May 30, 2025, the Appellate Tribunal for Electricity delivered its judgment in a group of appeals filed by Adyah Solar Energy Private Limited. These appeals were against orders passed by the Karnataka Electricity Regulatory Commission (KERC) dated June 15, 2021. The case concerns a solar project developed in Karnataka under the 1,200 MW Pavagada Solar Park initiative. Adyah, a special purpose vehicle of Renew Solar Private Limited, had executed a Power Purchase Agreement (PPA) with Bangalore Electricity Supply Company Limited (BESCOM) on April 20, 2018, which was later approved by KERC.

The core dispute began when the Government of India imposed a safeguard duty on the import of solar modules on July 30, 2018. This change in tax policy led to an increase in both capital and recurring costs for Adyah. According to the PPA, any such change in law entitles the affected party to relief, and Adyah accordingly filed petitions seeking compensation for this additional expenditure, including the safeguard duty and associated Integrated Goods and Services Tax (IGST), as well as carrying cost (interest on the additional working capital).

KERC accepted that the safeguard duty constituted a change in law under the PPA but denied relief on several counts. The Commission disallowed compensation for additional modules beyond what was contractually necessary to meet the minimum committed energy of 69.076 million units (MU) at a minimum CUF (Capacity Utilization Factor) of 15.76%. The Tribunal found this approach restrictive, especially since the appellant had declared a CUF of 27.76% and had installed additional modules before the Commercial Operation Date (COD) to meet this higher efficiency.

The Tribunal referred to its earlier rulings in the Nisarga and Parampujya Solar cases, which had established that developers could install additional modules to enhance output and are eligible for compensation under the change in law provisions if such modules were installed before COD. The Tribunal ruled that BESCOM had benefited from the additional power generated at lower tariffs and hence could not refuse compensation based on technical interpretations of the PPA. The doctrine of approbate and reprobate was cited to emphasize that BESCOM could not accept benefits and then reject related obligations.

Regarding the carrying cost, the Tribunal acknowledged that while the Supreme Court has stayed the enforcement of carrying cost claims in similar matters, the appellant was still entitled to receive it as per contractual provisions. The Tribunal directed KERC to compute carrying costs from the date of incurrence until reimbursement, but the payment remains subject to the Supreme Court’s decision in the pending civil appeal.

Another issue raised was the calculation of incremental tariffs. Adyah argued that compensation should be based on the actual energy generated and not just on the minimum contracted amount. However, the Tribunal upheld KERC’s method of computation based on minimum CUF, reasoning it aligned with the contractual obligations.

The final issue was the excess court fee demanded by KERC. Adyah had initially paid ₹5,000 as per the regulatory fee structure for regulatory matters, but KERC insisted on a fee based on 0.5% of the monetary claim. The Tribunal supported KERC’s interpretation, stating that since the case involved monetary compensation, the higher fee was justified.

The Tribunal partly allowed Adyah’s appeals. It directed the respondents to reimburse the safeguard duty and IGST paid for additional modules installed before COD and ordered carrying cost payments to be made once permitted by the Supreme Court. Other aspects of the Commission’s order, including the incremental tariff calculation and court fee assessment, were upheld.

 

  • Related Posts

    Morocco Launches 350 MW NOOR PV Multisites Solar Programme With November 30, 2026, Prequalification Deadline

    Morocco has launched a recruitment process inviting qualified contractors to participate in its NOOR PV Multisites programme, a large-scale solar power initiative aimed at expanding renewable electricity generation across the…

    HELLENiQ ENERGY Commissions 100 MW/200 MWh Battery Storage Park In Greece With €50 Million Investment

    HELLENiQ ENERGY has brought its first Battery Energy Storage System (BESS) into operation at its Thessaloniki Industrial Facilities in Greece, marking a significant step in the company’s strategy to expand…

    Have You Seen?

    U.S. Wants World Bank to Drop Ban on Upstream Oil and Gas Funding

    • October 15, 2026
    U.S. Wants World Bank to Drop Ban on Upstream Oil and Gas Funding

    Europe’s Gas Prices Close to 2022 High as Hormuz LNG Flows Remain Limited

    • October 15, 2026
    Europe’s Gas Prices Close to 2022 High as Hormuz LNG Flows Remain Limited

    India’s Annual Wind Power Installations to Double by 2030

    • October 15, 2026
    India’s Annual Wind Power Installations to Double by 2030

    Ship-to-Ship Oil Transfers Surge Off India’s West Coast

    • October 15, 2026
    Ship-to-Ship Oil Transfers Surge Off India’s West Coast

    Taiwan advances Alaska LNG deal as project funding remains uncertain

    • October 15, 2026
    Taiwan advances Alaska LNG deal as project funding remains uncertain

    Taiwan advances Alaska LNG deal as project funding remains uncertain

    • October 15, 2026
    Taiwan advances Alaska LNG deal as project funding remains uncertain

    White Paper: Determination and Measurement of Trace Impurities in Battery Off-Gas Using GC-ICP-MS

    • October 15, 2026
    White Paper: Determination and Measurement of Trace Impurities in Battery Off-Gas Using GC-ICP-MS

    Lithium Prices Plunge as EU-China Trade Deal Sparks Demand Fears

    • October 15, 2026
    Lithium Prices Plunge as EU-China Trade Deal Sparks Demand Fears

    IMF Warns of Worldwide Fallout as Attacks on Saudi Arabia Escalate

    • October 15, 2026
    IMF Warns of Worldwide Fallout as Attacks on Saudi Arabia Escalate

    Ukraine to Resume Russian Oil Refinery Strikes After Failed Energy Ceasefire

    • October 15, 2026
    Ukraine to Resume Russian Oil Refinery Strikes After Failed Energy Ceasefire