APTEL Rules In Favor Of Solar Developer Ordering NTPC To Refund Liquidated Damages For 140 MW Projects

Representational image. Credit: Canva

The Appellate Tribunal for Electricity (APTEL) has delivered a judgment in favor of Solaire Surya Urja Private Limited, a solar power developer in Rajasthan, against NTPC Limited and other entities. The case arose from a dispute over the delay in the commissioning of two solar power projects with a total capacity of 140 MW. The company had sought an extension of the Scheduled Commercial Operation Date (SCOD) due to the non-availability of the required evacuation transmission infrastructure, which was under the responsibility of Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL).

The appellant had entered into Power Purchase Agreements (PPAs) with NTPC in May 2016, under which the projects were scheduled to be commissioned by June 1, 2017. However, the company faced delays due to the absence of an adequate evacuation system, which prevented it from injecting power into the grid. Despite its repeated communications regarding the issue, NTPC imposed liquidated damages on the company for the delay in supplying power.

The Central Electricity Regulatory Commission (CERC), in its August 2021 order, had ruled against the appellant, holding it liable for the delay and allowing NTPC to recover liquidated damages. Dissatisfied with the decision, the company filed an appeal before APTEL.

APTEL reviewed the case and acknowledged that the delay was caused by factors beyond the control of the solar power developer. The tribunal observed that RRVPNL had not provided the necessary evacuation infrastructure in time and had even restricted the company from injecting power into the grid without prior approval. The tribunal noted that the appellant had commissioned parts of the projects much earlier but was unable to commence power supply due to the transmission constraints.

APTEL further examined the contractual clauses under the PPAs and concluded that the appellant was entitled to an extension of the SCOD under the force majeure provisions. It ruled that the appellant could not be penalized for a delay caused by external factors, such as the non-availability of the transmission system. The tribunal set aside CERC’s order and directed NTPC to refund the liquidated damages amount, if any, collected from the appellant.

The judgment highlights the importance of proper infrastructure planning for renewable energy projects and emphasizes that developers should not be penalized for delays caused by deficiencies in government agencies’ responsibilities. The ruling sets a precedent for similar cases where transmission constraints hinder the timely commissioning of renewable energy projects. The decision also reinforces the need for coordination between power developers and transmission utilities to ensure smooth project execution.

 

  • Related Posts

    Scatec Signs 25-Year PPA for 120 MW Solar Plant in Tunisia, Partnering with Aeolus

    Representational image. Credit: Canva Scatec ASA, a leading provider of renewable energy solutions, has signed a 25-year Power Purchase Agreement (PPA) with the Tunisian state utility, Société Tunisienne de l’Electricité…

    BluPine Energy Secures ₹1,787 Crore from NaBFID to Strengthen Renewable Energy Portfolio

    BluPine Energy, a leading renewable energy services company established in India by global infrastructure investor Actis, has successfully closed a structured financing deal of ₹1,787 crore with the National Bank…

    Have You Seen?

    China’s Purchases Stall After Trump’s Tariff Threat on Buyers of Venezuelan Oil

    • March 25, 2025
    China’s Purchases Stall After Trump’s Tariff Threat on Buyers of Venezuelan Oil

    COMMENTARY: Solar and Wind Power Are Expensive – Fraser Insitute

    • March 25, 2025
    COMMENTARY: Solar and Wind Power Are Expensive – Fraser Insitute

    Shell Vows to Raise Investor Returns as It Bets Big on LNG

    • March 25, 2025
    Shell Vows to Raise Investor Returns as It Bets Big on LNG

    Shell Traders Haven’t Lost Money in Any Quarter Over Last Decade

    • March 25, 2025
    Shell Traders Haven’t Lost Money in Any Quarter Over Last Decade

    US Army Corps to Narrow List of Emergency Energy Projects by Next Week

    • March 25, 2025
    US Army Corps to Narrow List of Emergency Energy Projects by Next Week

    Alaska Seeks South Korean Investors for Its $44-Billion LNG Project

    • March 25, 2025
    Alaska Seeks South Korean Investors for Its $44-Billion LNG Project

    India’s Peak Electricity Demand Set to Jump By 10% in 2025

    • March 25, 2025
    India’s Peak Electricity Demand Set to Jump By 10% in 2025

    Biggest Indian Oil Producer Seeks to Diversify to Withstand Supply Glut

    • March 25, 2025
    Biggest Indian Oil Producer Seeks to Diversify to Withstand Supply Glut

    Shell Flags Uncertain Outcome of $1.6-Billion Russian Court Claim

    • March 25, 2025
    Shell Flags Uncertain Outcome of $1.6-Billion Russian Court Claim

    Analyst Says NatGas Bulls Attempting to ‘Hold Line’ Ahead of April Rollover

    • March 25, 2025
    Analyst Says NatGas Bulls Attempting to ‘Hold Line’ Ahead of April Rollover