Eletronuclear stresses benefits Angra 3 would bring Brazil

Tuesday, 18 February 2025

Eletronuclear stresses benefits Angra 3 would bring Brazil
Angra 3 is currently about 65% complete (Image: Eletronuclear)

The background
 

Brazil has two operating reactors – Angra 1 and Angra 2 – which generate about 3% of the country’s electricity. Work on the Angra 3 project – to feature a Siemens/KWU 1405 MW pressurised water reactor – began in 1984 but was suspended two years later, before construction began. The scheme was resurrected in 2006, with first concrete in 2010. However, amid a corruption probe into government contracts, construction of the unit was halted for a second time in 2015, when it was 65% complete.

The project resumed again in November 2022 – at the time of the project’s revitalisation, Eletronuclear’s aim was to start operations by the end of 2026. However, work halted again in April 2023 after disputes with the municipality of the City of Angra dos Reis over agreements relating to “environmental compensation” payments and also changes relating to the granted planning permission.

The company is currently awaiting a government decision on completing Angra 3 – it said in September that a study by Brazil’s National Bank for Economic and Social Development had concluded that the cost of abandoning construction of the part-built nuclear power unit could be about BRL21 billion (USD3.7 billion), which it says was about the same as the cost of completing it.

It says the unit’s generating capacity will be sufficient to supply 4.5 million inhabitants and also noted that about BRL800 million in Angra 3 equipment was used in Angra 2 and between BRL500-600 million in nuclear fuel, which had been initially purchased for Angra 3, had been used in Angra 2.

What Lycurgo has said

In an article posted on Eletronuclear’s website the company’s president said the project was not just about power generation, but was one which has “the potential to transform investments into social development, generate jobs on a large scale and boost the Brazilian economy” and cited a Getúlio Vargas Foundation study showing that every dollar invested in nuclear energy generated two dollars in GDP.

Lycurgo said that as many as 7000 jobs could be directly created during the project, as well as tens of thousands of indirect jobs. The supply chain would bring benefits to areas of Brazil much wider than the region around Angra dos Reis. He also cited the cost of cancelling the project and stressed the climate target benefits of nuclear energy.

“The future plant also offers a competitive projected tariff, currently estimated at BRL 653.31 (USD 114) per megawatt-hour, below the average cost of several thermal plants in the country. Its steady and clean energy is expected to provide security to the electrical system, reducing dependence on fossil fuel thermal plants and their high variable costs.

“Completing the project will be a milestone for Brazil’s development, not only in the energy sector, but also as a catalyst for economic and social transformations. This is a decision that creates jobs, boosts the economy and reinforces the country’s commitment to sustainable and technological solutions,” he said.

The National Energy Policy Council was considering whether or not to give the go-ahead to Angra 3 during a meeting taking place on Tuesday.

   

  • Related Posts

    Reactor vessel installed at third Zhangzhou unit

    The vessel – weighing about 316 tonnes – is the high strength steel cylinder that will house the reactor core and all associated components, including the reactor vessel internals which…

    Uzbek uranium mine enters commercial production

    “Pilot industrial operations at the deposit began in December 2024, and over two years of active work, the Company has reached the stage of commercial production,” said Djamal Sabakhonovich Fayzullayev,…

    Have You Seen?

    Brazil, German partners line up €2bn for 80,000-tonne green hydrogen project

    • April 23, 2026
    Brazil, German partners line up €2bn for 80,000-tonne green hydrogen project

    Analysis: Are key Middle East sites now at risk of renewed firepower?

    • April 23, 2026
    Analysis: Are key Middle East sites now at risk of renewed firepower?

    Video | From recovery to reuse: a more sustainable approach to helium

    • April 23, 2026
    Video | From recovery to reuse: a more sustainable approach to helium

    Pulsar Helium signs Michigan acreage deal for exploration

    • April 23, 2026
    Pulsar Helium signs Michigan acreage deal for exploration

    UK committee calls for tighter group-based PFAS regulation

    • April 23, 2026
    UK committee calls for tighter group-based PFAS regulation

    COMMENTARY: Iran War May Crush Oil Demand Today, But Send it Soaring Long Term: Bousso

    • April 23, 2026
    COMMENTARY: Iran War May Crush Oil Demand Today, But Send it Soaring Long Term: Bousso

    Oil Gains as US-Iran Talks stall, Hormuz Shipping Still Disrupted

    • April 23, 2026
    Oil Gains as US-Iran Talks stall, Hormuz Shipping Still Disrupted

    S&P Global Cuts 2026 Oil Demand Forecast by 700,000 Bpd Due to Iran War

    • April 23, 2026
    S&P Global Cuts 2026 Oil Demand Forecast by 700,000 Bpd Due to Iran War

    Chevron Restarts Wheatstone LNG Amid Global Gas Shortage

    • April 23, 2026
    Chevron Restarts Wheatstone LNG Amid Global Gas Shortage

    HSBC Downgrades Indian Equities Again as Oil Shock Deepens

    • April 23, 2026
    HSBC Downgrades Indian Equities Again as Oil Shock Deepens