APTEL Rules In Favor Of Solar Developer Ordering NTPC To Refund Liquidated Damages For 140 MW Projects

Representational image. Credit: Canva

The Appellate Tribunal for Electricity (APTEL) has delivered a judgment in favor of Solaire Surya Urja Private Limited, a solar power developer in Rajasthan, against NTPC Limited and other entities. The case arose from a dispute over the delay in the commissioning of two solar power projects with a total capacity of 140 MW. The company had sought an extension of the Scheduled Commercial Operation Date (SCOD) due to the non-availability of the required evacuation transmission infrastructure, which was under the responsibility of Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL).

The appellant had entered into Power Purchase Agreements (PPAs) with NTPC in May 2016, under which the projects were scheduled to be commissioned by June 1, 2017. However, the company faced delays due to the absence of an adequate evacuation system, which prevented it from injecting power into the grid. Despite its repeated communications regarding the issue, NTPC imposed liquidated damages on the company for the delay in supplying power.

The Central Electricity Regulatory Commission (CERC), in its August 2021 order, had ruled against the appellant, holding it liable for the delay and allowing NTPC to recover liquidated damages. Dissatisfied with the decision, the company filed an appeal before APTEL.

APTEL reviewed the case and acknowledged that the delay was caused by factors beyond the control of the solar power developer. The tribunal observed that RRVPNL had not provided the necessary evacuation infrastructure in time and had even restricted the company from injecting power into the grid without prior approval. The tribunal noted that the appellant had commissioned parts of the projects much earlier but was unable to commence power supply due to the transmission constraints.

APTEL further examined the contractual clauses under the PPAs and concluded that the appellant was entitled to an extension of the SCOD under the force majeure provisions. It ruled that the appellant could not be penalized for a delay caused by external factors, such as the non-availability of the transmission system. The tribunal set aside CERC’s order and directed NTPC to refund the liquidated damages amount, if any, collected from the appellant.

The judgment highlights the importance of proper infrastructure planning for renewable energy projects and emphasizes that developers should not be penalized for delays caused by deficiencies in government agencies’ responsibilities. The ruling sets a precedent for similar cases where transmission constraints hinder the timely commissioning of renewable energy projects. The decision also reinforces the need for coordination between power developers and transmission utilities to ensure smooth project execution.

 

  • Related Posts

    Weekly Tech Insights: LONGi Advances Hi-MO X10 & Hi-MO 9, Growatt Explores Floating Solar, JinkoSolar Expands Sunny 365 Solar-Storage, Hoymiles Powers Rooftops with MIT-5000-8T

    LONGi and AGS International have deployed Hi-MO X10 645 W modules for a grid-connected warehouse rooftop project in Riyadh, delivering approximately 200 kWp of installed solar capacity. The technology focus…

    Green Energy Stocks Show Mixed Performance As Indian Markets Trade Flat (21 August 2026)

    The Indian stock market remained largely range-bound on August 21, 2026, with benchmark indices showing little movement. The S&P BSE SENSEX remained steady at 77,540.83 points, while the NIFTY 50…

    Have You Seen?

    India Boosts Battery Investment to Cut Solar Power Waste

    • August 24, 2026
    India Boosts Battery Investment to Cut Solar Power Waste

    Iranian Oil Supply to China Is Rapidly Drying Up

    • August 21, 2026
    Iranian Oil Supply to China Is Rapidly Drying Up

    Nigeria Eyes $50 Billion Offshore Oil and Gas Investment Boom

    • August 21, 2026
    Nigeria Eyes $50 Billion Offshore Oil and Gas Investment Boom

    East African Nations Offered 30% Share of Dangote’s Kenya Mega-Refinery

    • August 21, 2026
    East African Nations Offered 30% Share of Dangote’s Kenya Mega-Refinery

    Saudi Oil Exports from Mediterranean Soar with Shuttles North to Avoid Houthis

    • August 21, 2026
    Saudi Oil Exports from Mediterranean Soar with Shuttles North to Avoid Houthis

    Ukrainian Drone Attack Hits Lukoil Refinery Deep in Russia 

    • August 21, 2026
    Ukrainian Drone Attack Hits Lukoil Refinery Deep in Russia 

    China’s Teapots Look Beyond Iranian Oil amid U.S. Blockade

    • August 21, 2026
    China’s Teapots Look Beyond Iranian Oil amid U.S. Blockade

    Court Upholds Trump Admin Order to Restart SYU

    • August 21, 2026
    Court Upholds Trump Admin Order to Restart SYU

    Whisky waste-to-biomethane plant to meet 4% of Scotland’s gas demand

    • August 21, 2026
    Whisky waste-to-biomethane plant to meet 4% of Scotland’s gas demand

    CCS projects could put pressure on US Midwest CO2 supply

    • August 21, 2026
    CCS projects could put pressure on US Midwest CO2 supply