NRC extends Project Ike review timetable

Earlier this year the US Nuclear Regulatory Commission (NRC) formally accepted for review Orano Enrichment USA’s application for a licence to authorise possession and use of special nuclear material at the proposed Project IKE uranium enrichment facility. The regulator set an accelerated 12-month review schedule, eyeing completion of the process by 30 April 2027.

The revised schedule is set out in dated 27 October after the company asked for more time to submit responses to Requests for Additional Information – or RAIs – issued by the regulator in relation to the application. 

Orano USA announced in September 2024 its selection of Oak Ridge in Tennessee as its preferred site for a new centrifuge uranium enrichment facility. After pre-application engagement with the NRC, the company submitted its environmental report for the project in January this year, and its application in March.

The licensing effort leverages the licensing application from the Eagle Rock Enrichment Facility, a centrifuge plant Orano’s forerunner company Areva had previously planned to build at Idaho Falls. The NRC issued a licence in 2011 for Eagle Rock, but the licence was terminated – at the request of the company – in 2018.

“The original accelerated review schedule was based on assumptions that Orano would provide complete and timely responses to NRC’s RAIs and provide a detailed crosswalk comparing the Project IKE application to the previously approved Eagle Rock Enrichment Facility licence which Orano asserted would share some similarities to Project IKE,” the NRC said in its 27 October letter to the company. “The crosswalk was not provided, which limited the NRC review team’s ability to leverage the precedent from the Eagle Rock safety evaluation. Additionally, the staff has found in its review that there are limited similarities between the Project Ike and Eagle Rock applications that could be leveraged to expedite its review.”

Orano has told the NRC it expects to submit all RAI responses by 14 December, and, based on Orano’s revised response schedule, the NRC says it now anticipates completing the review of the application by 20 June 2027. The regulator says its staff will “continue to perform review activities and concurrence processes in parallel and will maintain accelerated review schedules for individual technical areas” as far as is practicable.

An Orano spokesperson has told the American Nuclear Society’s Nuclear News that the extended review time is not expected to delay the start of enrichment operations, expected in 2031.

   

  • Related Posts

    Newcleo, Curio team up for recycled nuclear fuel supply

    The agreement establishes a framework for the evaluation of commercial arrangements to provide Newcleo with a proliferation-resistant feedstock of recycled nuclear materials for its mixed-oxide (MOX) fuel fabrication activities and…

    Work programme being planned for next year, as Paks II audit continues

    First concrete was poured for the first new unit in February, before the Hungarian elections saw a change of government. In May, new Hungarian Prime Minister Peter Magyar’s government announced…

    Have You Seen?

    Goldman Sachs Warns of Massive Oil Glut in 2027

    • November 16, 2026
    Goldman Sachs Warns of Massive Oil Glut in 2027

    Iran Claims Two More Oil Tankers Hit Mines in Strait of Hormuz

    • November 16, 2026
    Iran Claims Two More Oil Tankers Hit Mines in Strait of Hormuz

    New North Sea Gas Supply Comes Online Amid Growing Political Backlash

    • November 16, 2026
    New North Sea Gas Supply Comes Online Amid Growing Political Backlash

    U.S. LNG Flows Hit Record High as Global Gas Supply Crisis Deepens

    • November 16, 2026
    U.S. LNG Flows Hit Record High as Global Gas Supply Crisis Deepens

    Germany backs €24m initiative to turn CO2 into industrial raw materials

    • November 16, 2026
    Germany backs €24m initiative to turn CO2 into industrial raw materials

    EIA Now Sees Global Oil Glut in Q4

    • November 16, 2026
    EIA Now Sees Global Oil Glut in Q4

    Helium Evolution targets new Saskatchewan discoveries in CAD $3m programme

    • November 16, 2026
    Helium Evolution targets new Saskatchewan discoveries in CAD $3m programme

    Oil Prices Fall as Fears of a Global Supply Glut Return

    • November 16, 2026
    Oil Prices Fall as Fears of a Global Supply Glut Return

    China Turns to Iraqi Oil as U.S. Blockade Chokes Iranian Supply

    • November 16, 2026
    China Turns to Iraqi Oil as U.S. Blockade Chokes Iranian Supply

    Video | Could natural gas processing unlock new CO2 supply?

    • November 16, 2026
    Video | Could natural gas processing unlock new CO2 supply?