Atucha I life extension work ‘44% completed’

“Significant progress,” the company said, had been made in “modernising essential systems and optimising key processes. This work will ensure that, once the refurbishment is complete, Atucha I continues to operate safely and efficiently, strengthening the contribution of nuclear energy as a base energy source for the country’s development”.

Atucha I, a 362 MWe pressurised heavy water reactor, entered commercial operation in 1974 and had a design life in its operating licence of 32 equivalent years of full power. The life extension project is seen as one of Argentina’s most significant infrastructure projects.

The first extension to its operating licence began in 2018 when the original 32-year mark was reached.

The duration of the amended operating licence was for the equivalent of 5 years operation at full power, or 10 years from 2014, which ended on 29 September 2024, which is when the current planned 30-month shutdown began. 

Nucleoeléctrica Argentina put the refurbishment programme’s cost at USD463 million in 2023 when it launched a fundraising round of bond sales to cover the LTO (long term operation) cost and construction of a dry storage facility for used fuel.

Background

Atucha I was designed and built by KWU, which was a joint venture of Germany’s Siemens and AEG. Over time, KWU was fully owned by Siemens, before being sold to the reactor business of France’s Areva which is now owned by EDF and trading as Framatome. However, Argentina now has an experienced supply chain of its own for pressurised heavy water reactors, having completed and brought into operation the similar Atucha II reactor in 2016.

It has become common for pressurised heavy water reactors like Atucha I to undergo refurbishment, which typically involves replacing pressure tubes and fuel channels, to enable another two decades of operation. Nucleoeléctrica Argentina said ahead of the shutdown that 2,000 jobs would be created as it modernised “all the processes and systems of the plant”.

   

  • Related Posts

    Copenhagen Atomics to build deconversion facility

    Under the agreement, Urenco will help design a dedicated facility for the deconversion of uranium hexafluoride (UF6) into uranium tetrafluoride (UF4) at Copenhagen Atomics’ fuel facility in Copenhagen. Copenhagen Atomics…

    Belgian nuclear power plant negotiations extended

    Engie, the French parent of Belgian power company Electrabel, and the Belgian government began negotiations in late April. At that time, they said their Letter of Intent covered a proposed…

    Have You Seen?

    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    • November 5, 2026
    IEEFA: $67.8 Billion in Asian LNG Power Projects Scrapped or Stalled

    EU Not Planning to Resume Russian Gas Purchases

    • November 5, 2026
    EU Not Planning to Resume Russian Gas Purchases

    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    • November 5, 2026
    China’s Diesel Exports Set to Plunge as Domestic Inventories Run Low

    Iran Reports More Tanker Fires in Strait of Hormuz

    • November 5, 2026
    Iran Reports More Tanker Fires in Strait of Hormuz

    India to Require State Utilities to Add Energy Storage Capacity

    • November 5, 2026
    India to Require State Utilities to Add Energy Storage Capacity

    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    • November 5, 2026
    European Gas Prices Drop on Iran Deal Hopes after U.S. Midterms

    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    • November 5, 2026
    Rigzone Talks to the ‘Disruption Wing’ of the USA DOE

    Samsung ramps up neon recycling to strengthen supply security

    • November 5, 2026
    Samsung ramps up neon recycling to strengthen supply security

    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    • November 5, 2026
    Baywater Healthcare acquires UK nitrous oxide and oxygen supplier

    Air Products exits two Chinese coal gasification projects

    • November 5, 2026
    Air Products exits two Chinese coal gasification projects