Renewed Bruce 3 back in service

The Major Component Replacement (MCR) which the Candu unit has undergone saw robotic tools used on a reactor face to rebuild a Candu reactor for the first time. The project also saw Bruce Power and its partners set a Candu refurbishment record for calandria tube removal by completing it 11 days ahead of schedule.

Unit 3 began its Major Component Replacement outage in March 2023 and was originally scheduled to return to service in January 2027. It was reconnected to the grid in the early hours of 3 June, since when Bruce Power continued with power ascension and the final testing and approvals required for commercial operation. Its early completion “is the most expedient refurbishment in Ontario to date and reinforces the province’s position as a global leader in nuclear energy”, according to Ontario’s Ministry of Energy and Mines.

“The Unit 3 MCR project was delivered safely and successfully, continuing Ontario’s track record of delivering nuclear refurbishments on time, on budget and with quality by a skilled workforce, industry partners and a robust Made-in-Canada supply chain,” Bruce Power said.

The refurbishment means the unit’s life has been extended by more than three decades. 

The Major Component Replacement projects are part of Bruce Power’s Life-Extension Program to refurbish Bruce units 3-8, to enable the site to operate into the 2060s (units 1 and 2 have already been refurbished). Unit 6’s MCR was completed ahead of schedule and under budget in 2024, and, with unit 4’s MCR already under way, this represents the midway point for the programme, the company said. Each MCR builds on those that have gone before: unit 3’s successful return to service, with key phases completed ahead of schedule, has been supported by innovation and continuous improvement; record-setting execution in critical work programmes, reflecting advancements in tooling, planning and workforce expertise; and ongoing improvements in efficiency and quality driven by lessons learned from earlier refurbishments.

Provisions built into Bruce Power’s refurbishment agreement with Ontario’s Independent Electricity System Operator will ensure that Ontario’s citizens benefit from savings realised during the Life-Extension Program and operation of the Bruce Nuclear Generating Station. Bruce said it is expecting to return about CAD150 million (about USD108 million) to the Independent Electricity System Operator as a result of its performance. 

“With unit 3 now back in service and providing safe, clean, reliable and affordable electricity to the province, we continue to demonstrate that large-scale nuclear projects in Ontario can be delivered safely, efficiently, and with real long term financial benefits for ratepayers,” said Eric Chassard, President and Chief Executive Officer, Bruce Power. “This achievement reflects the dedication of our workforce, our skilled trades partners, and the strength of our made-in-Canada nuclear industry.”

Bruce Power’s Life‑Extension Program directly and indirectly supports some 22,000 jobs annually and contributes billions of dollars each year to Ontario’s economy.

“When Ontario successfully completed the world’s largest nuclear refurbishment at Darlington ahead of schedule and under budget, critics said it couldn’t be done again. Yet again, we are proving them wrong,” the province’s Minister of Energy and Mines Stephen Lecce said.
 

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    Middle East Oil Tankers Are Going Dark for Longer

    • August 14, 2026
    Middle East Oil Tankers Are Going Dark for Longer

    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    • August 14, 2026
    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    • August 14, 2026
    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    • August 14, 2026
    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    Holcim UAE starts cement carbon capture pilot project

    • August 14, 2026
    Holcim UAE starts cement carbon capture pilot project

    Qatar Ras Laffan train five ‘goes offline’

    • August 14, 2026
    Qatar Ras Laffan train five ‘goes offline’

    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    • August 14, 2026
    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn