New Korean reactor cleared for start up

In January 2014, the government authorised construction of two APR1400 units as Saeul units 3 and 4 (formerly known as Shin Kori 5 and 6). Construction was originally scheduled to start in September 2014, but was then delayed. The regulator issued a construction licence in June 2016, and site works began immediately. Construction of unit 3 commenced in April 2017. However, following the change in government in June 2017, Korea Hydro & Nuclear Power (KHNP) decided to suspend work for three months. In October 2017, a government-organised committee voted 59.5% in favour of resuming construction of the two units. The committee stated that stability of power supply had been cited as a primary reason for the choice in survey responses. In September 2018, construction of unit 4 commenced.

Prior to the delay, commercial operation of the units was due in March 2021 and March 2022, respectively. In late December 2025 the Nuclear Safety and Security Commission (NSSC) issued an operating licence for Saeul 3, with fuel loading and approximately eight months of testing to follow. Commercial operation is expected around August 2026. Saeul 4 is expected to follow in late 2026.

“Since the operating licence was issued last year, the NSSC has been conducting pre-operational inspections (5 stages) on Saeul unit 3,” the regulator said. “During this process, inspections were conducted on items that must be performed before criticality, such as nuclear fuel loading inspections and high-temperature functional tests. As a result, it was confirmed that reactor criticality can be safely achieved.”

The NSSC said it plans to finally confirm the safety of the unit by conducting follow-up inspections, including power increase tests, from the time Saeul 3 achieves first criticality – a sustained chain reaction – until it enters commercial operation.

Once commercially operational, Saeul 3 will account for about 1.7% of South Korea’s total power generation and 37% of Ulsan’s electricity demand.

South Korea has four operational APR1400 units – Saeul units 1 and 2 (formerly Shin Kori 3 and 4) and Shin Hanul units 1 and 2, plus the APR1400s under construction as Saeul units 3 and 4. Four APR1400 units have also been built at the Barakah nuclear power plant in the UAE, which are all now in commercial operation.

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    Trump Insists Iran Has Agreed to Nuclear Inspections

    • June 23, 2026
    Trump Insists Iran Has Agreed to Nuclear Inspections

    Will US and International Sanctions on Iran be Lifted?

    • June 23, 2026
    Will US and International Sanctions on Iran be Lifted?

    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    • June 23, 2026
    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    • June 23, 2026
    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    • June 23, 2026
    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    • June 23, 2026
    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    • June 23, 2026
    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    Europe’s Battery Storage Installations Set to Quadruple by 2030

    • June 23, 2026
    Europe’s Battery Storage Installations Set to Quadruple by 2030