HERC Cancels Connectivity For 50 MW Solar Project Due To Captive Status Dispute

Representational image. Credit: Canva

AVAADA Green HN Project Pvt. Ltd. filed a petition with the Haryana Electricity Regulatory Commission (HERC) challenging the cancellation of in-principle feasibility and final connectivity approvals for its 50 MW solar power project at the 132/33 kV Adampur substation in Hisar, Haryana. The petitioner argued that the cancellation by Haryana Vidyut Prasaran Nigam Ltd. (HVPNL) and the insistence by Dakshin Haryana Bijli Vitran Nigam Ltd. (DHBVNL) on submitting captive status documents were arbitrary and contrary to the Electricity Act, 2003, and Electricity Rules, 2005.

The petitioner had applied in 2018 for connectivity under the captive model and submitted the necessary undertaking in 2019. In-principle feasibility was granted in May 2019, and final connectivity in September 2021. However, AVAADA later sought to sell power to Haryana Discoms at a cost-plus tariff. When this proposal was rejected in 2022, the petitioner reverted to the captive model and requested the continuation of connectivity accordingly.

HVPNL canceled final connectivity in March 2024, citing non-fulfillment of conditions tied to power sale agreements. It issued a final notice in November 2024 to submit documents proving captive status. Despite further communication from AVAADA in December 2024 requesting more time, HVPNL canceled the in-principle feasibility in March 2025, stating prolonged non-compliance.

The petitioner argued that the determination of captive status is only required after commissioning, as per the Electricity Rules, and not at the connectivity stage. It also claimed that it never applied under the Haryana Solar Policy and hence should not be bound by HAREDA guidelines. However, HVPNL produced documentation showing AVAADA’s application to HAREDA under the Solar Policy, thereby negating this claim.

The Commission examined whether the connectivity procedure and Solar Policy were applicable, and whether conditions for verifying captive status at the connectivity stage violated the Act and Rules. It upheld the mandatory nature of the Commission-approved connectivity procedure and held that the Solar Policy, along with HAREDA’s guidelines, applied to the project.

Ultimately, the Commission found that AVAADA was in breach of the terms and conditions linked to connectivity, including shareholding requirements and procedural compliance under the Solar Policy. It ruled that the cancellation of both final connectivity and in-principle feasibility by HVPNL was lawful and based on valid grounds. The petition was dismissed.

 

  • Related Posts

    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    Representational image. Credit: Canva For many years, hyperscalers assumed that data centre growth would increase gradually. But the sudden need for an additional 100–200 GW of global energy capacity by…

    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    Hoymiles successfully hosted its flagship StorageNext 2026 event on May 8, 2026, at Le Méridien, New Delhi, marking a significant milestone in advancing energy storage innovation in India. Aligned with…

    Have You Seen?

    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    • May 9, 2026
    Wood Mackenzie Says Rising Power Demand In Data Centres Will Push Emissions Higher But Accelerate Direct Decarbonisation Efforts

    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    • May 9, 2026
    Following Its Microinverter Breakthrough, Hoymiles Showcases Advanced Utility & Energy Storage Portfolio at StorageNext 2026 in New Delhi

    Gautam Solar Reports ₹4406 Cr Revenue in FY26, Achieves Over 4X Growth

    • May 9, 2026
    Gautam Solar Reports ₹4406 Cr Revenue in FY26, Achieves Over 4X Growth

    South Bow Working to Secure Required Permitting for Canada-US Oil Pipeline Proposal

    • May 8, 2026
    South Bow Working to Secure Required Permitting for Canada-US Oil Pipeline Proposal

    US Drillers Add Oil and Gas Rigs for Third Week in a Row, Says Baker Hughes

    • May 8, 2026
    US Drillers Add Oil and Gas Rigs for Third Week in a Row, Says Baker Hughes

    Enbridge Sees Best North American Energy Investment Climate in Over a Decade

    • May 8, 2026
    Enbridge Sees Best North American Energy Investment Climate in Over a Decade

    Oil Jumps After Renewed US-Iran Fighting, Then Pares Gains

    • May 8, 2026
    Oil Jumps After Renewed US-Iran Fighting, Then Pares Gains

    Freeport LNG Plant in Texas Expected to Reduce Output for Maintenance in Coming Days, Sources Say

    • May 8, 2026
    Freeport LNG Plant in Texas Expected to Reduce Output for Maintenance in Coming Days, Sources Say

    Diamondback Bets on Wider WTI-Brent Gap Amid US Export Ban Concerns

    • May 8, 2026
    Diamondback Bets on Wider WTI-Brent Gap Amid US Export Ban Concerns

    India’s Inflation Accelerates as High Energy Prices Start to Bite

    • May 8, 2026
    India’s Inflation Accelerates as High Energy Prices Start to Bite