Dismantling of Hamaoka 1 reactor under way

Hamaoka 1 and 2 are both boiling water reactors, starting up in 1973 and 1978, respectively. Unit 1 had a capacity of 540 MWe while unit 2’s capacity was 840 MWe. Chubu decided to close both units in January 2009 as they required expensive modifications to meet seismic standards imposed after the July 2007 Niigata Chuetsu offshore earthquake.

The utility submitted a decommissioning plan for Hamaoka 1 and 2 in June 2009, which was subsequently revised in September of that year. The overall plan divided the decommissioning of the two units into four stages. The first stage is for preparations for dismantling work at the units, while the second stage covers the dismantling and removal of equipment surrounding the reactors. The third stage is for the dismantling of the reactors themselves, while the fourth covers the demolition of buildings at both units.

The plan was approved by the Ministry of Economy, Trade and Industry in November 2009, when Chubu began stage 1 of the decommissioning programme.

Having completed stage two work at both units, on 18 December last year the Nuclear Regulation Authority approved Chubu’s application to move to the third stage of decommissioning at the units.

Chubu announced on 17 March that it had removed the upper lid of the pressure vessel of unit 2, marking the start of the dismantling of the reactor itself. As well as the reactor pressure vessel, the reactor internals and radiation shielding surrounding the vessel will be dismantled.

Hamaoka 1 and 2 are the first two commercial nuclear power reactors in Japan to enter the reactor dismantling phase.

Chubu plans to dismantle units 1 and 2 over a period of about 12 years, starting with the reactor of unit 2 first. The decommissioning of the two reactors is expected to be completed in fiscal 2042 after the reactor buildings are demolished.

   

  • Related Posts

    Construction of Chinese HTGR begins

    Xuwei Phase I was among 11 reactors approved by China’s State Council in August 2024. China National Nuclear Corporation (CNNC) plans to build two 1,208 MWe (net) Hualong One (HPR1000)…

    NAC to supply used fuel storage solution for Norway

    Norway holds about 16.5 tonnes of used fuel from six decades of operating nuclear research reactors. Much of it cannot be stored long term or disposed of in its current…

    Have You Seen?

    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    • November 6, 2026
    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    • November 6, 2026
    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    Europe’s Grid Spending Is Up 155% Since 2019

    • November 6, 2026
    Europe’s Grid Spending Is Up 155% Since 2019

    ADNOC Expands LNG Empire With Major New India Supply Deal

    • November 6, 2026
    ADNOC Expands LNG Empire With Major New India Supply Deal

    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    • November 6, 2026
    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    • November 6, 2026
    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    Viridi raises £2.2m to turn captured CO2 into chemicals

    • November 6, 2026
    Viridi raises £2.2m to turn captured CO2 into chemicals

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Oil Market Arrives at ‘Remarkable Destination’

    • November 6, 2026
    Oil Market Arrives at ‘Remarkable Destination’