GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

Representational image. Credit: Canva

Gujarat State Electricity Corporation Limited (GSECL) has filed Petition No. 2620 of 2026 before the Gujarat Electricity Regulatory Commission (GERC) seeking approval for a project-specific tariff for its 25 MW solar photovoltaic project in Palitana, located in the Bhavnagar district of Gujarat. The project is part of a broader state government initiative aimed at utilizing wasteland areas near existing transmission infrastructure to generate affordable renewable energy.

The initiative was introduced in 2019, under which the Government of Gujarat provided key financial and land support to boost solar development. As part of the scheme, wasteland was allocated at a nominal lease rate for a period of 30 years, along with a 50 percent capital subsidy to developers. GSECL was assigned the responsibility to develop a total of 2,500 MW of solar capacity under this framework. The Palitana project represents one of the important developments under this program.

The engineering, procurement, and construction work for the project was awarded to Larsen & Toubro through a competitive bidding process. Initially, the project was planned with a higher DC capacity. However, due to land constraints at the site, the final installed capacity was adjusted to 25 MW AC and 28.18 MW DC.

According to the petition, the total capital cost of the project has been finalized at ₹296.33 crore. This includes the cost of equipment supply and construction, along with additional expenses such as pre-operative costs and head office supervision charges. The project was commissioned in two phases. The first phase of 5 MW became operational in May 2022, while the remaining 20 MW was commissioned in June 2022.

GSECL has signed a Power Purchase Agreement with Gujarat Urja Vikas Nigam Limited (GUVNL) for the sale of electricity generated from the plant. The agreement covers a period of 25 years. As per the terms of the PPA, the tariff for the project will be determined by GERC using a cost-plus approach. This method will take into account the 50 percent capital subsidy provided by the state government.

The petition has been filed under the provisions of the Electricity Act 2003, specifically Sections 62 and 86, which give the state electricity regulatory commissions the authority to determine tariffs for electricity generation and supply. The filing also follows an earlier direction from the commission, which required GSECL to submit a project-specific tariff petition after the plant achieved commercial operation.

Through this petition, GSECL has requested GERC to approve the final project cost and determine a fixed tariff for the electricity that will be supplied to GUVNL from the Palitana solar project.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    Representational image. Credit: Canva The Northern Power Corporation is taking major steps to stabilize the electricity supply across Northern Vietnam as demand is expected to grow sharply in 2026. With…

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    Representational image. Credit: Canva Solar Energy Corporation of India Limited has announced a new tender to select Solar Project Developers (SPDs) for setting up 4455 kW of grid-connected rooftop solar…

    Have You Seen?

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    • April 10, 2026
    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates

    • April 10, 2026
    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates