Delay in Flamanville 3 attaining full power

Monday, 4 August 2025

The long-delayed Flamanville 3 EPR reactor in Normandy in northern France is now expected to reach full power for the first time “before the end of autumn 2025”, EDF said. It had earlier been scheduled to reach full power in “summer 2025”.

Delay in Flamanville 3 attaining full power
The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

The 1630 MWe (net) pressurised water reactor was connected to the grid for the first time on 21 December 2024. At that time, EDF said that “in accordance with the startup operations, the phases of testing and of connection and disconnection to the grid will continue for several months … until the reactor reaches 100% power”. This had been scheduled for summer 2025.

However, EDF has now said: “After its next reconnection to the grid, the Flamanville 3 teams will continue the testing phase before commissioning with an objective to reach full capacity before the end of autumn 2025.

“At the end of this testing period, the unit is expected to be operated at 100% capacity until the first planned outage for maintenance and refuelling, called Visite Complète 1 (VC1). This first planned outage should mainly take place in 2026.”

Construction work began in December 2007 on the third unit at the Flamanville site – where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013 but has faced a series of delays.

The first EPR units came online at Taishan in China, where unit 1 became the first EPR to enter commercial operation in 2018 followed by Taishan 2 in September 2019. In Europe, Olkiluoto 3 in Finland entered commercial operation in 2023, and two units are currently under construction at Hinkley Point C in the UK, with two more planned at Sizewell C.

   

  • Related Posts

    Key equipment installed in BREST-OD-300 turbine hall

    Concrete pouring began in May for the foundation of the turbine and generator for the reactor in Seversk in Russia’s Tomsk region, and Rosatom says that construction of the turbine…

    Concreting milestones at Chinese Hualong One units

    China National Nuclear Corporation (CNNC) said the last batch of concrete was poured for the inner dome of Zhangzhou unit 3 on 30 September. “This key milestone marks the completion…

    Have You Seen?

    Chevron, Shell and BP Pull Workers From the Gulf Ahead of Hurricane

    • October 7, 2026
    Chevron, Shell and BP Pull Workers From the Gulf Ahead of Hurricane

    Australia’s High Court Blocks Major Coal Mine Expansion Over Emissions

    • October 7, 2026
    Australia’s High Court Blocks Major Coal Mine Expansion Over Emissions

    QatarEnergy Secures $3 Billion Loan From Chinese Banks as LNG Exports Stall

    • October 7, 2026
    QatarEnergy Secures $3 Billion Loan From Chinese Banks as LNG Exports Stall

    Europe’s Fuel Squeeze Is Turning Into a Q3 Windfall for Equinor

    • October 7, 2026
    Europe’s Fuel Squeeze Is Turning Into a Q3 Windfall for Equinor

    How Much Gulf Production Will Isaias Knock Out?

    • October 7, 2026
    How Much Gulf Production Will Isaias Knock Out?

    Helix completes fifth helium well amid pause on Montana production

    • October 7, 2026
    Helix completes fifth helium well amid pause on Montana production

    Helix completes fourth helium well amid pause on Montana production

    • October 7, 2026
    Helix completes fourth helium well amid pause on Montana production

    Air Liquide sees structural healthcare trends boosting gas demand

    • October 7, 2026
    Air Liquide sees structural healthcare trends boosting gas demand

    US Crude Inventories Slide

    • October 7, 2026
    US Crude Inventories Slide

    Brent Back Above $100 as Houthis Hit Saudi Infrastructure

    • October 7, 2026
    Brent Back Above $100 as Houthis Hit Saudi Infrastructure