India’s Power Transmission Sector to See ₹5-6 Trillion Capex by FY32 Amid Renewable Energy Expansion: ICRA

India’s power transmission sector is expected to witness capital expenditure of ₹5-6 trillion between FY27 and FY32 as the country strengthens its grid infrastructure to support the rapid expansion of renewable energy capacity, according to ICRA.

The rating agency said the planned investments will focus on upgrading existing transmission infrastructure, adding evacuation capacity, and developing new transmission corridors to integrate the government’s target of over 900 GW of non-fossil fuel capacity by 2035-36, including approximately 548 GW of solar and wind power.

Ankit Jain, Vice President and Co-Group Head at ICRA, said the sector would require annual additions of around 20,000 circuit kilometres (ckm) of transmission lines and 120 gigavolt-amperes (GVA) of substation capacity to meet the targets outlined in the National Electricity Plan.

ICRA noted that outstanding orders and order inflows for key transmission equipment manufacturers in FY26 have more than doubled compared with FY22, reflecting the expected surge in transmission investments. However, limited manufacturing capacity, shortages of skilled manpower, and supply chain constraints could delay project execution unless equipment suppliers expand their production capabilities.

The report also highlighted persistent execution challenges, including land acquisition, right-of-way (RoW) issues, and regulatory approvals, which continue to delay transmission projects awarded through the tariff-based competitive bidding (TBCB) route.

According to ICRA, only about 12% of transmission projects commissioned by March 2026 under the TBCB model were completed within their scheduled commissioning dates. The remaining projects experienced delays ranging from two months to three years, with a median delay of more than 10 months.

The delays have increased the risk of renewable energy curtailment by restricting timely power evacuation from generation projects. Since the previous fiscal year, renewable energy developers in high-generation states have experienced significant curtailment due to inadequate transmission infrastructure.

As of May 2026, around 33% of the recently commissioned 54.8 GW of renewable energy capacity was being evacuated through the Temporary General Network Access (T-GNA) mechanism, with curtailment levels reaching 50-60% during solar generation hours. The issue is particularly pronounced in Rajasthan and Gujarat, while southern states have experienced relatively limited curtailment.

ICRA further noted that approximately 107 GW of solar, wind, hybrid, hydro, pumped storage, and thermal projects with granted grid connectivity are expected to be integrated into the interstate transmission system (ISTS) between FY27 and FY31. However, delays in transmission infrastructure development could continue to impact renewable energy commissioning schedules and project returns if grid expansion fails to keep pace with generation capacity.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    JSW Energy Wins INR443.74 Crore Order For 200 MW/400 MWh BESS And PCS Project From Bondada Renewable Energy

    JSW Energy PSP Eleven Limited (JEPEL), a step-down subsidiary of JSW Energy Limited, has secured new orders worth ₹443.74 crore from Bondada Renewable Energy Private Limited for the supply of…

    REC Incorporates SPV for Nawada-Durgapur-Jeerat 765 kV Interstate Transmission Project

    REC Limited has announced the incorporation of Nawada Durgapur Power Transmission Limited as a wholly owned subsidiary of REC Power Development and Consultancy Limited (RECPDCL) to facilitate the development of…

    Have You Seen?

    JSW Energy Wins INR443.74 Crore Order For 200 MW/400 MWh BESS And PCS Project From Bondada Renewable Energy

    • July 13, 2026
    JSW Energy Wins INR443.74 Crore Order For 200 MW/400 MWh BESS And PCS Project From Bondada Renewable Energy

    REC Incorporates SPV for Nawada-Durgapur-Jeerat 765 kV Interstate Transmission Project

    • July 13, 2026
    REC Incorporates SPV for Nawada-Durgapur-Jeerat 765 kV Interstate Transmission Project

    POWERGRID Wins TBCB Project For Krishnagiri REZ Phase-I Transmission System Across Three Southern States

    • July 13, 2026
    POWERGRID Wins TBCB Project For Krishnagiri REZ Phase-I Transmission System Across Three Southern States

    MNRE Reopens NISE Portal, Extends ALMM List-II Investment Protection Application Deadline To July 23, 2026

    • July 13, 2026
    MNRE Reopens NISE Portal, Extends ALMM List-II Investment Protection Application Deadline To July 23, 2026

    MNRE Extends Self-Certification Deadline For SPV Inverters Above 200 kW Until December 31, 2026

    • July 13, 2026
    MNRE Extends Self-Certification Deadline For SPV Inverters Above 200 kW Until December 31, 2026

    Tion Renewables Acquires 69 MWp Agri-PV Park in Germany from FEFA Projekt

    • July 13, 2026
    Tion Renewables Acquires 69 MWp Agri-PV Park in Germany from FEFA Projekt

    BERC Approves PPA And Energy Accounting Framework For 275 MW Rooftop Solar PV Project Under PM Surya Ghar Scheme In Bihar

    • July 13, 2026
    BERC Approves PPA And Energy Accounting Framework For 275 MW Rooftop Solar PV Project Under PM Surya Ghar Scheme In Bihar

    Solplanet Unveils Next-Generation Utility-Scale Solar Inverter at Intersolar Europe 2026

    • July 13, 2026
    Solplanet Unveils Next-Generation Utility-Scale Solar Inverter at Intersolar Europe 2026

    BERC Approves 185 MW Grid Connectivity For BSPGCL’s 185 MW Solar PV And 45.4 MW/90.8 MWh BESS Hybrid Project In Bihar

    • July 13, 2026
    BERC Approves 185 MW Grid Connectivity For BSPGCL’s 185 MW Solar PV And 45.4 MW/90.8 MWh BESS Hybrid Project In Bihar

    India’s Power Transmission Sector to See ₹5-6 Trillion Capex by FY32 Amid Renewable Energy Expansion: ICRA

    • July 13, 2026
    India’s Power Transmission Sector to See ₹5-6 Trillion Capex by FY32 Amid Renewable Energy Expansion: ICRA