First RITM-200 reactor unit manufactured for Leningrad nuclear icebreaker

Each of the Project 22220 nuclear icebreakers has two RITM-200s – pressurised water reactors with a thermal capacity of 175 MW, which converts to 30 MW at the propellers. It is 7.3 metres high with a diameter of 3.3 metres and an integral layout which its manufacturers say means it is lighter, more compact and 25 MW more powerful than previous generations used on nuclear-powered icebreakers. The service life is 40 years.

In addition to this one, which is the first for the Leningrad icebreaker under construction, a further 15 RITM reactor units are in various stages of production – for nuclear icebreakers, land-based SMR plants and floating power units.

The process of manufacturing the RITM-200 reactor unit concludes with test assembly, with all components assembled in their design positions “down to a thousandth of a millimetre” Rosatom said: “Successful completion of this operation allowed engineers to ensure the product was fully prepared for shipment and subsequent installation into the ship’s hull, ensuring reliable operation for at least the next 40 years”.

The second reactor unit for the Leningrad – whose keel was laid in January 2024 – is currently being prepared for hydraulic testing ahead of test assembly.

Anton Lebedev, head of ZiO-Podolsk, said: “Our company has already manufactured 10 RITM-200 reactor units and two more powerful RITM-400 units. Over the years, we have accumulated a colossal amount of knowledge and skills, and today we possess competencies unmatched anywhere else in the world.”

Background

There are currently a series of Project 22220 nuclear-powered icebreakers operating – the ArktikaSibirUral, the Yakutia, plus the Chukotka, which has beenundergoing mooring tests- and two under construction, the Leningrad and the Stalingrad at the Baltic Shipyard.

Within Rosatom’s machine-building division, Afrikantov OKBM is the designer, complete supplier, and manufacturer of the reactor internals for the RITM-200 and RITM-400 reactor units. Reactor vessel fabrication and test assembly are performed at ZiO-Podolsk.

The Project 22220 vessels are 173 metres long, 34 metres wide and with a height from the waterline to the mainmast of 57 metres. They are designed to break through ice up to three metres thick and have a speed of 22 knots in clear water. The first four have been escorting cargo ships along the Northern Sea Route for several years now.

There is also a larger nuclear-powered icebreaker under construction, the Rossiya, which will be the first of the proposed Project 10510 nuclear-powered icebreakers. It will feature two RITM-400 reactors for a propeller power of 120 MW. It will be able to penetrate ice up to 4.3 metres thick and clear a channel up to 50 metres wide. It has a reported construction target service date of 2030.

Nuclear-powered icebreakers are a key part of Russia’s plan to develop the Northern Sea Route, the shipping lane along its north coast which allows faster transport between Europe and Asia.

   

  • Related Posts

    Scottish sites suitable for nuclear new build, study says

    The Energy Secretary commissioned Great British Energy – Nuclear (GBE-N) in late 2025 to conduct a technical study into potential suitable areas in Scotland for possible new nuclear developments in…

    Commonwealth Fusion Systems joins UKAEA’s tritium blanket testing programme

    Future fusion power plants will rely on two hydrogen isotopes – deuterium and tritium – to produce energy. Deuterium can be readily extracted from seawater. Tritium, however, is scarce in…

    Have You Seen?

    Saudi Aramco Slashes July LPG Prices as Global Supply Swells

    • July 2, 2026
    Saudi Aramco Slashes July LPG Prices as Global Supply Swells

    Ukraine’s Drone Campaign Forces Russia to Buy Gasoline From India

    • July 2, 2026
    Ukraine’s Drone Campaign Forces Russia to Buy Gasoline From India

    KKR Makes Largest Ever Clean Energy Investment With $4.2B EDF Purchase

    • July 2, 2026
    KKR Makes Largest Ever Clean Energy Investment With $4.2B EDF Purchase

    Iran Exports Crude at 20% Premium Even as Unsold Barrels Pile Up at Sea

    • July 2, 2026
    Iran Exports Crude at 20% Premium Even as Unsold Barrels Pile Up at Sea

    EU Bows to Tech Lobby, Drops Ten-Year Renewables Rule for Data Centers

    • July 2, 2026
    EU Bows to Tech Lobby, Drops Ten-Year Renewables Rule for Data Centers

    Atlas Copco acquires Portuguese compressor distributor

    • July 2, 2026
    Atlas Copco acquires Portuguese compressor distributor

    Shell Aarhus biogas facility completes 18-month upgrade

    • July 2, 2026
    Shell Aarhus biogas facility completes 18-month upgrade

    Meritus expands in Colorado with HICO acquisition

    • July 2, 2026
    Meritus expands in Colorado with HICO acquisition

    Meritus expands Colorado with HICO acquisition

    • July 2, 2026
    Meritus expands Colorado with HICO acquisition

    California signs law recognising green hydrogen-fired power as renewables

    • July 2, 2026
    California signs law recognising green hydrogen-fired power as renewables