Refurbished Bruce unit back on the grid

Major Component Replacement – or MCR – involves removing and replacing key reactor components including steam generators, pressure tubes, calandria tubes and feeder tubes and adding 30-35 years to the reactor’s operating life. Bruce 3 was taken offline to begin its MCR outage in March 2023, with Bruce Power announcing the completion of the construction phase of the project in February.

Regulatory hold points are mandatory checkpoints beyond which reactor operation cannot proceed without approval from the Commission. The Canadian Nuclear Safety Commission (CNSC) applies four hold points to reactor refurbishment projects: loading fuel into the reactor; removing the guaranteed shutdown state and starting the reactor; exceeding 1% full power; and exceeding 35% full power.

Ramzi Jammal, Executive Vice-President and Chief Regulatory Operations Officer at the Canadian Nuclear Safety Commission, notified the company on 2 June of the regulator’s decision to remove the final regulatory hold point after CNSC staff confirmed that the company had met all of its commitments and remained in compliance with its licence conditions. 

Bruce Power Director, Community & External Affairs Maggie Tieman confirmed that the unit has been restarted. “Today at 1:34 a.m. Unit 3 was successfully synchronised to Ontario’s electricity grid. As we move forward, we will continue power ascension in Unit 3 and complete the remaining testing and approvals required for commercial operation,” she told World Nuclear News.

The Bruce site comprises eight operable Candu reactors divided equally between two plants: units 1-4 make up Bruce A, and units 5-8 are Bruce B. At Bruce A, units 1 and 2 have already been refurbished, returning to operations in 2012. Unit 4 is currently undergoing an MCR which began in February 2025. The four units making up Bruce B are also being refurbished: unit 6’s MCR was completed in 2024; units 5 is expected to begin its MCR later this year, according to the CNSC’s timeline, with overlapping MCR projects scheduled to begin at units 7 and 8 in 2028 and 2030 respectively.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    Middle East Oil Tankers Are Going Dark for Longer

    • August 14, 2026
    Middle East Oil Tankers Are Going Dark for Longer

    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    • August 14, 2026
    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    • August 14, 2026
    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    • August 14, 2026
    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    Holcim UAE starts cement carbon capture pilot project

    • August 14, 2026
    Holcim UAE starts cement carbon capture pilot project

    Qatar Ras Laffan train five ‘goes offline’

    • August 14, 2026
    Qatar Ras Laffan train five ‘goes offline’

    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    • August 14, 2026
    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn