KSERC Approves Technopark’s Capital Investment Proposals For Infrastructure And Solar Projects In Kerala

Representational image. Credit: Canva

M/s Technopark, a deemed distribution licensee in Thiruvananthapuram, filed a petition seeking approval for its capital investment proposals for the fiscal year 2023-24. The Kerala State Electricity Regulatory Commission (KSERC) held a hearing on this matter, with representatives from both Technopark and Kerala State Electricity Board Limited (KSEB Ltd) present.

Technopark’s petition proposed an investment of ₹517.95 lakh, with ₹213.63 lakh to be funded through grants and the remaining ₹304.32 lakh from its funds. The main projects outlined in the petition included upgrading the 11 kV power distribution system at Phase 1, installing rooftop grid-connected solar PV plants, and setting up a solar plant above a hybrid electric vehicle (EV) charging station.

A large portion of the proposed investment, ₹434.24 lakh, was intended for the revamp of the 11 kV power distribution system at Technopark Phase 1. Technopark emphasized the need for the upgrade due to the aging infrastructure, increased power demand from new developments, and the goal to ensure a reliable, uninterrupted power supply. KSEB Ltd acknowledged the problems with the existing system, especially frequent cable faults, and suggested methods such as planned trenching for cable laying and monitoring the usage of capital works. KSERC provisionally approved this cost, but with a note to align it with market rates and directed Technopark to secure the government grant balance already approved.

Technopark also proposed the installation of solar PV plants. One of the key proposals was for a 35kWp rooftop grid-connected solar PV plant at the Technocity campus, estimated at a cost of ₹13.63 lakh. This project was aimed at meeting the Renewable Purchase Obligation (RPO). KSEB Ltd noted that the entire expenditure could be covered by government grants. KSERC provisionally approved the cost, urging Technopark to ensure it aligns with MNRE’s benchmark rates for such projects.

Another proposal from Technopark involved installing a 15.5 kWp solar plant above a hybrid electric vehicle charging station at Phase 1, with an estimated cost of ₹6.45 lakh. Technopark explained that this project would not only help meet the RPO but also encourage EV usage and support the growth of the electric vehicle charging business. KSEB Ltd again pointed out that government funding could cover the entire cost. The Commission provisionally approved this proposal as well, again requiring it to be in line with MNRE rates.

Technopark also sought approval for two other solar PV plants: a 25 kWp On-Grid Solar PV Plant at the Park Centre Building and a 78 kWp On-Grid Solar PV plant on the Pump House water tank. The total cost for these two projects was ₹63.63 lakh. KSERC noted that the rates used for estimating the cost were higher than the MNRE-approved benchmark rates. The Commission approved the proposal but only at the MNRE benchmark rate.

In its final order, the Commission directed Technopark to carry out the projects through competitive bidding. It also instructed Technopark to fund capital investments, excluding grants, from accumulated regulatory surpluses. Technopark was asked to remove any replaced assets from its fixed asset register and submit detailed accounts, including tender documents and bills, during the truing-up process. Furthermore, all approved assets must be geo-tagged and properly documented.

 

  • Related Posts

    Pentagreen Capital and Candi Solar Sign US$50 Million Deal for 400 MW Solar and BESS Projects in India

    Pentagreen Capital and Candi Solar have signed a US$50 million financing partnership to support the development of approximately 400 MWp of solar power and battery energy storage projects across India.…

    Zambia–Tanzania 2,300 km Power Interconnector Targeted For Commissioning By 2029

    Zambia is expected to commission a major high-voltage electricity transmission project connecting the country with Tanzania and Kenya by the second quarter of 2029. The 2,300-kilometre Zambia-Tanzania interconnector is designed…

    Have You Seen?

    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    • November 6, 2026
    Energy Aspects Slashes Forecast of China’s November Diesel Exports

    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    • November 6, 2026
    FGE NexantECA Sees Slim Chance of U.S.-Iran Deal

    Europe’s Grid Spending Is Up 155% Since 2019

    • November 6, 2026
    Europe’s Grid Spending Is Up 155% Since 2019

    ADNOC Expands LNG Empire With Major New India Supply Deal

    • November 6, 2026
    ADNOC Expands LNG Empire With Major New India Supply Deal

    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    • November 6, 2026
    India’s HPCL Struggles to Secure Oil Tankers as Hormuz Risks Persist

    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    • November 6, 2026
    Asia’s Fuel Oil Market Signals Hopes of U.S.-Iran De-Escalation

    Viridi raises £2.2m to turn captured CO2 into chemicals

    • November 6, 2026
    Viridi raises £2.2m to turn captured CO2 into chemicals

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Colorado awards Vycarb $2.7m for carbon management tech

    • November 6, 2026
    Colorado awards Vycarb $2.7m for carbon management tech

    Oil Market Arrives at ‘Remarkable Destination’

    • November 6, 2026
    Oil Market Arrives at ‘Remarkable Destination’