BERC Approves 185 MW Grid Connectivity For BSPGCL’s 185 MW Solar PV And 45.4 MW/90.8 MWh BESS Hybrid Project In Bihar

The Bihar Electricity Regulatory Commission (BERC) has ruled in favor of Bihar State Power Generation Company Limited (BSPGCL) in a dispute over the grid connectivity capacity for a hybrid renewable energy project at Kajra in Lakhisarai district. The decision provides clarity on how transmission connectivity should be determined for hybrid projects that combine solar power generation with battery energy storage.

The case involved an 185 MW solar photovoltaic (PV) plant integrated with a 45.4 MW Battery Energy Storage System (BESS). BSPGCL approached the commission after the Bihar State Power Transmission Company Limited (BSPTCL), acting as the State Transmission Utility (STU), insisted that the project should obtain connectivity for a total capacity of 230.4 MW by adding the installed capacities of both the solar plant and the battery system.

BSPGCL argued that the project has been designed to operate on a non-overlapping basis. During daytime, the solar plant generates electricity for the grid while using around 20 percent of its output to charge the battery storage system. Once solar generation stops in the evening, the battery discharges the stored energy to the grid during peak demand hours. Since the solar plant and the battery never export electricity to the grid simultaneously, the project’s maximum power injection at any point remains limited to 185 MW.

The company also pointed out that the project is equipped with transformers having a maximum capacity of 200 MVA. This technical limit makes it impossible for the plant to inject 230.4 MW into the grid at the same time. BSPGCL stated that requiring connectivity for a higher capacity would unnecessarily increase its financial burden through larger bank guarantees and higher transmission charges for capacity that the project can neither use nor deliver.

BSPTCL defended its position by stating that connectivity should be based on the total installed nameplate capacity of all generation assets. It also raised concerns that under exceptional conditions, such as grid disturbances or faults, simultaneous power injection could occur if adequate safeguards were not in place. The utility further noted that the Power Purchase Agreement (PPA) allows flexibility in scheduling battery discharge, which could potentially result in power being supplied outside the originally planned operating window.

After examining the submissions, BERC rejected the transmission utility’s approach of simply adding the capacities of the solar plant and battery system. The commission observed that connectivity for hybrid projects should be determined by the maximum instantaneous power that can actually be injected into the grid, rather than by the sum of the installed capacities. It also stated that concerns about possible grid instability must be supported by technical studies or evidence and cannot be based on assumptions alone.

Accordingly, BERC directed that the project’s grid connectivity capacity be revised to 185 MW. At the same time, the commission instructed BSPGCL to submit a formal declaration or enter into a supplementary agreement with BSPTCL specifying the operational limits and charging and discharging schedule of the battery system. This requirement is intended to ensure safe, transparent, and efficient operation of the hybrid project while protecting the reliability of the state transmission network.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    India Daily: PM Surya Ghar Subsidy, POWERGRID Acquires Fatehgarh II, BPCL Tenders 1 MW Solar, VPA Advances 10 MW Solar, CEA Backs Flexible Thermal

    The Ministry of New and Renewable Energy has detailed the Central Financial Assistance guidelines for residential rooftop solar under PM Surya Ghar: Muft Bijli Yojana. With an overall outlay of…

    Indian Green Energy Stocks Show Mixed Trend As Adani Green Leads Gains (01 September 2026)

    Indian stock markets ended largely subdued on September 1, 2026, with benchmark indices facing mild pressure. The S&P BSE Sensex closed at around 76,944.28 points, down 0.02%, while the Nifty…

    Have You Seen?

    Russia Doubles Dark Fleet to Ship LNG to Asia

    • September 1, 2026
    Russia Doubles Dark Fleet to Ship LNG to Asia

    U.S. Energy Storage Capacity Installations Hit Record High in Q2

    • September 1, 2026
    U.S. Energy Storage Capacity Installations Hit Record High in Q2

    Asia Spot LNG Prices Hit 5-Month High as Hormuz Blockage Drags On

    • September 1, 2026
    Asia Spot LNG Prices Hit 5-Month High as Hormuz Blockage Drags On

    U.S. Oil Deal Pushes China and Russia Out of Venezuelan Fields

    • September 1, 2026
    U.S. Oil Deal Pushes China and Russia Out of Venezuelan Fields

    Europe’s Wind Power Buildout Jumps 30% in First Half

    • September 1, 2026
    Europe’s Wind Power Buildout Jumps 30% in First Half

    Price, Not Politics, Is Driving Most of India’s Oil Buying

    • September 1, 2026
    Price, Not Politics, Is Driving Most of India’s Oil Buying

    Ukrainian Drone Barrage Sets Key Russian Oil Port Ablaze

    • September 1, 2026
    Ukrainian Drone Barrage Sets Key Russian Oil Port Ablaze

    Solar Overtakes Coal as China’s Largest Power Source

    • September 1, 2026
    Solar Overtakes Coal as China’s Largest Power Source

    Two Supertankers Hit by Unknown Projectiles in Strait of Hormuz

    • September 1, 2026
    Two Supertankers Hit by Unknown Projectiles in Strait of Hormuz

    What Is the Oil, Gas Impact of Storm Edouard?

    • September 1, 2026
    What Is the Oil, Gas Impact of Storm Edouard?