Ministry of Power Amend Guidelines for Tariff-Based Bidding in Firm and Dispatchable Power from Grid-Connected RE Projects with ESS

Representational image. Credit: Canva

The guidelines for tariff-based competitive bidding to procure firm and dispatchable power from grid-connected renewable energy projects with energy storage systems were first notified on June 9, 2023. These guidelines were later amended on November 17, 2023, and again on February 2, 2024. The Ministry of Power has now introduced further amendments to these guidelines, affecting several key clauses.

One of the changes is in Clause 3.1.1(b), which now states that any deviations in the draft bidding documents, such as the Request for Selection (RfS), Power Purchase Agreement (PPA), and Power Sale Agreement (PSA), must be approved by the appropriate commission. However, if deviations were already approved by the government before these amendments, fresh approval will not be necessary. It is also clarified that providing detailed provisions in the project agreements in line with the guidelines will not be considered deviations.

A new clause, 3.3, has been added, allowing procurers to specify the sub-stations in the inter-state or intra-state transmission system where developers must connect their renewable power projects. This change aims to bring more clarity to location-specific bids.

Section 7.6(b) has been modified to address the consequences of generators failing to maintain the committed Capacity Utilization Factor (CUF). If a generator does not meet the minimum CUF for two consecutive years, excluding the first contract year, it will be considered in default. In such cases, the yearly minimum CUF obligation will be reduced to the average CUF of the two default years, and the generator must pay lump sum damages for up to 24 months or the remaining PPA period. If the generator fails to pay, the PPA may be terminated, and additional damages will be applicable.

Clause 7.7 has been revised to align the provisions of change in law with the Electricity (Timely Recovery of Costs due to Change in Law) Rules, 2021. The term “Change in Law” will now apply to events occurring within seven days before the last date of bid submission.

Clause 9.2.1 has been modified to ensure a balance between competition and project implementation feasibility. Procurers may specify technical criteria after assessing how many developers can meet them. Additionally, developers will be required to install GPS-enabled automatic weather stations and comply with cybersecurity regulations set by the central government.

A new Clause 10.3 states that the signing of the PPA and PSA should generally be completed within 30 days from the Letter of Award (LoA) issuance. This period can be extended up to 12 months, but beyond that, the LoA will be canceled. It is also clarified that any extension granted by the procurer will not be considered a deviation from the guidelines.

Clause 11.4 has been revised, making it mandatory for distribution licensees or intermediary procurers to approach the appropriate commission within 30 days of discovering the tariffs through competitive bidding.

New provisions have been introduced for earnest money deposits and performance bank guarantees. Insurance surety bonds can now be used as an alternative to bank guarantees, and other instruments approved under the General Financial Rules may also be accepted.

Finally, Clause 12.3 has been updated to clarify that performance bank guarantees can be encashed to recover damages or dues from the generator in case of default under the PPA. The recovered amount will be credited to the Payment Security Fund. Once the power supply begins, the guarantee will be returned within 45 days. In cases of partial power supply commencement, the corresponding guarantee will also be released within 45 days.

 

  • Related Posts

    Weekly Tech Insights: LONGi Advances Hi-MO X10 & Hi-MO 9, Growatt Explores Floating Solar, JinkoSolar Expands Sunny 365 Solar-Storage, Hoymiles Powers Rooftops with MIT-5000-8T

    LONGi and AGS International have deployed Hi-MO X10 645 W modules for a grid-connected warehouse rooftop project in Riyadh, delivering approximately 200 kWp of installed solar capacity. The technology focus…

    Green Energy Stocks Show Mixed Performance As Indian Markets Trade Flat (21 August 2026)

    The Indian stock market remained largely range-bound on August 21, 2026, with benchmark indices showing little movement. The S&P BSE SENSEX remained steady at 77,540.83 points, while the NIFTY 50…

    Have You Seen?

    India Boosts Battery Investment to Cut Solar Power Waste

    • August 24, 2026
    India Boosts Battery Investment to Cut Solar Power Waste

    Iranian Oil Supply to China Is Rapidly Drying Up

    • August 21, 2026
    Iranian Oil Supply to China Is Rapidly Drying Up

    Nigeria Eyes $50 Billion Offshore Oil and Gas Investment Boom

    • August 21, 2026
    Nigeria Eyes $50 Billion Offshore Oil and Gas Investment Boom

    East African Nations Offered 30% Share of Dangote’s Kenya Mega-Refinery

    • August 21, 2026
    East African Nations Offered 30% Share of Dangote’s Kenya Mega-Refinery

    Saudi Oil Exports from Mediterranean Soar with Shuttles North to Avoid Houthis

    • August 21, 2026
    Saudi Oil Exports from Mediterranean Soar with Shuttles North to Avoid Houthis

    Ukrainian Drone Attack Hits Lukoil Refinery Deep in Russia 

    • August 21, 2026
    Ukrainian Drone Attack Hits Lukoil Refinery Deep in Russia 

    China’s Teapots Look Beyond Iranian Oil amid U.S. Blockade

    • August 21, 2026
    China’s Teapots Look Beyond Iranian Oil amid U.S. Blockade

    Court Upholds Trump Admin Order to Restart SYU

    • August 21, 2026
    Court Upholds Trump Admin Order to Restart SYU

    Whisky waste-to-biomethane plant to meet 4% of Scotland’s gas demand

    • August 21, 2026
    Whisky waste-to-biomethane plant to meet 4% of Scotland’s gas demand

    CCS projects could put pressure on US Midwest CO2 supply

    • August 21, 2026
    CCS projects could put pressure on US Midwest CO2 supply