GERC Denies Extension Request For 3.948 MW Solar Project In Gujarat

Representational image. Credit: Canva

In a recent case before the Gujarat Electricity Regulatory Commission (GERC), Saanika Polytex Private Limited requested a six-month extension to commission its 3.948 MW solar power project along with the associated evacuation infrastructure. The company, registered as a generating company under the Electricity Act, 2003, cited several reasons for the delay, including challenges in land acquisition, changes in government banking policy, and delays in receiving approvals for the transmission line from various authorities. The petitioner described these delays as “inadvertent” and due to “unforeseen circumstances” beyond its control. The project was being developed under the Gujarat Renewable Energy Policy, 2023, and was governed by GERC’s Tariff Order dated August 31, 2024, which stipulated timelines for project completion.

Saanika Polytex faced significant hurdles in securing land for the project. The company initially planned to lease the land, but an internal dispute among the landowners forced them to purchase the land outright. This required a fresh application for non-agricultural land use. The first application was rejected in May 2024 due to a canal running through the property. After resolving land division issues, a new application was submitted in September 2024 and received approval in December 2024. The company also highlighted “regulatory uncertainty” as a factor in the delay, referencing a government clarification letter issued on August 31, 2024, which limited banking facilities to 30% of net consumption from the distribution company. This necessitated a re-evaluation of the project’s capacity and temporarily halted project activities.

The respondent, Dakshin Gujarat Vij Company Ltd (DGVCL), opposed the petition, arguing that the extension request lacked merit. DGVCL stated that the petitioner had not approached them for the payment of supervision charges for the distribution line, indicating the company was not prepared to proceed with the work. The respondent also pointed out that the project was to be completed within 12 months of receiving the Technical Feasibility Report on February 5, 2024, meaning the commissioning deadline was February 4, 2025. DGVCL noted that failure to meet these deadlines would normally lead to cancellation of connectivity and encashment of the bank guarantee. The respondent further argued that the reasons cited by Saanika Polytex were not valid “force majeure” events, and developers were responsible for adhering to the project timelines. DGVCL also mentioned that a sister concern of the petitioner had successfully commissioned a similar project within the prescribed timeline, suggesting that the deadlines were feasible.

GERC, in its final order dated September 16, 2025, rejected the petition. The commission found that the petitioner had not taken essential steps, including approaching DGVCL for distribution line development and payment of supervision charges. The commission also noted that the petitioner had not provided adequate documentation to substantiate claims regarding delays caused by land acquisition or government approvals. GERC concluded that the reasons provided by Saanika Polytex did not justify an extension, and the prayers for a six-month delay were dismissed.

The decision underscores the importance of timely project execution and adherence to regulatory timelines, highlighting that delays due to internal disputes or administrative issues may not be sufficient to grant extensions in renewable energy projects under Gujarat’s regulatory framework.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Hysata Begins Electrolyser Manufacturing Scale-Up in Australia With AI-Driven HysataFab Platform and 200 MW Annual Capacity

    Australian electrolyser manufacturer Hysata has launched HysataFab, an artificial intelligence (AI)-optimised manufacturing platform, and commissioned its first production line at the company’s 8,500-square-metre headquarters in Port Kembla, New South Wales.…

    Finnfund, Proparco Commit $33 Million to Colombia’s ERCO for Solar Expansion

    Finnfund, a Finnish impact investor, and Proparco, the French development finance institution, have committed a combined USD 33 million to Colombian integrated solar energy platform ERCO, with the investment supported…

    Have You Seen?

    Hysata Begins Electrolyser Manufacturing Scale-Up in Australia With AI-Driven HysataFab Platform and 200 MW Annual Capacity

    • September 26, 2026
    Hysata Begins Electrolyser Manufacturing Scale-Up in Australia With AI-Driven HysataFab Platform and 200 MW Annual Capacity

    Finnfund, Proparco Commit $33 Million to Colombia’s ERCO for Solar Expansion

    • September 26, 2026
    Finnfund, Proparco Commit $33 Million to Colombia’s ERCO for Solar Expansion

    B2U Begins Commercial Operation of 28 MWh Second-Life BESS Project in Texas

    • September 26, 2026
    B2U Begins Commercial Operation of 28 MWh Second-Life BESS Project in Texas

    GreenYellow Commissions 8 MWp of Rooftop Solar Across 18 Jerónimo Martins Sites in Portugal

    • September 26, 2026
    GreenYellow Commissions 8 MWp of Rooftop Solar Across 18 Jerónimo Martins Sites in Portugal

    Low Carbon Proposes 500 MW Solar and Battery Storage Project in West Oxfordshire

    • September 26, 2026
    Low Carbon Proposes 500 MW Solar and Battery Storage Project in West Oxfordshire

    Italy Pushes Refineries to Raise Fuel Output Amid Price Surge

    • September 25, 2026
    Italy Pushes Refineries to Raise Fuel Output Amid Price Surge

    India Weighs Mandatory Imported Coal Blending as Plant Stocks Crumble

    • September 25, 2026
    India Weighs Mandatory Imported Coal Blending as Plant Stocks Crumble

    EU Pressures UK to Match Its Tariffs on Chinese-Made Cars

    • September 25, 2026
    EU Pressures UK to Match Its Tariffs on Chinese-Made Cars

    Trump Advisers Study Impact of Diesel Export Ban

    • September 25, 2026
    Trump Advisers Study Impact of Diesel Export Ban

    CO2 and cheap power shape next wave of e-fuel projects

    • September 25, 2026
    CO2 and cheap power shape next wave of e-fuel projects