CERC Permits Continued Infirm Power Injection From 100 MW Solar Component Of Hybrid Project

TP Saurya Limited has received relief from the Central Electricity Regulatory Commission (CERC), which has allowed the company to continue injecting infirm power from the 100 MW solar component of its 600 MW wind-solar hybrid project until the project becomes eligible for part or early commissioning under its Power Purchase Agreement (PPA).

The Commission issued its order on 3 July 2026 after examining the company’s request for an extension of the infirm power injection period. The case arose because the solar portion of the hybrid project was ready for operation, while the wind component remained delayed due to pending transmission infrastructure.

The project was awarded by the Solar Energy Corporation of India (SECI) under Tranche-V of the Wind-Solar Hybrid scheme. It comprises 400 MW of solar capacity and 200 MW of wind capacity. The original commissioning deadline was January 2025, but it was later revised to May 2025 following delays in tariff adoption. SECI subsequently extended the deadline further to 24 February 2026, or two months after the availability of transmission connectivity, due to delays in the readiness of the Gadag-II transmission substation.

TP Saurya informed the Commission that it had successfully completed a 100 MW solar project at Bikaner in Rajasthan. However, the associated wind capacity in Karnataka could not be commissioned because transmission connectivity was still unavailable. The company argued that the Request for Selection (RfS) permits a completed project component to inject power even if the remaining component is delayed due to connectivity issues. At the same time, the PPA does not permit commercial commissioning of only one component of the hybrid project.

After reviewing the documents, CERC observed that the PPA and the RfS contain separate provisions that operate independently. While the PPA requires both solar and wind capacities to be commissioned in the prescribed ratio before part commissioning can be declared, the RfS allows a ready component to inject power and sell it outside the PPA when the remaining component is delayed because of pending connectivity or long-term access. Therefore, the Commission held that the completed solar component could continue operating without being treated as commercially commissioned under the PPA.

The Commission also noted that TP Saurya had already exhausted the maximum period of infirm power injection permitted by the Regional Load Despatch Centre under the Indian Electricity Grid Code. Since the delay in the Gadag-II transmission substation was beyond the developer’s control and none of the respondents opposed the extension of infirm power injection, CERC exercised its powers under Regulation 19(3) of the Grid Code to grant additional relief.

Accordingly, the Commission allowed the company to continue injecting infirm power from the 100 MW solar component until the associated 50 MW wind capacity is ready and the project becomes eligible for part or early commissioning. The continued injection will remain subject to compliance with the Grid Code and directions issued by the concerned Regional Load Despatch Centre.

The order also addressed a dispute regarding the sale of the generated power. MPSEZ Utilities Limited and CESC Limited argued that they should receive the electricity at the tariff specified under the PPA and opposed any sale to third parties. TP Saurya stated that both buyers had declined its commercial proposal, following which SECI issued a No Objection Certificate allowing third-party sales. After examining the contractual provisions and correspondence between the parties, the Commission also advised SECI to ensure that future PPAs clearly incorporate all relevant provisions of the RfS to prevent similar disputes.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Ventura County Partners with ForeFront Power for 7.7 MW Solar and Storage Project

    The County of Ventura has partnered with ForeFront Power to develop a 7.7 MW-DC solar energy and battery storage project at the Ventura County Government Center in California. The project…

    Greenvolt Secures €218 Million UniCredit Financing for 400 MW BESS Projects in Poland

    Greenvolt Group has secured a €218 million financing package from UniCredit to support the development of its Ełk and Turośń battery energy storage system (BESS) projects in Poland. The financing…

    Have You Seen?

    Siemens Energy to spin off Transformation of Industry with view to sale

    • August 28, 2026
    Siemens Energy to spin off Transformation of Industry with view to sale

    Energean in Exclusive Talks for $1 Billion BP Egypt Gas Deal

    • August 28, 2026
    Energean in Exclusive Talks for $1 Billion BP Egypt Gas Deal

    Trump Complained About Big Oil Profits, But Dumped Exxon Stock on Ceasefire Day

    • August 28, 2026
    Trump Complained About Big Oil Profits, But Dumped Exxon Stock on Ceasefire Day

    45 Power Plants in India Running on Critically Low Levels of Coal Stocks

    • August 28, 2026
    45 Power Plants in India Running on Critically Low Levels of Coal Stocks

    Africa Emerges as Center of Upstream Acreage Rush

    • August 28, 2026
    Africa Emerges as Center of Upstream Acreage Rush

    Thailand Accelerates Clean Energy Push to Cut LNG Dependence

    • August 27, 2026
    Thailand Accelerates Clean Energy Push to Cut LNG Dependence

    Qatar and Kuwait Restore 70% of Pre-War Oil Exports Through Hormuz

    • August 27, 2026
    Qatar and Kuwait Restore 70% of Pre-War Oil Exports Through Hormuz

    Weak Asian Oil Imports Challenge Claims of Surge in Hormuz Transits

    • August 27, 2026
    Weak Asian Oil Imports Challenge Claims of Surge in Hormuz Transits

    TotalEnergies Exits Russia’s Sanctioned Arctic LNG 2 Project

    • August 27, 2026
    TotalEnergies Exits Russia’s Sanctioned Arctic LNG 2 Project

    Fortum Seeks State Aid for Major New Nuclear Project in Sweden

    • August 27, 2026
    Fortum Seeks State Aid for Major New Nuclear Project in Sweden