CERC Grants 100% ISTS Charge Waiver For 174.9 MW Gujarat Hybrid Project

The Central Electricity Regulatory Commission (CERC) has extended the Scheduled Commercial Operation Date (SCOD) for Mounting Renewable Power Limited’s (MRPL) 250 MW wind-solar hybrid power project in Gujarat to June 30, 2026. The Commission has also approved a 100% waiver of Inter-State Transmission System (ISTS) charges for the 174.9 MW capacity commissioned by the revised deadline.

The decision was issued on October 26, 2026, following a petition filed by MRPL along with Welspun Living Limited and Welspun Corp Limited. The petitioners sought relief under the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020, citing delays caused by circumstances beyond their control.

The project is located in Jamnagar district, Gujarat, and is intended to supply renewable electricity to commercial consumers, including Welspun Living and Welspun Corp. The companies entered into Power Purchase Agreements (PPAs) with MRPL in February 2024. The project was initially planned for completion by mid-2025, in line with connectivity arrangements at the Bhachau substation.

However, project execution was affected by heavy rainfall, the impact of Cyclone Biparjoy, right-of-way disputes during transmission line construction, delays in government land allotments and pending land-use approvals in Gujarat. These challenges disrupted construction activities and pushed back the commissioning schedule.

The petitioners approached an independent committee established under the CERC regulations to assess delays in renewable energy projects. After examining project progress reports and land acquisition details, the committee issued its report on June 19, 2026, recommending an extension until June 30, 2026. The recommendation represented the maximum permissible extension of two six-month periods under the 2020 regulations.

CERC subsequently accepted the committee’s recommendations. By the revised deadline, MRPL had completed trial runs and achieved commercial operation for 174.9 MW of the planned 250 MW capacity. This included 115.5 MW of wind power and 59.4 MW of solar power.

The remaining 75 MW capacity was reported to be at an advanced stage of construction, with phased completion planned through August 2026. However, the transmission charge waiver approved by the Commission is limited to the capacity that achieved commercial operation on or before June 30, 2026.

The Commission’s bench comprised Chairperson Jishnu Barua and Members Ramesh Babu V., Harish Dudani and Ravinder Singh Dhillon. It directed the National Load Despatch Centre (NLDC) to verify the commercial operation certificates before implementing the approved waiver.

The order provides regulatory clarity for MRPL and its power purchasers by linking the transmission charge exemption to verified commissioning milestones. It also establishes the extent of relief available for the operational portion of the hybrid project while the remaining capacity progresses towards completion.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Zetwerk Completes US Power Transformer Installation Amid Rising Grid Demand

    Zetwerk Manufacturing Businesses Ltd. and its US subsidiary Unimacts have completed the installation of a power transformer manufactured by Zetwerk in North Carolina, marking a milestone in the company’s expansion…

    Gujarat Offers Additional Subsidy For Rooftop Solar Systems Up To 2.18 kWp Under PM Surya Ghar Scheme

    The Government of Gujarat has announced an additional state subsidy framework under the PM Surya Ghar: Muft Bijli Yojana to make rooftop solar installations more affordable for small residential consumers.…

    Have You Seen?

    Zetwerk Completes US Power Transformer Installation Amid Rising Grid Demand

    • October 27, 2026
    Zetwerk Completes US Power Transformer Installation Amid Rising Grid Demand

    Gujarat Offers Additional Subsidy For Rooftop Solar Systems Up To 2.18 kWp Under PM Surya Ghar Scheme

    • October 27, 2026
    Gujarat Offers Additional Subsidy For Rooftop Solar Systems Up To 2.18 kWp Under PM Surya Ghar Scheme

    CERC Approves 448 MW FDRE Tariffs at INR 4.82–₹4.91 Per Unit For Round-the-Clock Renewable Power

    • October 27, 2026
    CERC Approves 448 MW FDRE Tariffs at INR 4.82–₹4.91 Per Unit For Round-the-Clock Renewable Power

    CERC Grants 100% ISTS Charge Waiver For 174.9 MW Gujarat Hybrid Project

    • October 27, 2026
    CERC Grants 100% ISTS Charge Waiver For 174.9 MW Gujarat Hybrid Project

    CERC Denies Special ISTS Charge Waiver For 778.8 MW Wind And Solar Projects In Karnataka And Maharashtra

    • October 27, 2026
    CERC Denies Special ISTS Charge Waiver For 778.8 MW Wind And Solar Projects In Karnataka And Maharashtra

    Houthis Claim Attacks on Saudi Arabia’s East-West Oil Pipeline

    • October 26, 2026
    Houthis Claim Attacks on Saudi Arabia’s East-West Oil Pipeline

    Saudi Oil Output Jumps 12.2% to 8 Million Bpd in September

    • October 26, 2026
    Saudi Oil Output Jumps 12.2% to 8 Million Bpd in September

    IEA’s Birol: Energy Prices Won’t Return to Pre-War Levels in 2027

    • October 26, 2026
    IEA’s Birol: Energy Prices Won’t Return to Pre-War Levels in 2027

    India’s BPCL to Cut Russian Oil Imports Due to Higher Prices

    • October 26, 2026
    India’s BPCL to Cut Russian Oil Imports Due to Higher Prices

    Renergen completes commissioning of South African helium project

    • October 26, 2026
    Renergen completes commissioning of South African helium project