GERC Reviews Extension Request For 30 MW Hybrid Project Amid Regulatory And Supply Chain Delays In Gujarat

Representational image. Credit: Canva

Imandra Solar Private Limited filed Petition No. 2462 of 2025 before the Gujarat Electricity Regulatory Commission (GERC), seeking an extension of 120 days to complete the construction and commissioning of the evacuation infrastructure for its 30 MW wind-solar hybrid power project at Jafrabad, Amreli, Gujarat. The petitioner also requested that the Gujarat Energy Transmission Corporation (GETCO) be directed not to revoke its connectivity or encash its bank guarantees until the work is completed.

The project was to be completed within 12 months of receiving Stage-II connectivity approval from GETCO, dated 12 March 2024. Hence, the commissioning deadline was 11 March 2025. However, Imandra Solar cited several unforeseen and uncontrollable events that caused delays. These included delays in obtaining banking regulation clarity under the Green Energy Open Access (GEOA) Rules, delivery delays of crucial equipment like circuit breakers and transformers due to global supply chain disruptions, and right-of-way (ROW) issues with local landowners and farmers. Additional procedural delays included late approvals under Sections 68 and 164 of the Electricity Act and material drawing revisions.

GETCO, in its response, argued that the petitioner was aware of the project timelines and requirements and that delays in procurement and land acquisition were foreseeable risks, not force majeure. It further stated that the bank guarantees could be encashed if the project commissioning was not completed in time. GETCO maintained that any extension had to be granted strictly by the Commission as per the Hybrid Tariff Order and not by GETCO.

The Commission noted that many of the petitioner’s claims, such as the banking regulation confusion and supply chain issues, were legitimate and had been documented with follow-ups to government authorities. The Commission also observed that significant progress had been made, including completion of over 98% of the transmission line and partial work on the generator PSS and bay infrastructure.

Imandra Solar agreed to bear long-term transmission charges for 10% of the project capacity until commissioning and emphasized its intent to fulfill obligations. After hearing both parties, the Commission recognized the merit in the petitioner’s request and the industry-wide impact of the challenges cited. A decision on the extension and related reliefs will be based on the final findings in the order.

 

  • Related Posts

    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    Representational image. Credit: Canva For many years, hyperscalers assumed that data centre growth would increase gradually. But the sudden need for an additional 100–200 GW of global energy capacity by…

    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    Hoymiles successfully hosted its flagship StorageNext 2026 event on May 8, 2026, at Le Méridien, New Delhi, marking a significant milestone in advancing energy storage innovation in India. Aligned with…

    Have You Seen?

    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    • May 9, 2026
    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    • May 9, 2026
    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    Gautam Solar Reports ₹4406 Cr Revenue in FY26, Achieves Over 4X Growth

    • May 9, 2026
    Gautam Solar Reports ₹4406 Cr Revenue in FY26, Achieves Over 4X Growth

    South Bow Working to Secure Required Permitting for Canada-US Oil Pipeline Proposal

    • May 8, 2026
    South Bow Working to Secure Required Permitting for Canada-US Oil Pipeline Proposal

    US Drillers Add Oil and Gas Rigs for Third Week in a Row, Says Baker Hughes

    • May 8, 2026
    US Drillers Add Oil and Gas Rigs for Third Week in a Row, Says Baker Hughes

    Enbridge Sees Best North American Energy Investment Climate in Over a Decade

    • May 8, 2026
    Enbridge Sees Best North American Energy Investment Climate in Over a Decade

    Oil Jumps After Renewed US-Iran Fighting, Then Pares Gains

    • May 8, 2026
    Oil Jumps After Renewed US-Iran Fighting, Then Pares Gains

    Freeport LNG Plant in Texas Expected to Reduce Output for Maintenance in Coming Days, Sources Say

    • May 8, 2026
    Freeport LNG Plant in Texas Expected to Reduce Output for Maintenance in Coming Days, Sources Say

    Diamondback Bets on Wider WTI-Brent Gap Amid US Export Ban Concerns

    • May 8, 2026
    Diamondback Bets on Wider WTI-Brent Gap Amid US Export Ban Concerns

    India’s Inflation Accelerates as High Energy Prices Start to Bite

    • May 8, 2026
    India’s Inflation Accelerates as High Energy Prices Start to Bite