First unit at San’ao plant starts up

“At 12.21pm [local time] on 13 February, the first criticality control point of unit 1 of the San’ao nuclear power plant was officially released, and the unit began the reactor criticality operation phase,” China General Nuclear (CGN) said. “At 3.08 am on 14 February, the reactor of unit 1 of the San’ao nuclear power plant reached criticality for the first time, marking the official entry of the unit into power operation mode and taking a key step towards grid connection and power generation.”

In September 2020, the executive meeting of China’s State Council approved the construction of units 1 and 2 as the first phase of the San’ao plant. The NNSA issued a construction permit for the two units on 30 December that year and first concrete for unit 1 was poured the following day. The first concrete for San’ao 2 was poured on 30 December 2021. San’ao 1 and 2 are scheduled to begin supplying electricity in 2026 and 2027, respectively. 

The San’ao plant is the first nuclear power project in China’s Yangtze River Delta region to adopt the Hualong One reactor design. A total of six Hualong One units are planned for the San’ao site.

Upon completion, the project will provide over 54 TWh of electricity annually to Zhejiang Province and the Yangtze River Delta region, reducing standard coal consumption by over 16 million tonnes and carbon dioxide emissions by over 51 million tonnes annually, CGN noted.

The San’ao project marks the first Chinese nuclear power project involving private capital, with Geely Technology Group taking a 2% stake in the plant. CGN holds 46% of the shares of the project company Cangnan Nuclear Power, with other state-owned enterprises holding the remainder.

   

  • Related Posts

    India begins public consultation on SHANTI Bill rules

    The SHANTI Bill – to give it its full name, the Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Bill, 2025 – completed the legislative process in…

    Blue Energy, GE Vernova take gas-plus-nuclear collaboration to next stage

    In May, Blue Energy – a vertically integrated deployment platform for financeable, turnkey nuclear power plants compatible with leading reactor technology – announced it was joining up with GE Vernova…

    Have You Seen?

    China Added 200,000 Bpd to Crude Reserves in July Despite Hormuz Crisis

    • August 17, 2026
    China Added 200,000 Bpd to Crude Reserves in July Despite Hormuz Crisis

    Japan’s Oil Crisis Eases, But the Import Bill Keeps Climbing

    • August 17, 2026
    Japan’s Oil Crisis Eases, But the Import Bill Keeps Climbing

    Iraq-Syria Oil Pipeline to Bypass Hormuz Is 4 Years and $15 Billion Away

    • August 17, 2026
    Iraq-Syria Oil Pipeline to Bypass Hormuz Is 4 Years and $15 Billion Away

    China’s Renewables Boom Faces Record Clean Power Curtailments

    • August 17, 2026
    China’s Renewables Boom Faces Record Clean Power Curtailments

    Diversifying helium: Can dedicated projects reshape global supply?

    • August 17, 2026
    Diversifying helium: Can dedicated projects reshape global supply?

    Hormuz Tanker Traffic Slows to a Trickle

    • August 17, 2026
    Hormuz Tanker Traffic Slows to a Trickle

    India Lets Delayed Renewable Projects Pay to Keep Grid Access

    • August 17, 2026
    India Lets Delayed Renewable Projects Pay to Keep Grid Access

    Indian Oil Giant Secures U.S. License to Return to Venezuela

    • August 17, 2026
    Indian Oil Giant Secures U.S. License to Return to Venezuela

    Asian Refiners Seek Alternative Pickup Point for Saudi Crude

    • August 17, 2026
    Asian Refiners Seek Alternative Pickup Point for Saudi Crude

    India’s Chief Economic Adviser Calls for Return of E10 Petrol

    • August 17, 2026
    India’s Chief Economic Adviser Calls for Return of E10 Petrol