GERC Grants Partial Extension For 100 MW Solar Project Amid Dispute Over Delay And Force Majeure

Representational image. Credit: Canva

The Gujarat Urja Vikas Nigam Limited (GUVNL) filed a petition against Juniper Green Energy Pvt. Ltd. and other parties regarding a 100 MW solar power project under the Gujarat State Electricity Regulatory Commission (GERC). The case revolved around the Power Purchase Agreement (PPA) that was signed between GUVNL and Juniper Green Energy on August 26, 2021, for a tariff of Rs. 2.22 per unit. Juniper later requested a revision in the commissioning timeline, citing delays due to a Force Majeure event caused by global supply chain disruptions and increased module prices due to policy changes, especially the imposition of Basic Customs Duty (BCD) and the Approved List of Models and Manufacturers (ALMM) mandate.

Juniper argued that these circumstances were beyond their control and significantly impacted their ability to complete the project on time. As per the terms of the PPA, the scheduled commissioning date was set for August 25, 2022. However, Juniper sought an extension of 258 days, requesting the date to be moved to May 10, 2023. GUVNL, however, denied this extension and imposed penalties for the delay. The case then moved to GERC for adjudication.

During the hearings, Juniper submitted that the international module market experienced price hikes due to post-COVID supply issues and geopolitical tensions like the Russia-Ukraine war, which disrupted logistics and manufacturing. They also pointed to policy changes in India that added further financial and logistical challenges, including the imposition of BCD from April 2022 and ALMM compliance requirements, which limited the availability of approved modules. The company claimed they had taken all possible steps to mitigate delays, including signing contracts with module suppliers and starting project construction.

GUVNL, on the other hand, argued that the reasons cited did not qualify under the Force Majeure clause. It contended that the imposition of BCD and ALMM compliance was already known well in advance, and developers had been given ample time to plan accordingly. GUVNL maintained that the delay was due to commercial reasons and did not merit an extension of the commissioning date. It insisted that the PPA terms should be enforced strictly, including the imposition of liquidated damages and reduction of tariff for the capacity commissioned after the deadline.

After reviewing the arguments, GERC observed that while certain macroeconomic events like BCD and ALMM affected the renewable energy industry as a whole, the developer must prove specific adverse impacts on their project. The commission acknowledged that there were global issues, but also noted that Juniper had not provided clear documentary evidence of being directly and severely impacted. Ultimately, GERC ruled that Juniper was not entitled to the full extension sought. Instead, the commission granted a partial extension of 107 days, up to December 10, 2022, considering some delay due to unforeseen circumstances.

As a result, any capacity commissioned beyond that date would be subject to reduced tariffs and other penalties as per the PPA. The ruling highlighted the need for developers to plan with greater foresight and flexibility, especially in a rapidly evolving regulatory and economic landscape. The order set a precedent on how Force Majeure claims are evaluated in renewable energy contracts, stressing the importance of evidence and contract discipline.

 

  • Related Posts

    “Integrated Fluid Control Solutions Are Key to Reliable Hydrogen Applications”: Dongshin Oh of Bürkert Korea

    Hydrogen projects rely on precise control of pressure, flow and other process conditions. In this interview, conducted at World Hydrogen Expo 2026 in South Korea, Mr. Dongshin Oh, Account Sales…

    Just 7 Days to Go! Tamil Nadu Energy Expo 2026 Set to Bring Together 3,000+ Industry Professionals in Coimbatore  

    The countdown is on! With just 7 days to go, Coimbatore is gearing up to welcome the clean energy industry’s key players, innovators and decision-makers for Tamil Nadu Energy Expo…

    Have You Seen?

    Iran Rules Out Return of UN Nuclear Inspectors as U.S. War Talks Stall

    • November 13, 2026
    Iran Rules Out Return of UN Nuclear Inspectors as U.S. War Talks Stall

    India’s Road Fuel Demand Won’t Peak Until 2034

    • November 13, 2026
    India’s Road Fuel Demand Won’t Peak Until 2034

    Appalachian Power Investing Nearly $25 Billion For Gas and Coal Power Plants

    • November 13, 2026
    Appalachian Power Investing Nearly $25 Billion For Gas and Coal Power Plants

    Asian Refiners Turn Back to Gulf Oil Despite War Risks

    • November 13, 2026
    Asian Refiners Turn Back to Gulf Oil Despite War Risks

    Iran Says Gas Tanker Hit Mine in Strait of Hormuz

    • November 13, 2026
    Iran Says Gas Tanker Hit Mine in Strait of Hormuz

    Pakistan Scrambles for LNG as Winter Gas Crisis Deepens

    • November 13, 2026
    Pakistan Scrambles for LNG as Winter Gas Crisis Deepens

    COP31 declaration targets global scale-up of biogas and biomethane

    • November 13, 2026
    COP31 declaration targets global scale-up of biogas and biomethane

    Oil Prices Head for Second Weekly Loss Despite Fresh Middle East Attacks

    • November 13, 2026
    Oil Prices Head for Second Weekly Loss Despite Fresh Middle East Attacks

    Asian Airlines Face a $148-a-Barrel Fuel Gamble

    • November 13, 2026
    Asian Airlines Face a $148-a-Barrel Fuel Gamble

    India Seeks Private Investors for $910 Million Oil Reserve

    • November 13, 2026
    India Seeks Private Investors for $910 Million Oil Reserve