Delay in Flamanville 3 attaining full power

Monday, 4 August 2025

The long-delayed Flamanville 3 EPR reactor in Normandy in northern France is now expected to reach full power for the first time “before the end of autumn 2025”, EDF said. It had earlier been scheduled to reach full power in “summer 2025”.

Delay in Flamanville 3 attaining full power
The Flamanville EPR (Image: Alexis Morin and Antoine-Soubigou/EDF)

The 1630 MWe (net) pressurised water reactor was connected to the grid for the first time on 21 December 2024. At that time, EDF said that “in accordance with the startup operations, the phases of testing and of connection and disconnection to the grid will continue for several months … until the reactor reaches 100% power”. This had been scheduled for summer 2025.

However, EDF has now said: “After its next reconnection to the grid, the Flamanville 3 teams will continue the testing phase before commissioning with an objective to reach full capacity before the end of autumn 2025.

“At the end of this testing period, the unit is expected to be operated at 100% capacity until the first planned outage for maintenance and refuelling, called Visite Complète 1 (VC1). This first planned outage should mainly take place in 2026.”

Construction work began in December 2007 on the third unit at the Flamanville site – where two reactors have been operating since 1986 and 1987. The dome of the reactor building was put in place in July 2013 and the reactor vessel was installed in January 2014. The reactor was originally expected to start commercial operation in 2013 but has faced a series of delays.

The first EPR units came online at Taishan in China, where unit 1 became the first EPR to enter commercial operation in 2018 followed by Taishan 2 in September 2019. In Europe, Olkiluoto 3 in Finland entered commercial operation in 2023, and two units are currently under construction at Hinkley Point C in the UK, with two more planned at Sizewell C.

   

  • Related Posts

    US uranium production up again

    US mines produced 1,388,000 pounds U3O8 (534 tU) in 2025, up from 677,000 pounds U3O8 in 2024. The 2025 figure was the highest since 2016’s production of 2,545,000 pounds, according…

    Sogin begins re-encapsulation of uranium-thorium fuel

    Between 1968 and 1970, 84 elements of irradiated fuel from the uranium-thorium cycle from the Elk River experimental reactor in Minnesota, USA, were shipped to the Rotondella plant for reprocessing…

    Have You Seen?

    Oil Prices Dive as More Tankers Move Through Strait of Hormuz

    • June 27, 2026
    Oil Prices Dive as More Tankers Move Through Strait of Hormuz

    AMERICAN ENERGY SNAPSHOT: America’s Strategic Petroleum Reserve

    • June 27, 2026
    AMERICAN ENERGY SNAPSHOT: America’s Strategic Petroleum Reserve

    Magnolia Oil & Gas Is in Lead to Acquire WildFire for Over $4 Billion

    • June 27, 2026
    Magnolia Oil & Gas Is in Lead to Acquire WildFire for Over $4 Billion

    US Natural Gas Drops on Cooler Outlooks as July Contract Expires

    • June 27, 2026
    US Natural Gas Drops on Cooler Outlooks as July Contract Expires

    US Energy Firms Add Most Rigs in a Week Since June 2022, Baker Hughes Says

    • June 26, 2026
    US Energy Firms Add Most Rigs in a Week Since June 2022, Baker Hughes Says

    Chevron Eyes More Deals to Power US Data Centers

    • June 26, 2026
    Chevron Eyes More Deals to Power US Data Centers

    US Diesel Refining Economics Remain Firm Despite Iran War Truce

    • June 26, 2026
    US Diesel Refining Economics Remain Firm Despite Iran War Truce

    US Refining Capacity Fell by 263,000 Barrels Per Day in 2025, Says EIA

    • June 26, 2026
    US Refining Capacity Fell by 263,000 Barrels Per Day in 2025, Says EIA

    Qatar Offers First Crude Loadings to Buyers Since War Began

    • June 26, 2026
    Qatar Offers First Crude Loadings to Buyers Since War Began

    China’s Crude Imports Set to Hit Weakest Level Since 2016

    • June 26, 2026
    China’s Crude Imports Set to Hit Weakest Level Since 2016