CERC Approves Tariff For 1200 MW Wind-Solar Hybrid Power Project At ₹4.64-₹4.73/kWh

Representational image. Credit: Canva

The Central Electricity Regulatory Commission has issued an order regarding the adoption of tariffs for a 1,200 MW wind-solar hybrid power project. This project, developed under a competitive bidding process, is connected to the inter-state transmission system and aims to provide peak power supply. The Solar Energy Corporation of India (SECI) initiated the bidding process, received responses from several companies, and finalized agreements with selected developers.

SECI floated a request for selection in November 2022, receiving eight bids for a total capacity of 2,390 MW. Following a thorough evaluation, four companies were awarded contracts for a combined capacity of 1,200 MW. These companies include AMP Energy Green Private Limited, ReNew Vikram Shakti Private Limited, Hero Solar Energy Private Limited, and ACME Cleantech Solutions Private Limited. The selected bidders were issued letters of award in April 2023.

SECI subsequently signed power supply agreements with Assam Power Distribution Company Limited for 100 MW and Chhattisgarh State Power Distribution Company Limited for 500 MW. In addition, power purchase agreements were executed with AMP Energy Green Sixteen Private Limited, Clean Renewable Energy (Barmer) Private Limited, and ACME Urja One Private Limited for different capacities.

The competitive bidding process determined the tariffs for the project, ranging from ₹4.64 to ₹4.73 per kWh. The lowest tariff was offered by AMP Energy Green Private Limited at ₹4.64 per kWh, followed by ReNew Vikram Shakti Private Limited at ₹4.69 per kWh. SECI has also requested approval for a trading margin of ₹0.07 per kWh, which has been agreed upon by the distribution companies.

The commission reviewed SECI’s submissions and confirmed that the bidding process was conducted transparently and following established guidelines. It was noted that SECI is responsible for entering into agreements with developers and ensuring the supply of power to distribution companies.

The order also discusses the financial and contractual obligations of SECI and developers, including the requirement for payment security mechanisms. SECI is required to establish a letter of credit to ensure timely payments to developers. Additionally, developers are expected to meet financial closure requirements and achieve full project commissioning within the specified timeframe.

The commission has approved the adoption of the discovered tariffs for the entire 1,200 MW capacity, with the condition that SECI finalizes agreements for the remaining 600 MW. SECI is required to submit documentation once the agreements are signed. If SECI fails to secure contracts for the full capacity, it must inform the commission accordingly.

The project is expected to enhance renewable energy generation and provide a reliable peak power supply. The hybrid nature of the project, combining wind and solar energy, ensures a stable and efficient power output. The commission’s approval facilitates the smooth implementation of the project, supporting India’s renewable energy goals and ensuring affordable power for consumers.

 

  • Related Posts

    Sembcorp Gets Conditional Approval for 300 MW Malaysia-Singapore Renewable Power Project, with 2.2 GWp Floating Solar and 4.3 GWh BESS

    Sembcorp Utilities Pte Ltd, a wholly owned subsidiary of Sembcorp Industries, has received Conditional Approval from Singapore’s Energy Market Authority (EMA) for a 300 MW renewable power import project from…

    Delhi’s Clean Energy Transition: IEEFA-Ember Study Calls for Battery Storage and Rooftop Solar as Demand Rises to 38,482 MU

    Delhi’s electricity transition will increasingly depend on expanding distributed renewable energy, battery energy storage, energy efficiency and demand-side flexibility as the capital’s electricity demand continues to rise, according to a…

    Have You Seen?

    Oil Price Uncertainty as Negotiations Continue

    • August 8, 2026
    Oil Price Uncertainty as Negotiations Continue

    ADNOC Reports 15 Vessel Attacks as Hormuz Risks Mount

    • August 8, 2026
    ADNOC Reports 15 Vessel Attacks as Hormuz Risks Mount

    Sembcorp Gets Conditional Approval for 300 MW Malaysia-Singapore Renewable Power Project, with 2.2 GWp Floating Solar and 4.3 GWh BESS

    • August 8, 2026
    Sembcorp Gets Conditional Approval for 300 MW Malaysia-Singapore Renewable Power Project, with 2.2 GWp Floating Solar and 4.3 GWh BESS

    Delhi’s Clean Energy Transition: IEEFA-Ember Study Calls for Battery Storage and Rooftop Solar as Demand Rises to 38,482 MU

    • August 8, 2026
    Delhi’s Clean Energy Transition: IEEFA-Ember Study Calls for Battery Storage and Rooftop Solar as Demand Rises to 38,482 MU

    US Energy Firms Leave Rig Count Unchanged in Latest Week, Baker Hughes Says

    • August 8, 2026
    US Energy Firms Leave Rig Count Unchanged in Latest Week, Baker Hughes Says

    US Senate Passes Sweeping Russia Energy Sanctions, Next Stop US House

    • August 8, 2026
    US Senate Passes Sweeping Russia Energy Sanctions, Next Stop US House

    Hundreds of Millions in Grid Deposits Linger in Uncertainty Following Texas Data Center Pause

    • August 8, 2026
    Hundreds of Millions in Grid Deposits Linger in Uncertainty Following Texas Data Center Pause

    Navgrun Plans 1.2 GW TOPCon G12R Manufacturing Facility, Complementing Existing 700 MW Module Capacity in India

    • August 8, 2026
    Navgrun Plans 1.2 GW TOPCon G12R Manufacturing Facility, Complementing Existing 700 MW Module Capacity in India

    LONGi to Supply Hi-MO 9 Modules for 71 MWp Solar Portfolio in Italy

    • August 8, 2026
    LONGi to Supply Hi-MO 9 Modules for 71 MWp Solar Portfolio in Italy

    India Remains Dependent on Imports for 90% of Oil Demand

    • August 7, 2026
    India Remains Dependent on Imports for 90% of Oil Demand